FAR and DFARS › FAR Part 17: Special Contracting Methods › Subpart 17.2
FAR 17.202 Use of options.
The codified text (eCFR, as of 2026-10-02). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule.
In plain English
This section explains when a contracting officer may include options in a contract. Options are generally allowed when it is in the Government's interest, but the section lists situations where options should normally not be used or must not be used. It also allows options in service contracts when continuity of operations is needed.
Applies to: Contracting officers using sealed bidding or negotiation
What it requires
- When using sealed bidding, make a written determination that there is a reasonable likelihood the options will be exercised before including the provision at 52.217-5 in the solicitation.
- Do not employ options if the contractor will incur undue risks, market prices are likely to change substantially, or the option represents known firm requirements for which funds are available (with limited exceptions).
Key terms: options · sealed bidding · contracting by negotiation · indefinite quantity contract · requirements contract
Written by AI from this section's text. A guide, not legal advice: the text below rules.
The text
(a) Subject to the limitations of paragraphs (b) and (c) of this section, for both sealed bidding and contracting by negotiation, the contracting officer may include options in contracts when it is in the Government's interest. When using sealed bidding, the contracting officer shall make a written determination that there is a reasonable likelihood that the options will be exercised before including the provision at 52.217-5, Evaluation of Options, in the solicitation. (See 17.207(f) with regard to the exercise of options.)
(b) Inclusion of an option is normally not in the Government's interest when, in the judgment of the contracting officer—
(1) The foreseeable requirements involve—
(i) Minimum economic quantities (i.e., quantities large enough to permit the recovery of startup costs and production of the required supplies at a reasonable price); and
(ii) Delivery requirements far enough into the future to permit competitive acquisition, production, and delivery.
(2) An indefinite quantity or requirements contract would be more appropriate than a contract with options. However, this does not preclude the use of an indefinite quantity contract or requirements contract with options.
(c) The contracting officer shall not employ options if—
(1) The contractor will incur undue risks; e.g., the price or availability of necessary materials or labor is not reasonably foreseeable;
(2) Market prices for the supplies or services involved are likely to change substantially; or
(3) The option represents known firm requirements for which funds are available unless (i) the basic quantity is a learning or testing quantity and (ii) competition for the option is impracticable once the initial contract is awarded.
(d) In recognition of (1) the Government's need in certain service contracts for continuity of operations and (2) the potential cost of disrupted support, options may be included in service contracts if there is an anticipated need for a similar service beyond the first contract period.
Sections that refer to it
- 17.208 Solicitation provisions and contract clauses.
← 17.201 [Reserved] · 17.203 Solicitations. →
Rule changes for FAR Part 17
- Federal Acquisition Regulation: Revolutionary Federal Acquisition Regulation Overhaul Parts 16, 17, and 35 ↗ · proposed 2026-09-18 · comments due 2026-10-19
- Federal Acquisition Regulation: Inflation Adjustment of Acquisition-Related Thresholds ↗ · final rule 2025-08-27 · effective 2025-10-01
- Federal Acquisition Regulation; Technical Amendments ↗ · final rule 2025-05-12 · effective 2025-06-11
- Federal Acquisition Regulation: Preventing Organizational Conflicts of Interest in Federal Acquisition ↗ · proposed 2025-01-15 · comments due 2025-03-17
- Federal Acquisition Regulation: Inflation Adjustment of Acquisition-Related Thresholds ↗ · proposed 2024-11-29 · comments due 2025-01-28
- Federal Acquisition Regulation: Prohibition on the Use of Reverse Auctions for Complex, Specialized, or Substantial Design and Construction Services ↗ · proposed 2024-08-29 · comments due 2024-10-28
- Federal Acquisition Regulation; Technical Amendments ↗ · final rule 2024-07-30 · effective 2024-08-29
- Federal Acquisition Regulation: Reverse Auction Guidance ↗ · final rule 2024-07-30 · effective 2024-08-29
Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗. Plain words for the terms: glossary.