DFARS 217.7404-3 Definitization schedule.
The codified text (eCFR, as of 2026-10-02). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule.
In plain English
This section requires Undefinitized Contract Actions (UCAs) to include a schedule for definitization, generally by the earlier of 180 days after the contractor submits a qualifying proposal or when obligated funds exceed 50 percent of the not-to-exceed price. Submitting a qualifying proposal on schedule is a material element of the contract, and failure to do so can lead the contracting officer to withhold payments or take other actions.
Applies to: UCAs and contractors holding them
What it requires
- Submit a qualifying proposal in accordance with the contract definitization schedule
Key terms: UCAs · definitization schedule · qualifying proposal · not-to-exceed price · material element of the contract
Written by AI from this section's text. A guide, not legal advice: the text below rules.
The text
(a) UCAs shall contain definitization schedules that provide for definitization by the earlier of—
(1) The date that is 180 days after the contractor submits a qualifying proposal. This date may not be extended beyond an additional 90 days without a written determination by the head of the contracting activity without power of redelegation, the commander of the combatant command concerned, or the Under Secretary of Defense for Acquisition and Sustainment that it is in the best interests of the military department or the defense agency, the combatant command, or the Department of Defense, respectively, to continue the action; or
(2) The date on which the amount of funds obligated under the contract action is equal to more than 50 percent of the not-to-exceed price.
(b)(1) Submission of a qualifying proposal in accordance with the definitization schedule is a material element of the contract. If the contractor does not submit a qualifying proposal in accordance with the contract definitization schedule, notwithstanding FAR 52.216-26, Payments of Allowable Costs Before Definitization, the contracting officer may withhold an amount necessary to protect the interests of the Government, not to exceed 5 percent of all subsequent financing requests, or take other appropriate actions (e.g., documenting the noncompliance in the contractor's past performance evaluation or terminating the contract for default).
(2) Contracting officers shall document in the contract file the justification for withholding or not withholding payments if the qualifying proposal was not submitted in accordance with the contract definitization schedule.
Sections it refers to
- 52.216-26 Payments of Allowable Costs Before Definitization.
Sections that refer to it
- 216.603-2 Application.
- 217.7404-5 Exceptions.
← 217.7404-2 Price ceiling. · 217.7404-4 Limitations on obligations. →
Rule changes for DFARS Part 217
- Defense Federal Acquisition Regulation Supplement: Mitigating Risks Related to Foreign Ownership, Control, or Influence (DFARS Case 2021-D011) ↗ · proposed 2026-05-07 · comments due 2026-07-06
- Defense Federal Acquisition Regulation Supplement: Assessing Contractor Implementation of Cybersecurity Requirements (DFARS Case 2019-D041) ↗ · final rule 2025-09-10 · effective 2025-11-10
- Defense Federal Acquisition Regulation Supplement: Inflation Adjustment of Acquisition-Related Thresholds (DFARS Case 2024-D002) ↗ · final rule 2025-08-25 · effective 2025-10-01
- Defense Federal Acquisition Regulation Supplement: Inflation Adjustment of Acquisition-Related Thresholds (DFARS Case 2024-D002) ↗ · proposed 2025-01-17 · comments due 2025-03-18
- Defense Federal Acquisition Regulation Supplement; Technical Amendments ↗ · final rule 2025-01-17 · effective 2025-01-17
- Defense Federal Acquisition Regulation Supplement: Disclosure of Information Regarding Foreign Obligations (DFARS Case 2018-D064) ↗ · proposed 2024-11-15 · comments due 2025-01-14
- Defense Federal Acquisition Regulation Supplement: Data Universal Numbering System to Unique Entity Identifier Transition (DFARS Case 2022-D023) ↗ · final rule 2024-09-26 · effective 2024-10-01
- Defense Federal Acquisition Regulation Supplement: Assessing Contractor Implementation of Cybersecurity Requirements (DFARS Case 2019-D041) ↗ · proposed 2024-08-15 · comments due 2024-10-15
Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗. Plain words for the terms: glossary.