FAR 22.1012-1 Prevailing wage determinations.
The codified text (eCFR, as of 2026-10-02). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule.
In plain English
This section explains when revised prevailing wage determinations must be included in solicitations, contracts, or modifications. It sets timing rules based on when the contracting agency receives the revision, with different deadlines for sealed bidding and other contract actions. Contractors should understand that a revised wage determination may become effective and change contract requirements if it is received within the specified timeframes.
Applies to: Contracting officers and contractors involved in contracts subject to prevailing wage determinations.
What it requires
- The contracting officer shall monitor the Wage Determinations at SAM.gov website to determine whether the applicable wage determination has been revised.
- Revisions published on the Wage Determinations at SAM.gov website or otherwise communicated to the contracting officer within the timeframes prescribed at 22.1012-1(b) and (c) are effective and must be included in the resulting contract.
- If the contracting officer has submitted an e98 to the Department of Labor requesting a prevailing wage determination and has not received a response within 10 days, the contracting officer shall contact the Wage and Hour Division by telephone to determine when the wage determination can be expected
Key terms: prevailing wage determination · Wage and Hour Administrator · Wage Determinations at SAM.gov · e98 process · sealed bidding
Written by AI from this section's text. A guide, not legal advice: the text below rules.
The text
(a)(1) The Wage and Hour Administrator may issue revisions to prevailing wage determinations periodically. The need for inclusion of a revised prevailing wage determination in a solicitation, contract or contract modification (see 22.1007) is determined by the date of receipt of the revised prevailing wage determination by the contracting agency. (Note the distinction between receipt by the agency and receipt by the contracting officer which may occur later.)
(i) For purposes of using Wage Determinations at SAM.gov, the time of receipt by the contracting agency shall be the first day of publication of the revised prevailing wage determination on the website.
(ii) For purposes of using the e98 process, the time of receipt by the contracting agency shall be the date the agency receives actual notice of a new or revised prevailing wage determination from the Department of Labor as an e98 response.
(2) In selecting a prevailing wage determination from the Wage Determinations at SAM.gov website for use in a solicitation or other contract action, the contracting officer shall monitor the Wage Determinations at SAM.gov website to determine whether the applicable wage determination has been revised. Revisions published on the Wage Determinations at SAM.gov website or otherwise communicated to the contracting officer within the timeframes prescribed at 22.1012-1(b) and (c) are effective and must be included in the resulting contract. Monitoring can be accomplished by use of the Wage Determinations at SAM.gov website's “Alert Service”.
(b) The following shall apply when contracting by sealed bidding: a revised prevailing wage determination shall not be effective if it is received by the contracting agency less than 10 days before the opening of bids, and the contracting officer finds that there is not reasonable time to incorporate the revision in the solicitation.
(c) For contractual actions other than sealed bidding, a revised prevailing wage determination received by the contracting agency after award of a new contract or a modification as specified in 22.1007(b) shall not be effective provided that the start of performance is within 30 days of the award or the specified modification. If the contract does not specify a start of performance date which is within 30 days of the award or the specified modification, and if contract performance does not commence within 30 days of the award or the specified modification, any revision received by the contracting agency not less than 10 days before commencement of the work shall be effective.
(d) If the contracting officer has submitted an e98 to the Department of Labor requesting a prevailing wage determination and has not received a response within 10 days, the contracting officer shall contact the Wage and Hour Division by telephone to determine when the wage determination can be expected. (The telephone number is provided on the e98 website.)
Sections it refers to
- 22.1007 Requirement to obtain wage determinations.
Sections that refer to it
- 22.1014 Delay over 60 days in bid opening or commencement of work.
← 22.1012 Applicability of revisions to wage determinations. · 22.1012-2 Wage determinations based on collective bargaining agreements. →
Rule changes for FAR Part 22
- Federal Acquisition Regulation: Trade Agreements Thresholds ↗ · final rule 2026-03-13 · effective 2026-03-13
- Federal Acquisition Regulation: Inflation Adjustment of Acquisition-Related Thresholds ↗ · final rule 2025-08-27 · effective 2025-10-01
- Office of Federal Procurement Policy; Federal Acquisition Regulation: Pay Equity and Transparency in Federal Contracting ↗ · proposed 2025-01-08
- Federal Acquisition Regulation: Improving Consistency Between Procurement and Nonprocurement Procedures on Suspension and Debarment ↗ · final rule 2025-01-03 · effective 2025-01-17
- Federal Acquisition Regulation: Training To Prevent Human Trafficking for Certain Air Carriers; Correction ↗ · final rule 2024-12-30 · effective 2025-01-03
- Federal Acquisition Regulation: Training To Prevent Human Trafficking for Certain Air Carriers ↗ · final rule 2024-12-16 · effective 2025-01-03
- Federal Acquisition Regulation: Inflation Adjustment of Acquisition-Related Thresholds ↗ · proposed 2024-11-29 · comments due 2025-01-28
- Federal Acquisition Regulation: Combating Trafficking in Persons-Definition and Agency Responsibilities ↗ · proposed 2024-07-18 · comments due 2024-09-16
Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗. Plain words for the terms: glossary.