DFARS 225.7003-2 Restrictions.
The codified text (eCFR, as of 2026-10-02). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule.
In plain English
This section restricts acquiring certain military items, or their components, unless any specialty metals in them are melted or produced in the United States. It also restricts acquiring specialty metal itself as an end item unless it is melted or produced in the United States. These restrictions apply except as provided in 225.7003-3.
Applies to: Contractors acquiring the listed items, their components, or specialty metal as an end item for DoD
What it requires
- Do not acquire the listed items or their components unless any specialty metals in them are melted or produced in the United States
- Do not acquire specialty metal as an end item unless it is melted or produced in the United States
Key terms: specialty metals · melted or produced in the United States · end item · components
Written by AI from this section's text. A guide, not legal advice: the text below rules.
The text
(a) The following restrictions implement 10 U.S.C. 4863. Except as provided in 225.7003-3—
(1) Do not acquire the following items, or any components of the following items, unless any specialty metals contained in the items or components are melted or produced in the United States (also see guidance at PGI 225.7003-2(a)):
(i) Aircraft.
(ii) Missile or space systems.
(iii) Ships.
(iv) Tank or automotive items.
(v) Weapon systems.
(vi) Ammunition.
(2) Do not acquire a specialty metal (e.g., raw stock, including bar, billet, slab, wire, plate, and sheet; castings; and forgings) as an end item, unless the specialty metal is melted or produced in the United States. This restriction applies to specialty metal acquired by a contractor for delivery to DoD as an end item, in addition to specialty metal acquired by DoD directly from the entity that melted or produced the specialty metal.
(b) For more information on specialty metals restrictions and reporting of noncompliances, see https://www.acq.osd.mil/asda/dpc/cp/ic/specialty-metals-restrictions.html.
Sections it refers to
- 225.7003-3 Exceptions.
Sections that refer to it
- 225.7003-3 Exceptions.
- 225.7003-5 Solicitation provision and contract clauses.
- 225.7009-2 Restriction.
← 225.7003-1 Definitions. · 225.7003-3 Exceptions. →
Rule changes for DFARS Part 225
- Defense Federal Acquisition Regulation Supplement: Modifications to Printed Circuit Board Acquisition Restrictions (DFARS Case 2022-D011) ↗ · proposed 2026-07-02 · comments due 2026-08-31
- Defense Federal Acquisition Regulation Supplement: Small Purchase Exception for the Acquisition of U.S. Flags (DFARS Case 2024-D013) ↗ · proposed 2026-06-25 · comments due 2026-08-24
- Defense Federal Acquisition Regulation Supplement: Inflation Adjustment of Acquisition-Related Thresholds (DFARS Case 2024-D002) ↗ · final rule 2025-08-25 · effective 2025-10-01
- Defense Federal Acquisition Regulation Supplement; Technical Amendments ↗ · final rule 2025-08-25 · effective 2025-08-25
- Defense Federal Acquisition Regulation Supplement: Inflation Adjustment of Acquisition-Related Thresholds (DFARS Case 2024-D002) ↗ · proposed 2025-01-17 · comments due 2025-03-18
- Defense Federal Acquisition Regulation Supplement; Technical Amendments ↗ · final rule 2024-12-18 · effective 2024-12-18
- Defense Federal Acquisition Regulation Supplement: Inapplicability of Additional Defense-Unique Laws and Certain Non-Statutory DFARS Clauses to Commercial Item Contracts (DFARS Case 2018-D074) ↗ · final rule 2024-11-15 · effective 2024-11-25
- Defense Federal Acquisition Regulation Supplement; Technical Amendments ↗ · final rule 2024-11-15 · effective 2024-11-15
Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗. Plain words for the terms: glossary.