FAR 25.607 Noncompliance.

The codified text (eCFR, as of 2026-10-02). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule.

In plain English

This section tells the contracting officer how to handle suspected violations of the Buy American statute or Recovery Act section 1605, which restrict the use of foreign construction materials. The officer must review allegations, notify the contractor of any apparent unauthorized use, and may require removal and replacement or take other contractual actions. Contractors should understand that unauthorized use can lead to serious consequences, including contract termination or suspension/debarment.

Applies to: Contractors and subcontractors on contracts subject to the Buy American statute or Recovery Act section 1605

Key terms: foreign construction material · Buy American statute · section 1605 of the Recovery Act · unauthorized use · removal and replacement

Written by AI from this section's text. A guide, not legal advice: the text below rules.

The text

The contracting officer must—

(a) Review allegations of violations of section 1605 of the Recovery Act or Buy American statute;

(b) Unless fraud is suspected, notify the contractor of the apparent unauthorized use of foreign construction material and request a reply, to include proposed corrective action; and

(c) If the review reveals that a contractor or subcontractor has used foreign construction material without authorization, take appropriate action, including one or more of the following:

(1) Process a determination concerning the inapplicability of section 1605 of the Recovery Act or the Buy American statute in accordance with 25.606.

(2) Consider requiring the removal and replacement of the unauthorized foreign construction material.

(3) If removal and replacement of foreign construction material incorporated in a building or work would be impracticable, cause undue delay, or otherwise be detrimental to the interests of the Government, the contracting officer may determine in writing that the foreign construction material need not be removed and replaced. A determination to retain foreign construction material does not constitute a determination that an exception to section 1605 of the Recovery Act or the Buy American statute applies, and this should be stated in the determination. Further, a determination to retain foreign construction material does not affect the Government's right to suspend or debar a contractor, subcontractor, or supplier for violation of section 1605 of the Recovery Act or the Buy American statute, or to exercise other contractual rights and remedies, such as reducing the contract price or terminating the contract for default.

(4) If the noncompliance is sufficiently serious, consider exercising appropriate contractual remedies, such as terminating the contract for default. Also consider preparing and forwarding a report to the agency suspending and debarring official in accordance with subpart 9.4. If the noncompliance appears to be fraudulent, refer the matter to other appropriate agency officials, such as the agency's inspector general or the officer responsible for criminal investigation.

Sections it refers to

  • 25.606 Postaward determinations.

← 25.606 Postaward determinations. · 25.700 Scope of subpart. →