FAR and DFARS › DFARS Part 252: Solicitation Provisions and Contract Clauses › Subpart 252.2

DFARS 252.217-7001 Surge option.

The codified text (eCFR, as of 2026-10-02). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule.

In plain English

This clause gives the Government an option to increase the quantity of supplies or services under the contract by a stated percentage or amount, and/or to accelerate the delivery rate. It sets out how the option delivery schedule is determined, how the option is exercised, and how price or cost for the added or accelerated items is negotiated. It matters because it defines the contractor's obligations and limits when the Government uses this surge option.

Applies to: Contractors under contracts that include DFARS clause 252.217-7001.

What it requires

  • If there is no Capabilities Analysis Plan in the contract, furnish the Contracting Officer a delivery schedule within 30 days from the date of award showing the maximum sustainable rate of delivery.
  • Do not revise the option delivery schedule without approval from the Contracting Officer.
  • If the option cost or price was not previously agreed upon, submit a cost or price proposal (including a cost breakdown) to the Contracting Officer within 30 days from the date of option exercise.
  • Proceed with performance of the contract as modified while any resulting claim is being settled.

Key terms: Surge Option · Capabilities Analysis Plan (CAP) · option delivery schedule · maximum sustainable rate of delivery · not-to-exceed price

Written by AI from this section's text. A guide, not legal advice: the text below rules.

The text

As prescribed in 217.208-70(b), use the following clause:

Surge Option (DEC 2018)

(a) General. The Government has the option to—

(1) Increase the quantity of supplies or services called for under this contract by no more than ____percent or ____[insert quantity and description of services or supplies to be increased]; and/or

(2) Accelerate the rate of delivery called for under this contract, at a price or cost established before contract award or to be established by negotiation as provided in this clause.

(b) Schedule. (1) When the Capabilities Analysis Plan (CAP) is included in the contract, the option delivery schedule shall be the production rate provided with the Plan. If the Plan was negotiated before contract award, then the negotiated schedule shall be used.

(2) If there is no CAP in the contract, the Contractor shall, within 30 days from the date of award, furnish the Contracting Officer a delivery schedule showing the maximum sustainable rate of delivery for items in this contract. This delivery schedule shall provide acceleration by month up to the maximum sustainable rate of delivery achievable within the Contractor's existing facilities, equipment, and subcontracting structure.

(3) The Contractor shall not revise the option delivery schedule without approval from the Contracting Officer.

(c) Exercise of option. (1) The Contracting Officer may exercise this option at any time before acceptance by the Government of the final scheduled delivery.

(2) The Contracting Officer will provide a preliminary oral or written notice to the Contractor stating the quantities to be added or accelerated under the terms of this clause, followed by a contract modification incorporating the transmitted information and instructions. The notice and modification will establish a not-to-exceed price equal to the highest contract unit price or cost of the added or accelerated items as of the date of the notice.

(3) The Contractor will not be required to deliver at a rate greater than the maximum sustainable delivery rate under paragraph (b)(2) of this clause, nor will the exercise of this option extend delivery more than 24 months beyond the scheduled final delivery.

(d) Price negotiation. (1) Unless the option cost or price was previously agreed upon, the Contractor shall, within 30 days from the date of option exercise, submit to the Contracting Officer a cost or price proposal (including a cost breakdown) for the added or accelerated items.

(2) Failure to agree on a cost or price in negotiations resulting from the exercise of this option shall constitute a dispute concerning a question of fact within the meaning of the Disputes clause of this contract. However, nothing in this clause shall excuse the Contractor from proceeding with the performance of the contract, as modified, while any resulting claim is being settled.

(End of clause)

Sections it refers to

Sections that refer to it

← 252.217-7000 Exercise of option to fulfill foreign military sales commitments. · 252.217-7002 Offering property for exchange. →

Rule changes for DFARS Part 252

Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗. Plain words for the terms: glossary.

DFARS 252.217-7001 Surge option · SpendQuery