DFARS 252.223-7008 Prohibition of Hexavalent Chromium.
The codified text (eCFR, as of 2026-10-02). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule.
In plain English
This clause prohibits contractors from delivering or using materials that contain hexavalent chromium above a certain concentration or that would require its removal or reapplication later. It also requires contractors to flow down this prohibition to subcontracts for supplies, maintenance and repair services, or construction materials.
Applies to: Contractors and subcontractors providing supplies, maintenance and repair services, or construction materials under a contract that includes this clause.
What it requires
- Do not provide any deliverable or construction material that contains hexavalent chromium in a concentration greater than 0.1 percent by weight in any homogeneous material, unless otherwise specified by the Contracting Officer.
- Do not provide any deliverable or construction material that requires the removal or reapplication of hexavalent chromium materials during subsequent sustainment phases, unless otherwise specified by the Contracting Officer.
- If authorization for incorporation of hexavalent chromium is required, submit a request to the Contracting Officer.
- Include the substance of this clause, including paragraph (d), in all subcontracts for supplies, maintenance and repair services, or construction materials, including subcontracts for commercial products or commercial services.
Key terms: Homogeneous material · Mechanically disjointed · Hexavalent chromium · Deliverable · Construction material
Written by AI from this section's text. A guide, not legal advice: the text below rules.
The text
As prescribed in 223.7306, use the following clause:
Prohibition of Hexavalent Chromium (JAN 2023)
(a) Definitions. As used in this clause—
Homogeneous material means a material that cannot be mechanically disjointed into different materials and is of uniform composition throughout.
(1) Examples of homogeneous materials include individual types of plastics, ceramics, glass, metals, alloys, paper, board, resins, and surface coatings.
(2) Homogeneous material does not include conversion coatings that chemically modify the substrate. Mechanically disjointed means that the materials can, in principle, be separated by mechanical actions such as unscrewing, cutting, crushing, grinding, and abrasive processes.
(b) Prohibition. (1) Unless otherwise specified by the Contracting Officer, the Contractor shall not provide any deliverable or construction material under this contract that—
(i) Contains hexavalent chromium in a concentration greater than 0.1 percent by weight in any homogenous material; or
(ii) Requires the removal or reapplication of hexavalent chromium materials during subsequent sustainment phases of the deliverable or construction material.
(2) This prohibition does not apply to hexavalent chromium produced as a by-product of manufacturing processes.
(c) If authorization for incorporation of hexavalent chromium in a deliverable or construction material is required, the Contractor shall submit a request to the Contracting Officer.
(d) Subcontracts. The Contractor shall include the substance of this clause, including this paragraph (d), in all subcontracts, including subcontracts for commercial products or commercial services, that are for supplies, maintenance and repair services, or construction materials.
(End of clause)
Sections it refers to
- 223.7306 Contract clause.
← 252.223-7007 Safeguarding Sensitive Conventional Arms, Ammunition, and Explosives. · 252.223-7009 Prohibition of Procurement of Fluorinated Fire-Fighting Agent for Use on Military Installations. →
Rule changes for DFARS Part 252
- Defense Federal Acquisition Regulation Supplement: Modifications to Printed Circuit Board Acquisition Restrictions (DFARS Case 2022-D011) ↗ · proposed 2026-07-02 · comments due 2026-08-31
- Defense Federal Acquisition Regulation Supplement: Certification Requirement for Military Recruitment Advertising (DFARS Case 2024-D022) ↗ · proposed 2026-06-25 · comments due 2026-08-24
- Defense Federal Acquisition Regulation Supplement: Small Purchase Exception for the Acquisition of U.S. Flags (DFARS Case 2024-D013) ↗ · proposed 2026-06-25 · comments due 2026-08-24
- Defense Federal Acquisition Regulation Supplement: Mitigating Risks Related to Foreign Ownership, Control, or Influence (DFARS Case 2021-D011) ↗ · proposed 2026-05-07 · comments due 2026-07-06
- Defense Federal Acquisition Regulation Supplement: Assessing Contractor Implementation of Cybersecurity Requirements (DFARS Case 2019-D041) ↗ · final rule 2025-09-10 · effective 2025-11-10
- Defense Federal Acquisition Regulation Supplement: Limitation on Certain Institutes of Higher Education (DFARS Case 2024-D023); Correction ↗ · final rule 2025-08-28 · effective 2025-08-28
- Defense Federal Acquisition Regulation Supplement: Disclosure of DoD Funding in Technical Publications (DFARS Case 2024-D003) ↗ · proposed 2025-08-25 · comments due 2025-10-24
- Defense Federal Acquisition Regulation Supplement: Limitation on Certain Institutes of Higher Education (DFARS Case 2024-D023) ↗ · final rule 2025-08-25 · effective 2025-08-25
Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗. Plain words for the terms: glossary.