FAR and DFARS › DFARS Part 252: Solicitation Provisions and Contract Clauses › Subpart 252.2
DFARS 252.231-7000 Supplemental cost principles.
In plain English: This clause says that when a contract's cost allowability is decided under FAR Part 31, it must also be decided under the Defense FAR Supplement Part 231 as in effect on the contract date. In practice, a contractor has to check both the FAR and DFARS cost principles to know which costs can be charged to the government. (A summary written by AI from the official text below, which is what governs. Not legal advice.)
When it applies: as prescribed in 231.100-70, which says when contracting officers use it.
Last amended 2016-12-22 · This page's summary last updated 2026-11-07 · Text as of 2026-10-29 (the eCFR copy this page shows) · Official text of DFARS 252.231-7000 ↗
The codified text (eCFR, as of 2026-10-29). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule. Today's text against the overhaul, side by side.
Open SAM.gov notices that cite DFARS 252.231-7000 · Ask the AI chat about it
In more detail
Applies to: DoD contracts that use cost-reimbursement or other cost-based pricing where allowable costs are determined
What it requires
- Determine cost allowability under both FAR Part 31 and DFARS Part 231 as in effect on the contract date
Key terms: allowability · FAR part 31 · DFARS part 231 · in effect on the date of this contract
Written by AI from this section's text. A guide, not legal advice: the text below rules.
The text
As prescribed in 231.100-70, use the following clause:
Supplemental Cost Principles (DEC 1991)
When the allowability of costs under this contract is determined in accordance with part 31 of the Federal Acquisition Regulation (FAR), allowability shall also be determined in accordance with part 231 of the Defense FAR Supplement, in effect on the date of this contract.
(End of clause)
Sections it refers to
- 231.100-70 Contract clause.
Sections that refer to it
- 231.100-70 Contract clause.
← 252.229-7014 Full Exemption from Two-Percent Excise Tax on Certain Foreign Procurements. · 252.232-7000 Advance payment pool. →
Rule changes for DFARS Part 252
- Defense Federal Acquisition Regulation Supplement: Modifications to Printed Circuit Board Acquisition Restrictions (DFARS Case 2022-D011) ↗ · proposed 2026-07-02 · comments due 2026-08-31
- Defense Federal Acquisition Regulation Supplement: Certification Requirement for Military Recruitment Advertising (DFARS Case 2024-D022) ↗ · proposed 2026-06-25 · comments due 2026-08-24
- Defense Federal Acquisition Regulation Supplement: Small Purchase Exception for the Acquisition of U.S. Flags (DFARS Case 2024-D013) ↗ · proposed 2026-06-25 · comments due 2026-08-24
- Defense Federal Acquisition Regulation Supplement: Mitigating Risks Related to Foreign Ownership, Control, or Influence (DFARS Case 2021-D011) ↗ · proposed 2026-05-07 · comments due 2026-07-06
- Defense Federal Acquisition Regulation Supplement: Assessing Contractor Implementation of Cybersecurity Requirements (DFARS Case 2019-D041) ↗ · final rule 2025-09-10 · effective 2025-11-10
- Defense Federal Acquisition Regulation Supplement: Limitation on Certain Institutes of Higher Education (DFARS Case 2024-D023); Correction ↗ · final rule 2025-08-28 · effective 2025-08-28
- Defense Federal Acquisition Regulation Supplement: Disclosure of DoD Funding in Technical Publications (DFARS Case 2024-D003) ↗ · proposed 2025-08-25 · comments due 2025-10-24
- Defense Federal Acquisition Regulation Supplement: Limitation on Certain Institutes of Higher Education (DFARS Case 2024-D023) ↗ · final rule 2025-08-25 · effective 2025-08-25
Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗. Plain words for the terms: glossary.