FAR and DFARS › DFARS Part 252: Solicitation Provisions and Contract Clauses › Subpart 252.2

DFARS 252.232-7013 Performance-Based Payments—Deliverable-Item Basis.

In plain English: This clause sets up performance-based payments on a deliverable-item basis, meaning the government pays the contractor as specific, scheduled events are completed rather than as costs are incurred. The contractor must keep financial statements under GAAP, report incurred costs on each payment request in the prescribed format, and provide security for the payments, with title to property as the preferred form. If adequate security is not provided or is found insufficient, payments can be withheld or suspended and the contractor may have to repay unliquidated financing. (A summary written by AI from the official text below, which is what governs. Not legal advice.)

When it applies: as prescribed in 232.1005-70(a)(2), which says when contracting officers use it.

Last amended 2022-12-30 · This page's summary last updated 2026-11-07 · Text as of 2026-10-29 (the eCFR copy this page shows) · Official text of DFARS 252.232-7013 ↗

The codified text (eCFR, as of 2026-10-29). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule. Today's text against the overhaul, side by side.

Open SAM.gov notices that cite DFARS 252.232-7013 · Ask the AI chat about it

In more detail

Applies to: Contractors receiving performance-based payments on deliverable-item contracts under the specified CLINs

What it requires

  • Keep financial statements in compliance with Generally Accepted Accounting Principles to receive performance-based payments
  • Submit incurred cost information with all payment requests in the format the clause prescribes, and give the Contracting Officer access to accounting books and records on request
  • Provide adequate security for the financing payments, preferably title to the property described in FAR 52.232-32(f), or an acceptable alternative
  • Promptly provide additional security if the Contracting Officer determines existing security is insufficient

Key terms: Performance-based payments · Deliverable-item basis · Performance-based payments schedule · Incurred cost · Security for financing

Written by AI from this section's text. A guide, not legal advice: the text below rules.

The text

As prescribed in 232.1005-70(a)(2), use the following clause:

Performance-Based Payments—Deliverable-Item Basis (DEC 2022)

(a) Performance-based payments shall form the basis for the contract financing payments provided under this contract and shall apply to Contract Line Item Number(s) (CLIN(s)) [Contracting Officer insert applicable CLIN(s)]. The performance-based payments schedule (Contract Attachment ____) describes the basis for payment, to include identification of the individual payment events, CLINs to which each event applies, evidence of completion, and amount of payment due upon completion of each event.

(b) In accordance with 10 U.S.C. 3802(c), the Contractor's financial statements shall be in compliance with Generally Accepted Accounting Principles in order to receive performance-based payments.

(c)(1) The Contractor shall, in addition to providing the information required by FAR 52.232-32, submit information for all payment requests using the following format:

(2) Incurred cost is determined by the Contractor's accounting books and records, to which the Contractor shall provide access upon request of the Contracting Officer. An acceptable accounting system in accordance with DFARS 252.242-7006 is not required for reporting of incurred costs under this clause. If the Contractor's accounting system is not capable of tracking costs on a job order basis, the Contractor shall provide a realistic approximation of the allocation of incurred costs attributable to this contract in accordance with the Contractor's accounting system. FAR 52.232-32(m) does not require certification of incurred costs.

(d) Security for financing. (1) Title to the property described in paragraph (f) of the clause at FAR 52.232-32, Performance-Based Payments, is the preferred security for receipt of performance-based payments.

(2)(i) If the Contractor's accounting system is not capable of identifying and tracking through the build cycle the property that is allocable and properly chargeable to this contract, the Contracting Officer may consider acceptance of one or a combination of the following alternative forms of security sufficient to constitute adequate security for the performance-based payments and so specify in the contract, consistent with FAR 32.202-4:

(A) A paramount lien on assets.

(B) An irrevocable letter of credit from a federally insured financial institution.

(C) A bond from a surety, acceptable in accordance with FAR part 28.

(D) A guarantee of repayment from a person or corporation of demonstrated liquid net worth, connected by significant ownership interest to the Contractor.

(E) Title to identified Contractor assets of adequate worth.

(ii) Paragraph (f) of the clause at FAR 52.232-32 does not apply to the extent that the Contractor and the Contracting Officer agree on alternative forms of security. In the event the Contractor fails to provide adequate security, as required in this contract, no financing payment will be made under this contract. Upon receipt of adequate security, financing payments will be made, including all previous payments to which the Contractor is entitled, in accordance with the terms of the provisions for contract financing. If at any time the Contracting Officer determines that the security provided by the Contractor is insufficient, the Contractor shall promptly provide such additional security as the Contracting Officer determines necessary. In the event the Contractor fails to provide such additional security, the Contracting Officer may collect or liquidate such security that has been provided and suspend further payments to the Contractor; and the Contractor shall repay to the Government the amount of unliquidated financing payments as the Contracting Officer at his sole discretion deems repayable.

(End of clause)

Sections it refers to

Sections that refer to it

  • 232.1005-70 Solicitation provisions and contract clauses.

Related DFARS 252.232 sections

← 252.232-7012 Performance-Based Payments—Whole-Contract Basis. · 252.232-7014 [Reserved] →

Rule changes for DFARS Part 252

Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗. Plain words for the terms: glossary.