DFARS 252.234-7004 Cost and Software Data Reporting System.

In plain English: This clause requires the contractor to run a documented cost and software data reporting process that meets the DoD CSDR Manual, with management procedures that produce timely, reliable cost data reports (CCDRs) and software resources data reports (SRDRs). It also ties that reporting to the Government-approved CSDR plan (DD Form 2794) and its Resource Distribution Table. For the Basic version, subcontracts over $50 million must also carry CSDR reporting requirements, and subcontractor changes must be reported to the Government. (A summary written by AI from the official text below, which is what governs. Not legal advice.)

When it applies: as prescribed in 234.7101(b), which says when contracting officers use it.

Last amended 2016-12-22 · This page's summary last updated 2026-11-07 · Text as of 2026-10-29 (the eCFR copy this page shows) · Official text of DFARS 252.234-7004 ↗

The codified text (eCFR, as of 2026-10-29). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule. Today's text against the overhaul, side by side.

Open SAM.gov notices that cite DFARS 252.234-7004 · Ask the AI chat about it

In more detail

Applies to: contractors performing DoD contracts that prescribe the Basic or Alternate I version of this clause

What it requires

  • Use a documented standard CSDR process that satisfies the DoD 5000.04-M-1 CSDR Manual
  • Maintain management procedures that generate timely and reliable CCDR and SRDR information
  • Report based on the Government-approved CSDR plan (DD Form 2794) and its Resource Distribution Table
  • Require CSDR reporting from subcontractors at any tier over $50 million (Basic) or from those identified in the CSDR plan (Alternate I), and notify the Government when subcontractors change or new awards are made

Key terms: Cost and Software Data Reporting (CSDR) · Contractor cost data reports (CCDRs) · Software resources data reports (SRDRs) · DD Form 2794 (CSDR plan) · Resource Distribution Table

Written by AI from this section's text. A guide, not legal advice: the text below rules.

The text

Basic. As prescribed in 234.7101(b) and (b)(1), use the following clause:

Cost and Software Data Reporting System—Basic (NOV 2014)

(a) In the performance of this contract, the Contractor shall use—

(1) A documented standard cost and software data reporting (CSDR) process that satisfies the guidelines contained in the DoD 5000.04-M-1, CSDR Manual;

(2) Management procedures that provide for generation of timely and reliable information for the contractor cost data reports (CCDRs) and software resources data reports (SRDRs) required by the CCDR and SRDR data items of this contract; and

(3) The Government-approved CSDR plan for this contract, DD Form 2794, and the related Resource Distribution Table as the basis for reporting in accordance with the required CSDR data item descriptions.

(b) The Contractor shall require CSDR reporting from subcontractors at any tier with a subcontract that exceeds $50 million. If, for subcontracts that exceed $50 million, the Contractor changes subcontractors or makes new subcontract awards, the Contractor shall notify the Government.

(End of clause)

Alternate I. As prescribed in 234.7101(b) and (b)(2), use the following clause, which uses a different paragraph (b) than the basic clause:

Cost and Software Data Reporting System—Alternate I (NOV 2014)

(a) In the performance of this contract, the Contractor shall use—

(1) A documented standard cost and software data reporting (CSDR) process that satisfies the guidelines contained in the DoD 5000.04-M-1, CSDR Manual;

(2) Management procedures that provide for generation of timely and reliable information for the contractor cost data reports (CCDRs) and software resources data reports (SRDRs) required by the CCDR and SRDR data items of this contract; and

(3) The Government-approved CSDR plan for this contract, DD Form 2794, and the related Resource Distribution Table as the basis for reporting in accordance with the required CSDR data item descriptions (DIDs).

(b) The Contractor shall require CSDR reporting from selected subcontractors identified in the CSDR contract plan as requiring such reporting. If the Contractor changes subcontractors or makes new awards for selected subcontract effort, the Contractor shall notify the Government.

(End of clause)

Sections it refers to

  • 234.7101 Solicitation provision and contract clause.

Sections that refer to it

  • 234.7101 Solicitation provision and contract clause.
  • 242.503-2 Post-award conference procedure.

Related DFARS 252.234 sections

← 252.234-7003 Notice of Cost and Software Data Reporting System. · 252.235-7000 Indemnification Under 10 U.S.C. 3861—Fixed Price. →

Rule changes for DFARS Part 252

Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗. Plain words for the terms: glossary.