DFARS 252.245-7003 Contractor Property Management System Administration.
The codified text (eCFR, as of 2026-10-02). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule.
In plain English
This clause requires contractors to set up and keep a property management system that meets the criteria in FAR 52.245-1. If the Contracting Officer finds material weaknesses and disapproves the system, the contractor must fix them or submit a corrective action plan, and payments may be withheld under DFARS 252.242-7005.
Applies to: Contractors managing and controlling Government property under contracts that include this clause
What it requires
- Establish and maintain an acceptable property management system
- Respond within 30 days to a written initial determination of material weaknesses, stating in writing the rationale for disagreeing if applicable
- Within 45 days of receiving a final determination of material weaknesses, either correct the weaknesses or submit an acceptable corrective action plan with milestones and actions
Key terms: Acceptable property management system · Material weakness · Property management system · Corrective action plan · Withholding payments
Written by AI from this section's text. A guide, not legal advice: the text below rules.
The text
As prescribed in 245.107(3), insert the following clause:
Contractor Property Management System Administration (Jan 2025)
(a) Definitions. As used in this clause—
Acceptable property management system means a property system that complies with the system criteria in paragraph (c) of this clause.
Material weakness means a deficiency or combination of deficiencies in the internal control over information in contractor business systems, such that there is a reasonable possibility that a material misstatement of such information will not be prevented, or detected and corrected, on a timely basis. A reasonable possibility exists when the likelihood of an event occurring is—
(1) Probable; or
(2) More than remote but less than likely (section 806 of Pub. L. 116-283).
Property management system means the Contractor's system or systems for managing and controlling Government property.
(b) General. The Contractor shall establish and maintain an acceptable property management system. Failure to maintain an acceptable property management system, as defined in this clause, may result in disapproval of the system by the Contracting Officer and/or withholding of payments.
(c) System criteria. The Contractor's property management system shall be in accordance with paragraphs (b) and (f) of the contract clause at Federal Acquisition Regulation 52.245-1.
(d) Material weaknesses. (1) The Contracting Officer will provide an initial determination to the Contractor, in writing, of any material weaknesses. The initial determination will describe the underlying deficiency in sufficient detail to allow the Contractor to understand the weaknesses or deficiency.
(2) The Contractor shall respond within 30 days to a written initial determination from the Contracting Officer that identifies material weaknesses in the Contractor's property management system. If the Contractor disagrees with the initial determination, the Contractor shall state, in writing, its rationale for disagreeing.
(3) The Contracting Officer will evaluate the Contractor's response and notify the Contractor, in writing, of the Contracting Officer's final determination concerning—
(i) Remaining material weaknesses;
(ii) The adequacy of any proposed or completed corrective action; and
(iii) System disapproval, if the Contracting Officer determines that one or more material weaknesses remain.
(e) If the Contractor receives the Contracting Officer's final determination of material weaknesses, the Contractor shall, within 45 days of receipt of the final determination, either correct the material weaknesses or submit an acceptable corrective action plan showing milestones and actions to eliminate the material weaknesses.
(f) Withholding payments. If the Contracting Officer makes a final determination to disapprove the Contractor's property management system, and the contract includes the clause at 252.242-7005, Contractor Business Systems, the Contracting Officer will withhold payments in accordance with that clause.
(End of clause)
Sections it refers to
- 245.107 Contract clauses.
- 52.245-1 Government Property.
- 252.242-7005 Contractor business systems.
Sections that refer to it
- 242.7000 Contractor business system deficiencies.
- 242.7001 Contract clause.
- 245.105 Contractors' property management system compliance.
- 245.107 Contract clauses.
- 252.242-7005 Contractor business systems.
← 252.245-7002 [Reserved] · 252.245-7004 [Reserved] →
Rule changes for DFARS Part 252
- Defense Federal Acquisition Regulation Supplement: Modifications to Printed Circuit Board Acquisition Restrictions (DFARS Case 2022-D011) ↗ · proposed 2026-07-02 · comments due 2026-08-31
- Defense Federal Acquisition Regulation Supplement: Certification Requirement for Military Recruitment Advertising (DFARS Case 2024-D022) ↗ · proposed 2026-06-25 · comments due 2026-08-24
- Defense Federal Acquisition Regulation Supplement: Small Purchase Exception for the Acquisition of U.S. Flags (DFARS Case 2024-D013) ↗ · proposed 2026-06-25 · comments due 2026-08-24
- Defense Federal Acquisition Regulation Supplement: Mitigating Risks Related to Foreign Ownership, Control, or Influence (DFARS Case 2021-D011) ↗ · proposed 2026-05-07 · comments due 2026-07-06
- Defense Federal Acquisition Regulation Supplement: Assessing Contractor Implementation of Cybersecurity Requirements (DFARS Case 2019-D041) ↗ · final rule 2025-09-10 · effective 2025-11-10
- Defense Federal Acquisition Regulation Supplement: Limitation on Certain Institutes of Higher Education (DFARS Case 2024-D023); Correction ↗ · final rule 2025-08-28 · effective 2025-08-28
- Defense Federal Acquisition Regulation Supplement: Disclosure of DoD Funding in Technical Publications (DFARS Case 2024-D003) ↗ · proposed 2025-08-25 · comments due 2025-10-24
- Defense Federal Acquisition Regulation Supplement: Limitation on Certain Institutes of Higher Education (DFARS Case 2024-D023) ↗ · final rule 2025-08-25 · effective 2025-08-25
Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗. Plain words for the terms: glossary.