FAR and DFARS › DFARS Part 252: Solicitation Provisions and Contract Clauses › Subpart 252.2

DFARS 252.246-7002 Warranty of construction (Germany).

In plain English: This clause makes the contractor warrant that construction work conforms to the contract and is free of defects in equipment, materials, design, or workmanship, including those from subcontractors and suppliers. The warranty runs for periods set in Section 13 of VOB Part B, starting from final acceptance (or from when the Government takes possession, if earlier). For a small business, it means the contractor must fix defects at its own expense and pass through or enforce supplier and subcontractor warranties for the Government's benefit. (A summary written by AI from the official text below, which is what governs. Not legal advice.)

When it applies: as prescribed in 246.710(2), which says when contracting officers use it.

Last amended 2016-12-22 · This page's summary last updated 2026-11-07 · Text as of 2026-10-29 (the eCFR copy this page shows) · Official text of DFARS 252.246-7002 ↗

The codified text (eCFR, as of 2026-10-29). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule. Today's text against the overhaul, side by side.

Open SAM.gov notices that cite DFARS 252.246-7002 · Ask the AI chat about it

In more detail

Applies to: construction contractors performing work in Germany under a DFARS contract

What it requires

  • Remedy, at the Contractor's expense, any failure to conform to the contract, any defect, and any resulting damage to Government property within the warranty period.
  • Obtain all warranties from subcontractors, manufacturers, or suppliers that would be given in normal commercial practice.
  • Require warranties to be executed in writing for the Government's benefit, and enforce them for the Government, when directed by the Contracting Officer.
  • Restore any work damaged while fulfilling the clause.

Key terms: VOB, Part B (Section 13) · final acceptance · latent defects · Contracting Officer · warranty period

Written by AI from this section's text. A guide, not legal advice: the text below rules.

The text

As prescribed in 246.710(2), use the following clause:

Warranty of Construction (Germany) (JUN 1997)

(a) In addition to any other representations in this contract, the Contractor warrants, except as provided in paragraph (j) of this clause, that the work performed under this contract conforms to the contract requirements and is free of any defect of equipment, material, or design furnished or workmanship performed by the Contractor or any subcontractor or supplier at any tier.

(b) This warranty shall continue for the period(s) specified in Section 13, VOB, Part B, commencing from the date of final acceptance of the work under this contract. If the Government takes possession of any part of the work before final acceptance, this warranty shall continue for the period(s) specified in Section 13, VOB, Part B, from the date the Government takes possession.

(c) The Contractor shall remedy, at the Contractor's expense, any failure to conform or any defect. In addition, the Contractor shall remedy, at the Contractor's expense, any damage to Government-owned or -controlled real or personal property when that damage is the result of—

(1) The Contractor's failure to conform to contract requirements; or

(2) Any defect of equipment, material, or design furnished or workmanship performed.

(d) The Contractor shall restore any work damaged in fulfilling the terms and conditions of this clause.

(e) The Contracting Officer shall notify the Contractor, in writing, within a reasonable period of time after the discovery of any failure, defect, or damage.

(f) If the Contractor fails to remedy any failure, defect, or damage within a reasonable period of time after receipt of notice, the Government shall have the right to replace, repair, or otherwise remedy the failure, defect, or damage at the Contractor's expense.

(g) With respect to all warranties, express or implied, from subcontractors, manufacturers, or suppliers for work performed and materials furnished under this contract, the Contractor shall—

(1) Obtain all warranties that would be given in normal commercial practice;

(2) Require all warranties to be executed in writing, for the benefit of the Government, if directed by the Contracting Officer; and

(3) Enforce all warranties for the benefit of the Government as directed by the Contracting Officer.

(h) In the event the Contractor's warranty under paragraph (b) of this clause has expired, the Government may bring suit at its expense to enforce a subcontractor's, manufacturer's, or supplier's warranty.

(i) Unless a defect is caused by the Contractor's negligence, or the negligence of a subcontractor or supplier at any tier, the Contractor shall not be liable for the repair of any defects of material or design furnished by the Government or for the repair of any damage resulting from any defeat in Government-furnished material or design.

(j) This warranty shall not limit the Government's right under the Inspection clause of this contract, with respect to latent defects, gross mistakes, or fraud.

(End of clause)

Sections it refers to

Sections that refer to it

Related DFARS 252.246 sections

← 252.246-7001 Warranty of data. · 252.246-7003 Notification of Potential Safety Issues. →

Rule changes for DFARS Part 252

Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗. Plain words for the terms: glossary.