DFARS 252.247-7023 Transportation of Supplies by Sea.
In plain English: This clause requires contractors that will ship DoD-related supplies by sea to notify the Contracting Officer and MARAD, and to use U.S.-flag vessels for that transport. Foreign-flag use is allowed only through a written waiver requested at least 45 days before sailing, and the contractor must report each shipment's bill of lading and certify its vessel use on the final invoice. Failure to provide the required invoice representation can cause the invoice to be rejected as improper. (A summary written by AI from the official text below, which is what governs. Not legal advice.)
When it applies: as prescribed in 247.574(a), which says when contracting officers use it.
Last amended 2024-10-01 · This page's summary last updated 2026-11-07 · Text as of 2026-10-29 (the eCFR copy this page shows) · Official text of DFARS 252.247-7023 ↗
The codified text (eCFR, as of 2026-10-29). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule. Today's text against the overhaul, side by side.
Open SAM.gov notices that cite DFARS 252.247-7023 · Ask the AI chat about it
In more detail
Applies to: prime contractors (and subcontractors on covered shipments) transporting DoD supplies by sea
What it requires
- Notify the Contracting Officer and MARAD within 3 business days after award, or before the shipment departure date, whichever is earlier, stating intent to ship by sea with the contract (and any task/delivery order) number
- Use U.S.-flag vessels for ocean transport under the contract, unless a waiver is approved
- Submit any foreign-flag waiver request in writing at least 45 days before the needed sailing date, with the listed cargo, shipping, and diligent-efforts details
- Within 30 days after each shipment, send MARAD and the Contracting Officer a copy of the ocean bill of lading, and include a vessel-use representation with the final invoice if the contract exceeds the simplified acquisition threshold
Key terms: U.S.-flag vessel · Foreign-flag vessel · Ocean transportation · Supplies (clearly identifiable for eventual use by or owned by DoD) · Simplified acquisition threshold
Written by AI from this section's text. A guide, not legal advice: the text below rules.
The text
As prescribed in 247.574(a) and (a)(1), use the following basic clause:
Transportation of Supplies by Sea—Basic (OCT 2024)
(a) Definitions. As used in this clause—
Foreign-flag vessel means any vessel that is not a U.S.-flag vessel.
Ocean transportation means any water-borne transportation aboard a ship, vessel, boat, barge, ferry, or the like outside the internal waters of the United States as defined in 33 CFR 2.24.
Subcontractor means a supplier, materialman, distributor, or vendor at any level below the prime contractor whose contractual obligation to perform results from, or is conditioned upon, award of the prime contract and who is performing any part of the work or other requirement of the prime contract.
Supplies means supplies that are clearly identifiable for eventual use by or owned by DoD at the time of transportation by sea, or are otherwise transported by DoD, regardless of ownership or use by DoD. An item is clearly identifiable for eventual use by DoD if, for example, the contract documentation contains a reference to a DoD contract number or a military destination.
U.S.-flag vessel means either a vessel belonging to the United States or a vessel of the United States as that term is defined in 46 U.S.C. 116.
(b) If the transportation of supplies by sea is anticipated under this contract, the Contractor shall—
(1) Notify the Contracting Officer and Maritime Administration (MARAD) at [email protected]—
(i) Within 3 business days after contract award; or
(ii) Immediately prior to the shipment departure date necessary to meet delivery schedules, whichever is earlier; and
(2) Include in the notification—
(i) A statement of the Contractor's intent to transport supplies by sea;
(ii) The contract number; and
(iii) The task-order or delivery-order number, when applicable.
(c)(1) The Contractor shall use U.S.-flag vessels when transporting any supplies by sea under this contract.
(2) A subcontractor transporting supplies by sea under this contract shall use U.S.-flag vessels if—
(i) This contract is a construction contract; or
(ii) The supplies being transported are—
(A) Other than commercial products or
(B) Commercial products that—
(1) The Contractor is reselling or distributing to the Government without adding value (generally, the Contractor does not add value to items that it contracts for f.o.b. destination shipment);
(2) Are shipped in direct support of U.S. military contingency operations, exercises, or forces deployed in humanitarian or peacekeeping operations; or
(3) Are commissary or exchange cargoes transported outside of the Defense Transportation System in accordance with 10 U.S.C. 2643.
(d) The Contractor and its subcontractors may request, via the Contracting Officer, a waiver of the requirement to use a U.S.-flag vessel, or identification of any available U.S.-flag vessels, if the Contractor or a subcontractor sufficiently explains that—
(1) U.S.-flag vessels are not available at a fair and reasonable rate for commercial vessels of the United States; or
(2) U.S.-flag vessels are otherwise not available.
(e) The Contractor must submit any request for use of foreign-flag vessels in writing to the Contracting Officer at least 45 days prior to the sailing date necessary to meet its delivery schedules. The Contracting Officer will process requests submitted after such date(s) as expeditiously as possible, however, if a DoD waiver is not approved prior to the shipper's sailing date, this will not of itself constitute a compensable delay under this or any other clause of this contract. Requests shall contain at a minimum—
(1) Type, weight, and cube of cargo;
(2) Required shipping date(s) and required delivery date(s);
(3) Special handling and discharge requirements;
(4) Loading and discharge points;
(5) Name of shipper and consignee;
(6) Prime contract number; and
(7) A documented description of current, diligent efforts made to secure U.S.-flag vessels, including points of contact (with names and telephone numbers) with at least two U.S.-flag carriers contacted. Copies of quotes will suffice for this purpose. Copies of telephone notes, emails, and other relevant communications will otherwise be considered for this purpose.
(f) The Contractor shall, within 30 days after each shipment covered by this clause, provide the Contracting Officer and MARAD at [email protected], Attention: Military Team, one copy of the rated on board vessel operating carrier's ocean bill of lading, which shall contain the following information:
(1) Prime contract number;
(2) Name of vessel;
(3) Vessel flag of registry;
(4) Date of loading;
(5) Port of loading;
(6) Port of final discharge;
(7) Description of commodity;
(8) Gross weight in pounds and cubic feet if available;
(9) Total ocean freight in U.S. dollars; and
(10) Name of the carrier.
(g) If this contract exceeds the simplified acquisition threshold, the Contractor shall provide with its final invoice under this contract a representation that to the best of its knowledge and belief—
(1) No ocean transportation was used in the performance of this contract;
(2) Ocean transportation was used and only U.S.-flag vessels were used for all ocean shipments under the contract;
(3) Ocean transportation was used, and the Contractor had received a prior-approved waiver for U.S.-flag vessels for all foreign-flag ocean transportation; or
(4) Ocean transportation was used and some or all of the shipments were made on foreign-flag vessels without the written consent of DoD. The Contractor shall describe these shipments in the following format:
(h) If this contract exceeds the simplified acquisition threshold and the final invoice does not include the required representation, the Government will reject and return it to the Contractor as an improper invoice for the purposes of the Prompt Payment clause of this contract. In the event there has been unauthorized use of foreign-flag vessels in the performance of this contract, the Contracting Officer is entitled to equitably adjust the contract, based on the unauthorized use.
(i) If the Contractor did not anticipate transporting any supplies by sea at the time of contract award and, therefore, did not provide the notification required by paragraph (b) of this clause, but prior to shipment of supplies, the Contractor learns that supplies will be transported by sea, the Contractor shall—
(1) Provide the notification required by paragraph (b) of this clause to the Contracting Officer and MARAD as soon as it is known that supplies will be transported by sea; and
(2) Comply with all the terms and conditions of this clause.
(j) Subcontracts. In the award of subcontracts for the types of supplies described in paragraph (c)(2) of this clause, including subcontracts for commercial products, the Contractor shall flow down the requirements of this clause as follows:
(1) The Contractor shall insert the substance of this clause, including this paragraph (j), in subcontracts that exceed the simplified acquisition threshold in part 2 of the Federal Acquisition Regulation.
(2) The Contractor shall insert the substance of paragraphs (a) through (f) of this clause, and this paragraph (j), in subcontracts that are at or below the simplified acquisition threshold in part 2 of the Federal Acquisition Regulation.
(End of clause)
Alternate I. As prescribed in 247.574(a) and (a)(2), use the following clause, which uses a different paragraph (c) than the basic clause:
Transportation of Supplies by Sea—Alternate I (OCT 2024)
(a) Definitions. As used in this clause—
Foreign-flag vessel means any vessel that is not a U.S.-flag vessel.
Ocean transportation means any water-borne transportation aboard a ship, vessel, boat, barge, ferry, or the like outside the internal waters of the United States as defined in 33 CFR 2.24.
Subcontractor means a supplier, materialman, distributor, or vendor at any level below the prime contractor whose contractual obligation to perform results from, or is conditioned upon, award of the prime contract and who is performing any part of the work or other requirement of the prime contract.
Supplies means supplies that are clearly identifiable for eventual use by or owned by DoD at the time of transportation by sea, or are otherwise transported by DoD, regardless of ownership or use by DoD. An item is clearly identifiable for eventual use by DoD if, for example, the contract documentation contains a reference to a DoD contract number or a military destination.
U.S.-flag vessel means either a vessel belonging to the United States or a vessel of the United States as that term is defined in 46 U.S.C. 116.
(b) If the transportation of supplies by sea is anticipated under this contract, the Contractor shall—
(1) Notify the Contracting Officer and Maritime Administration (MARAD) at [email protected]—
(i) Within 3 business days after contract award; or
(ii) Immediately prior to the shipment departure date necessary to meet delivery schedules, whichever is earlier; and
(2) Include in the notification—
(i) A statement of the Contractor's intent to transport supplies by sea;
(ii) The contract number; and
(iii) The task-order or delivery-order number, when applicable.
(c)(1) The Contractor shall use U.S.-flag vessels when transporting any supplies by sea under this contract.
(2) A subcontractor transporting supplies by sea under this contract shall use U.S.-flag vessels if the supplies being transported are—
(i) Other than commercial products; or
(ii) Commercial products that—
(A) The Contractor is reselling or distributing to the Government without adding value (generally, the Contractor does not add value to items that it subcontracts for f.o.b. destination shipment);
(B) Are shipped in direct support of U.S. military contingency operations, exercises, or forces deployed in humanitarian or peacekeeping operations (Note: This contract requires shipment of commercial products in direct support of U.S. military contingency operations, exercises, or forces deployed in humanitarian or peacekeeping operations); or
(C) Are commissary or exchange cargoes transported outside of the Defense Transportation System in accordance with 10 U.S.C. 2643.
(d) The Contractor and its subcontractors may request, via the Contracting Officer, a waiver of the requirement to use a U.S.-flag vessel, or identification of any available U.S.-flag vessels, if the Contractor or a subcontractor sufficiently explains that—
(1) U.S.-flag vessels are not available at a fair and reasonable rate for commercial vessels of the United States; or
(2) U.S.-flag vessels are otherwise not available.
(e) The Contractor must submit any request for use of foreign-flag vessels in writing to the Contracting Officer at least 45 days prior to the sailing date necessary to meet its delivery schedules. The Contracting Officer will process requests submitted after such date(s) as expeditiously as possible, however, if a DoD waiver is not approved prior to the shipper's sailing date, this will not of itself constitute a compensable delay under this or any other clause of this contract. Requests shall contain at a minimum—
(1) Type, weight, and cube of cargo;
(2) Required shipping date(s) and required delivery date(s);
(3) Special handling and discharge requirements;
(4) Loading and discharge points;
(5) Name of shipper and consignee;
(6) Prime contract number; and
(7) A documented description of current, diligent efforts made to secure U.S.-flag vessels, including points of contact (with names and telephone numbers) with at least two U.S.-flag carriers contacted. Copies of quotes will suffice for this purpose. Copies of telephone notes, emails, and other relevant communications will otherwise be considered for this purpose.
(f) The Contractor shall, within 30 days after each shipment covered by this clause, provide the Contracting Officer and MARAD at [email protected], Attention: Military Team, one copy of the rated on board vessel operating carrier's ocean bill of lading, which shall contain the following information:
(1) Prime contract number;
(2) Name of vessel;
(3) Vessel flag of registry;
(4) Date of loading;
(5) Port of loading;
(6) Port of final discharge;
(7) Description of commodity;
(8) Gross weight in pounds and cubic feet if available;
(9) Total ocean freight in U.S. dollars; and
(10) Name of the carrier.
(g) If this contract exceeds the simplified acquisition threshold, the Contractor shall provide with its final invoice under this contract a representation that to the best of its knowledge and belief—
(1) No ocean transportation was used in the performance of this contract;
(2) Ocean transportation was used and only U.S.-flag vessels were used for all ocean shipments under the contract;
(3) Ocean transportation was used, and the Contractor had had received a prior-approved waiver for U.S.-flag vessels for all foreign-flag ocean transportation; or
(4) Ocean transportation was used and some or all of the shipments were made on foreign-flag vessels without the written consent of the DoD. The Contractor shall describe these shipments in the following format:
(h) If this contract exceeds the simplified acquisition threshold and the final invoice does not include the required representation, the Government will reject and return it to the Contractor as an improper invoice for the purposes of the Prompt Payment clause of this contract. In the event there has been unauthorized use of foreign-flag vessels in the performance of this contract, the Contracting Officer is entitled to equitably adjust the contract, based on the unauthorized use.
(i) If the Contractor did not anticipate transporting any supplies by sea at the time of contract award and, therefore, did not provide the notification required by paragraph (b) of this clause, but prior to shipment of supplies, the Contractor learns that supplies will be transported by sea, the Contractor shall—
(1) Provide the notification required by paragraph (b) of this clause to the Contracting Officer and MARAD as soon as it is known that supplies will be transported by sea; and
(2) Comply with all the terms and conditions of this clause.
(j) Subcontracts. In the award of subcontracts for the types of supplies described in paragraph (c)(2) of this clause, including subcontracts for commercial products, the Contractor shall flow down the requirements of this clause as follows:
(1) The Contractor shall insert the substance of this clause, including this paragraph (j), in subcontracts that exceed the simplified acquisition threshold in part 2 of the Federal Acquisition Regulation.
(2) The Contractor shall insert the substance of paragraphs (a) through (f) of this clause, and this paragraph (j), in subcontracts that are at or below the simplified acquisition threshold in part 2 of the Federal Acquisition Regulation.
(End of clause)
Alternate II. As prescribed in 247.574(a) and (a)(3), use the following clause, which uses a different paragraph (c) than the basic clause:
Transportation of Supplies by Sea—Alternate II (OCT 2024)
(a) Definitions. As used in this clause—
Foreign-flag vessel means any vessel that is not a U.S.-flag vessel.
Ocean transportation means any water-borne transportation aboard a ship, vessel, boat, barge, ferry, or the like outside the internal waters of the United States as defined in 33 CFR 2.24.
Subcontractor means a supplier, materialman, distributor, or vendor at any level below the prime contractor whose contractual obligation to perform results from, or is conditioned upon, award of the prime contract and who is performing any part of the work or other requirement of the prime contract.
Supplies means supplies that are clearly identifiable for eventual use by or owned by DoD at the time of transportation by sea, or are otherwise transported by DoD, regardless of ownership or use by DoD. An item is clearly identifiable for eventual use by DoD if, for example, the contract documentation contains a reference to a DoD contract number or a military destination.
U.S.-flag vessel means either a vessel belonging to the United States or a vessel of the United States as that term is defined in 46 U.S.C. 116.
(b) If the transportation of supplies by sea is anticipated under this contract, the Contractor shall—
(1) Notify the Contracting Officer and Maritime Administration (MARAD) at [email protected]—
(i) Within 3 business days after contract award; or
(ii) Immediately prior to the shipment departure date necessary to meet delivery schedules, whichever is earlier; and
(2) Include in the notification—
(i) A statement of the Contractor's intent to transport supplies by sea;
(ii) The contract number; and
(iii) The task-order or delivery-order number, when applicable.
(c)(1) The Contractor shall use U.S.-flag vessels when transporting any supplies by sea under this contract.
(2) A subcontractor transporting supplies by sea under this contract shall use U.S.-flag vessels if the supplies being transported are—
(i) Other than commercial products; or
(ii) Commercial products that—
(A) The Contractor is reselling or distributing to the Government without adding value (generally, the Contractor does not add value to items that it subcontracts for f.o.b. destination shipment);
(B) Are shipped in direct support of U.S. military contingency operations, exercises, or forces deployed in humanitarian or peacekeeping operations; or
(C) Are commissary or exchange cargoes transported outside of the Defense Transportation System in accordance with 10 U.S.C. 2643 (Note: This contract requires transportation of commissary or exchange cargoes outside of the Defense Transportation System in accordance with 10 U.S.C. 2643).
(d) The Contractor and its subcontractors may request, via the Contracting Officer, a waiver of the requirement to use a U.S.-flag vessel, or identification of any available U.S.-flag vessels, if the Contractor or a subcontractor sufficiently explains that—
(1) U.S.-flag vessels are not available at a fair and reasonable rate for commercial vessels of the United States; or
(2) U.S.-flag vessels are otherwise not available.
(e) The Contractor must submit any request for use of foreign-flag vessels in writing to the Contracting Officer at least 45 days prior to the sailing date necessary to meet its delivery schedules. The Contracting Officer will process requests submitted after such date(s) as expeditiously as possible, however, if a DoD waiver is not approved prior to the shipper's sailing date, this will not of itself constitute a compensable delay under this or any other clause of this contract.
(2) Required shipping date(s) and required delivery date(s);
(3) Special handling and discharge requirements;
(4) Loading and discharge points;
(5) Name of shipper and consignee;
(6) Prime contract number; and
(7) A documented description of current, diligent efforts made to secure U.S.-flag vessels, including points of contact (with names and telephone numbers) with at least two U.S.-flag carriers contacted. Copies of quotes will suffice for this purpose. Copies of telephone notes, emails, and other relevant communications will otherwise be considered for this purpose.
(f) The Contractor shall, within 30 days after each shipment covered by this clause, provide the Contracting Officer and MARAD at [email protected], Attention: Military Team, one copy of the rated on board vessel operating carrier's ocean bill of lading, which shall contain the following information:
(1) Prime contract number;
(2) Name of vessel;
(3) Vessel flag of registry;
(4) Date of loading;
(5) Port of loading;
(6) Port of final discharge;
(7) Description of commodity;
(8) Gross weight in pounds and cubic feet if available;
(9) Total ocean freight in U.S. dollars; and
(10) Name of steamship company.
(g) If this contract exceeds the simplified acquisition threshold, the Contractor shall provide with its final invoice under this contract a representation that to the best of its knowledge and belief—
(1) No ocean transportation was used in the performance of this contract;
(2) Ocean transportation was used and only U.S.-flag vessels were used for all ocean shipments under the contract;
(3) Ocean transportation was used, and the Contractor had the written consent of the Contracting Officer for all foreign-flag ocean transportation; or
(4) Ocean transportation was used and some or all of the shipments were made on foreign-flag vessels without the written consent of the Contracting Officer. The Contractor shall describe these shipments in the following format:
(h) If this contract exceeds the simplified acquisition threshold and the final invoice does not include the required representation, the Government will reject and return it to the Contractor as an improper invoice for the purposes of the Prompt Payment clause of this contract. In the event there has been unauthorized use of foreign-flag vessels in the performance of this contract, the Contracting Officer is entitled to equitably adjust the contract, based on the unauthorized use.
(i) If the Contractor did not anticipate transporting any supplies by sea at the time of contract award, and, therefore, did not provide the notification required by paragraph (b) of this clause, but prior to shipment of the supplies, the Contractor learns after the award of the contract that supplies will be transported by sea, the Contractor shall—
(1) Provide the notification required by paragraph (b) of this clause to the Contracting Officer and MARAD as soon as it is known that supplies will be transported by sea; and
(2) Comply with all the terms and conditions of this clause.
(j) Subcontracts. In the award of subcontracts for the types of supplies described in paragraph (c)(2) of this clause, including subcontracts for commercial products, the Contractor shall flow down the requirements of this clause as follows:
(1) The Contractor shall insert the substance of this clause, including this paragraph (j), in subcontracts that exceed the simplified acquisition threshold in part 2 of the Federal Acquisition Regulation.
(2) The Contractor shall insert the substance of paragraphs (a) through (f) of this clause, and this paragraph (j), in subcontracts that are at or below the simplified acquisition threshold in part 2 of the Federal Acquisition Regulation.
(End of clause)
Sections it refers to
- 247.574 Solicitation provisions and contract clauses.
Sections that refer to it
- 212.301 Solicitation provisions and contract clauses for the acquisition of commercial products and commercial services.
- 212.504 Applicability of certain laws to subcontracts for the acquisition of commercial products and commercial services.
- 242.1502 Policy.
- 247.574 Solicitation provisions and contract clauses.
Related DFARS 252.247 sections
- 252.247-7007 Liability and insurance.
- 252.247-7008—252.247-7013 [Reserved]
- 252.247-7014 Demurrage.
- 252.247-7015 [Reserved]
- 252.247-7016 Contractor liability for loss or damage.
- 252.247-7017—252.247-7021 [Reserved]
- 252.247-7022 [Reserved]
- 252.247-7024 [Reserved]
- 252.247-7025 Reflagging or Repair Work.
- 252.247-7026 Evaluation Preference for Use of Domestic Shipyards—Applicable to Acquisition of Carriage by Vessel for DoD Cargo in the Coastwise or Noncontiguous Trade.
- 252.247-7027 Riding Gang Member Requirements.
- 252.247-7028 Application for U.S. Government Shipping Documentation/Instructions.
← 252.247-7022 [Reserved] · 252.247-7024 [Reserved] →
Rule changes for DFARS Part 252
- Defense Federal Acquisition Regulation Supplement: Modifications to Printed Circuit Board Acquisition Restrictions (DFARS Case 2022-D011) ↗ · proposed 2026-07-02 · comments due 2026-08-31
- Defense Federal Acquisition Regulation Supplement: Certification Requirement for Military Recruitment Advertising (DFARS Case 2024-D022) ↗ · proposed 2026-06-25 · comments due 2026-08-24
- Defense Federal Acquisition Regulation Supplement: Small Purchase Exception for the Acquisition of U.S. Flags (DFARS Case 2024-D013) ↗ · proposed 2026-06-25 · comments due 2026-08-24
- Defense Federal Acquisition Regulation Supplement: Mitigating Risks Related to Foreign Ownership, Control, or Influence (DFARS Case 2021-D011) ↗ · proposed 2026-05-07 · comments due 2026-07-06
- Defense Federal Acquisition Regulation Supplement: Assessing Contractor Implementation of Cybersecurity Requirements (DFARS Case 2019-D041) ↗ · final rule 2025-09-10 · effective 2025-11-10
- Defense Federal Acquisition Regulation Supplement: Limitation on Certain Institutes of Higher Education (DFARS Case 2024-D023); Correction ↗ · final rule 2025-08-28 · effective 2025-08-28
- Defense Federal Acquisition Regulation Supplement: Disclosure of DoD Funding in Technical Publications (DFARS Case 2024-D003) ↗ · proposed 2025-08-25 · comments due 2025-10-24
- Defense Federal Acquisition Regulation Supplement: Limitation on Certain Institutes of Higher Education (DFARS Case 2024-D023) ↗ · final rule 2025-08-25 · effective 2025-08-25
Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗. Plain words for the terms: glossary.