FAR and DFARS › FAR Part 28: Bonds and Insurance › Subpart 28.3
FAR 28.305 Overseas workers' compensation and war-hazard insurance.
The codified text (eCFR, as of 2026-10-02). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule.
In plain English
This section explains that the Defense Base Act extends workers' compensation benefits to certain employees working overseas on public-work contracts or foreign assistance contracts. It also describes how war-hazard risk protection is provided and the process for waiving these requirements.
Applies to: Contractors with employees working outside the United States on public-work contracts or certain foreign assistance contracts.
What it requires
- Provide workers' compensation coverage as required by the Defense Base Act when it applies.
- If the Defense Base Act is waived, provide workers' compensation coverage against work injury or death and assume liability for war-hazard injury, death, capture, or detention for those employees.
Key terms: Public-work contract · Defense Base Act · Longshoremen's and Harbor Workers' Compensation Act · War Hazards Compensation Act · waiver
Written by AI from this section's text. A guide, not legal advice: the text below rules.
The text
(a) Public-work contract, as used in this subpart, means any contract for a fixed improvement or for any other project, fixed or not, for the public use of the United States or its allies, involving construction, alteration, removal, or repair, including projects or operations under service contracts and projects in connection with the national defense or with war activities, dredging, harbor improvements, dams, roadways, and housing, as well as preparatory and ancillary work in connection therewith at the site or on the project.
(b) The Defense Base Act (42 U.S.C. 1651 et seq.) extends the Longshoremen's and Harbor Workers' Compensation Act (33 U.S.C. 901) to various classes of employees working outside the United States, including those engaged in performing—
(1) Public-work contracts; or
(2) Contracts approved or financed under the Foreign Assistance Act of 1961 (Pub. L. 87-195) other than (i) contracts approved or financed by the Development Loan Fund (unless the Secretary of Labor, acting upon the recommendation of a department or agency, determines that such contracts should be covered) or (ii) contracts exclusively for materials or supplies.
(c) When the Defense Base Act applies (see 42 U.S.C. 1651 et seq.) to these employees, the benefits of the Longshoremen's and Harbor Workers' Compensation Act are extended through operation of the War Hazards Compensation Act (42 U.S.C. 1701 et seq.) to protect the employees against the risk of war hazards (injury, death, capture, or detention). When, by means of an insurance policy or a self-insurance program, the contractor provides the workers' compensation coverage required by the Defense Base Act, the contractor's employees automatically receive war-hazard risk protection.
(d) When the agency head recommends a waiver to the Secretary of Labor, the Secretary may waive the applicability of the Defense Base Act to any contract, subcontract, work location, or classification of employees.
(e) If the Defense Base Act is waived for some or all of the contractor's employees, the benefits of the War Hazards Compensation Act are automatically waived with respect to those employees for whom the Defense Base Act is waived. For those employees, the contractor shall provide workers' compensation coverage against the risk of work injury or death and assume liability toward the employees and their beneficiaries for war-hazard injury, death, capture, or detention. The contract shall provide either that the costs of this liability or the reasonable costs of insurance against this liability shall be allowed as a cost under the contract.
← 28.304 Risk-pooling arrangements. · 28.306 Insurance under fixed-price contracts. →
Rule changes for FAR Part 28
- Federal Acquisition Regulation: Revolutionary Federal Acquisition Regulation Overhaul Parts 14, 28, 36, and 52 ↗ · proposed 2026-09-18 · comments due 2026-10-19
- Federal Acquisition Regulation; Technical Amendments ↗ · final rule 2024-04-22 · effective 2024-05-22
Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗. Plain words for the terms: glossary.