FAR 31.205-31 Plant reconversion costs.
The codified text (eCFR, as of 2026-10-02). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule.
In plain English
This section says that costs to restore or rehabilitate a contractor's facilities back to their pre-contract condition are generally unallowable, except for costs of removing Government property and any restoration caused by that removal. Additional costs may be allowed only in special circumstances, and only to the extent agreed upon before the costs are incurred.
Applies to: Contractors incurring plant reconversion costs under Government contracts
What it requires
- Obtain agreement on any additional reconversion costs before those costs are incurred
- Avoid duplication of these costs through contingencies, additional profit or fee, or other contracts
Key terms: Plant reconversion costs · fair wear and tear · Government property · unallowable · contingencies
Written by AI from this section's text. A guide, not legal advice: the text below rules.
The text
Plant reconversion costs are those incurred in restoring or rehabilitating the contractor's facilities to approximately the same condition existing immediately before the start of the Government contract, fair wear and tear excepted. Reconversion costs are unallowable except for the cost of removing Government property and the restoration or rehabilitation costs caused by such removal. However, in special circumstances where equity so dictates, additional costs may be allowed to the extent agreed upon before costs are incurred. Care should be exercised to avoid duplication through allowance as contingencies, additional profit or fee, or in other contracts.
← 31.205-30 Patent costs. · 31.205-32 Precontract costs. →
Rule changes for FAR Part 31
- Federal Acquisition Regulation; Technical Amendments ↗ · final rule 2024-04-22 · effective 2024-05-22
Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗. Plain words for the terms: glossary.