FAR 32.503-9 Liquidation rates—alternate method.

The codified text (eCFR, as of 2026-10-02). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule.

In plain English

This section describes an alternate method for setting the liquidation rate on progress payments, allowing the contractor to keep the profit on completed items. The contracting officer may reduce the rate only if nine specific conditions are met, and must change it in certain situations. Any change requires a contract modification.

Applies to: Government contracts with progress payments where the contracting officer and contractor use the alternate liquidation rate method.

What it requires

  • The contractor must request a reduction in the liquidation rate.
  • The contractor must agree to certify annually, or more often if requested, that the alternate rate continues to meet the conditions in subsections 5, 6, and 7.
  • The certificate must be accompanied by adequate supporting information.
  • The contracting officer must issue a contract modification to specify the new rate in the Progress Payments clause whenever the liquidation rate is changed.

Key terms: liquidation rate · alternate method · progress payments · earned profit · contract modification

Written by AI from this section's text. A guide, not legal advice: the text below rules.

The text

(a) The liquidation rate determined under 32.503-8 shall apply throughout the period of contract performance unless the contracting officer adjusts the liquidation rate under the alternate method in this 32.503-9. The objective of the alternate liquidation rate method is to permit the contractor to retain the earned profit element of the contract prices for completed items in the liquidation process. The contracting officer may reduce the liquidation rate if—

(1) The contractor requests a reduction in the rate;

(2) The rate has not been reduced in the preceding 12 months;

(3) The contract delivery schedule extends at least 18 months from the contract award date;

(4) Data on actual costs are available (i) for the products delivered, or (ii) if no deliveries have been made, for a performance period of at least 12 months;

(5) The reduced liquidation rate would result in the Government recouping under each invoice the full extent of the progress payments applicable to the costs allocable to that invoice;

(6) The contractor would not be paid for more than the costs of items delivered and accepted (less allocable progress payments) and the earned profit on those items;

(7) The unliquidated progress payments would not exceed the limit prescribed in paragraph (a)(5) of the Progress Payments clause;

(8) The parties agree on an appropriate rate; and

(9) The contractor agrees to certify annually, or more often if requested by the contracting officer, that the alternate rate continues to meet the conditions of subsections 5, 6, and 7 above. The certificate must be accompanied by adequate supporting information.

(b) The contracting officer shall change the liquidation rate in the following circumstances:

(1) The rate shall be increased for both previous and subsequent transactions, if the contractor experiences a lower profit rate than the rate anticipated at the time the liquidation rate was established. Accordingly, the contracting officer shall adjust the progress payments associated with contract items already delivered, as well as subsequent progress payments.

(2) The rate shall be increased or decreased in keeping with the successive changes to the contract price or target profit when—

(i) The target profit is changed under a fixed-price incentive contract with successive targets; or

(ii) A redetermined price involves a change in the profit element under a contract with prospective price redetermination at stated intervals.

(c) Whenever the liquidation rate is changed, the contracting officer shall issue a contract modification to specify the new rate in the Progress Payments clause. Adequate consideration for these contract modifications is provided by the consideration included in the initial contract. The parties shall promptly make the payment or liquidation required in the circumstances.

Sections it refers to

  • 32.503-8 Liquidation rates—ordinary method.

Sections that refer to it

  • 32.110 Payment of subcontractors under cost-reimbursement prime contracts.
  • 32.501 General.
  • 32.502-4 Contract clauses.
  • 32.503-12 Maximum unliquidated amount.

← 32.503-8 Liquidation rates—ordinary method. · 32.503-10 Establishing alternate liquidation rates. →