FAR 36.213-4 Notice of award.
The codified text (eCFR, as of 2026-10-02). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule.
In plain English
This section explains how a contracting officer must issue a notice of award for construction contracts. It matters because the notice must be in writing or electronic, include required information, and tell the contractor about bonds and when work starts.
Applies to: Contracting officers issuing a notice of award under FAR part 36
What it requires
- Issue the notice of award in writing or electronically
- Include the information required by 14.408
- Identify the invitation for bids
- Identify the contractor's bid
Key terms: notice of award · invitation for bids · award price · payment and performance bonds · notice to proceed
Written by AI from this section's text. A guide, not legal advice: the text below rules.
The text
When a notice of award is issued, it shall be done in writing or electronically, shall contain information required by 14.408, and shall—
(a) Identify the invitation for bids;
(b) Identify the contractor's bid;
(c) State the award price;
(d) Advise the contractor that any required payment and performance bonds must be promptly executed and returned to the contracting officer;
(e) Specify the date of commencement of work, or advise that a notice to proceed will be issued.
Sections it refers to
- 14.408 Award.
← 36.213-3 Invitations for bids. · 36.214 Special procedures for price negotiation in construction contracting. →
Rule changes for FAR Part 36
- Federal Acquisition Regulation: Revolutionary Federal Acquisition Regulation Overhaul Parts 14, 28, 36, and 52 ↗ · proposed 2026-09-18 · comments due 2026-10-19
- Federal Acquisition Regulation: Inflation Adjustment of Acquisition-Related Thresholds ↗ · final rule 2025-08-27 · effective 2025-10-01
- Federal Acquisition Regulation; Technical Amendments ↗ · final rule 2024-12-16 · effective 2025-01-03
- Federal Acquisition Regulation: Inflation Adjustment of Acquisition-Related Thresholds ↗ · proposed 2024-11-29 · comments due 2025-01-28
- Federal Acquisition Regulation: Prohibition on the Use of Reverse Auctions for Complex, Specialized, or Substantial Design and Construction Services ↗ · proposed 2024-08-29 · comments due 2024-10-28
- Federal Acquisition Regulation: Sustainable Procurement ↗ · final rule 2024-04-22 · effective 2024-05-22
Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗. Plain words for the terms: glossary.