FAR and DFARS › FAR Part 36: Construction and Architect-engineer Contracts › Subpart 36.5
FAR 36.507 Permits and responsibilities.
The codified text (eCFR, as of 2026-10-02). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule.
In plain English
This section tells the contracting officer to include the Permits and Responsibilities clause (52.236-7) in certain construction and demolition-type solicitations and contracts. It matters to contractors because it signals that the clause will appear in those contracts, so they should review it when bidding.
Applies to: Contracting officers handling fixed-price or cost-reimbursement construction contracts, or fixed-price dismantling, demolition, or removal of improvements contracts
Key terms: contracting officer · 52.236-7, Permits and Responsibilities · fixed-price · cost-reimbursement · construction contract
Written by AI from this section's text. A guide, not legal advice: the text below rules.
The text
The contracting officer shall insert the clause at 52.236-7, Permits and Responsibilities, in solicitations and contracts when a fixed-price or cost-reimbursement construction contract or a fixed-price dismantling, demolition, or removal of improvements contract is contemplated.
Sections it refers to
- 52.236-7 Permits and Responsibilities.
Sections that refer to it
- 52.236-7 Permits and Responsibilities.
← 36.506 Superintendence by the contractor. · 36.508 Other contracts. →
Rule changes for FAR Part 36
- Federal Acquisition Regulation: Revolutionary Federal Acquisition Regulation Overhaul Parts 14, 28, 36, and 52 ↗ · proposed 2026-09-18 · comments due 2026-10-19
- Federal Acquisition Regulation: Inflation Adjustment of Acquisition-Related Thresholds ↗ · final rule 2025-08-27 · effective 2025-10-01
- Federal Acquisition Regulation; Technical Amendments ↗ · final rule 2024-12-16 · effective 2025-01-03
- Federal Acquisition Regulation: Inflation Adjustment of Acquisition-Related Thresholds ↗ · proposed 2024-11-29 · comments due 2025-01-28
- Federal Acquisition Regulation: Prohibition on the Use of Reverse Auctions for Complex, Specialized, or Substantial Design and Construction Services ↗ · proposed 2024-08-29 · comments due 2024-10-28
- Federal Acquisition Regulation: Sustainable Procurement ↗ · final rule 2024-04-22 · effective 2024-05-22
Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗. Plain words for the terms: glossary.