FAR 36.510 Operations and storage areas.

The codified text (eCFR, as of 2026-10-02). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule.

In plain English

This section tells contracting officers when to include the clause at 52.236-10, Operations and Storage Areas, in certain fixed-price construction or dismantling/demolition/removal contracts. It matters because the clause is mandatory when the expected contract amount exceeds the simplified acquisition threshold, and optional at or below that threshold.

Applies to: Contracting officers awarding fixed-price construction or dismantling, demolition, or removal of improvements contracts

What it requires

  • Insert the clause at 52.236-10 in solicitations and contracts when a fixed-price construction or fixed-price dismantling, demolition, or removal of improvements contract is contemplated and the contract amount is expected to exceed the simplified acquisition threshold

Key terms: 52.236-10 · Operations and Storage Areas · simplified acquisition threshold · fixed-price construction contract · dismantling, demolition, or removal of improvements

Written by AI from this section's text. A guide, not legal advice: the text below rules.

The text

The contracting officer shall insert the clause at 52.236-10, Operations ald Storage Areas, in solicitations and contracts when a fixed-price construction contract or a fixed-price dismantling, demolition, or removal of improvements contract is contemplated and the contract amount is expected to exceed the simplified acquisition threshold. The contracting officer may insert the clause in solicitations and contracts when a fixed-price construction or a fixed-price contract for dismantling, demolition, or removal of improvements is contemplated and the contract amount is expected to be at or below the simplified acquisition threshold.

Sections it refers to

Sections that refer to it

← 36.509 Protection of existing vegetation, structures, equipment, utilities, and improvements. · 36.511 Use and possession prior to completion. →

Rule changes for FAR Part 36

Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗. Plain words for the terms: glossary.