FAR 36.515 Schedules for construction contracts.
The codified text (eCFR, as of 2026-10-02). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule.
In plain English
This section tells contracting officers when they may include the Schedules for Construction Contracts clause (52.236-15) in a solicitation or contract. It matters to construction contractors because that clause can impose scheduling requirements on how work progress is planned and tracked.
Applies to: Fixed-price construction contracts meeting the stated conditions
Key terms: contracting officer · 52.236-15 · fixed-price construction contract · simplified acquisition threshold · period of actual work performance
Written by AI from this section's text. A guide, not legal advice: the text below rules.
The text
The contracting officer may insert the clause at 52.236-15, Schedules for Construction Contracts, in solicitations and contracts when a fixed-price construction contract is contemplated, the contract amount is expected to exceed the simplified acquisition threshold, and the period of actual work performance exceeds 60 days. This clause may also be inserted in such solicitations and contracts when work performance is expected to last less than 60 days and an unusual situation exists that warrants imposition of the requirements. This clause should not be used in the same contract with clauses covering other management approaches for ensuring that a contractor makes adequate progress.
Sections it refers to
- 52.236-15 Schedules for Construction Contracts.
Sections that refer to it
- 52.236-15 Schedules for Construction Contracts.
← 36.514 Availability and use of utility services. · 36.516 Quantity surveys. →
Rule changes for FAR Part 36
- Federal Acquisition Regulation: Revolutionary Federal Acquisition Regulation Overhaul Parts 14, 28, 36, and 52 ↗ · proposed 2026-09-18 · comments due 2026-10-19
- Federal Acquisition Regulation: Inflation Adjustment of Acquisition-Related Thresholds ↗ · final rule 2025-08-27 · effective 2025-10-01
- Federal Acquisition Regulation; Technical Amendments ↗ · final rule 2024-12-16 · effective 2025-01-03
- Federal Acquisition Regulation: Inflation Adjustment of Acquisition-Related Thresholds ↗ · proposed 2024-11-29 · comments due 2025-01-28
- Federal Acquisition Regulation: Prohibition on the Use of Reverse Auctions for Complex, Specialized, or Substantial Design and Construction Services ↗ · proposed 2024-08-29 · comments due 2024-10-28
- Federal Acquisition Regulation: Sustainable Procurement ↗ · final rule 2024-04-22 · effective 2024-05-22
Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗. Plain words for the terms: glossary.