FAR 36.609-3 Work oversight in architect-engineer contracts.

The codified text (eCFR, as of 2026-10-02). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule.

The text

The contracting officer shall insert the clause at 52.236-24, Work Oversight in Architect-Engineer Contracts, in all architect-engineer contracts.

Sections it refers to

  • 52.236-24 Work Oversight in Architect-Engineer Contracts.

Sections that refer to it

  • 52.236-24 Work Oversight in Architect-Engineer Contracts.

← 36.609-2 Redesign responsibility for design errors or deficiencies. · 36.609-4 Requirements for registration of designers. →

Rule changes for FAR Part 36

Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗. Plain words for the terms: glossary.

FAR 36.609-3 Work oversight in architect-engineer contracts · SpendQuery