FAR 44.202-2 Considerations.

The codified text (eCFR, as of 2026-10-02). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule.

In plain English

This section lists the factors a contracting officer must review when deciding whether to consent to a subcontract. It matters to contractors because it shows what the government will examine before approving a subcontract, including compliance with small business subcontracting requirements and cost or price analysis.

Applies to: Contracting officers responsible for consenting to subcontracts, and the prime contractors requesting that consent

What it requires

  • Review the request and supporting data
  • Consider whether the subcontracting decision is consistent with any approved make-or-buy program
  • Consider whether the contractor complied with prime contract requirements on small business subcontracting and purchases from nonprofit agencies designated by the Committee for Purchase From People Who Are Blind or Severely Disabled
  • Consider whether the contractor performed adequate cost or price analysis or price comparisons and obtained certified cost or pricing data and data other than certified cost or pricing data

Key terms: consent · make-or-buy program · small business subcontracting · certified cost or pricing data · System for Award Management

Written by AI from this section's text. A guide, not legal advice: the text below rules.

The text

(a) The contracting officer responsible for consent must, at a minimum, review the request and supporting data and consider the following:

(1) Is the decision to subcontract consistent with the contractor's approved make-or-buy program, if any (see 15.407-2)?

(2) Is the subcontract for special test equipment, equipment or real property that are available from Government sources?

(3) Is the selection of the particular supplies, equipment, or services technically justified?

(4) Has the contractor complied with the prime contract requirements regarding—

(i) Small business subcontracting, including, if applicable, its plan for subcontracting with small, veteran-owned, service-disabled veteran-owned, HUBZone, small disadvantaged and women-owned small business concerns (see part 19); and

(ii) Purchase from nonprofit agencies designated by the Committee for Purchase From People Who Are Blind or Severely Disabled (41 U.S.C. 8504) (see part 8)?

(5) Was adequate price competition obtained or its absence properly justified?

(6) Did the contractor adequately assess and dispose of subcontractors' alternate proposals, if offered?

(7) Does the contractor have a sound basis for selecting and determining the responsibility of the particular subcontractor?

(8) Has the contractor performed adequate cost or price analysis or price comparisons and obtained certified cost or pricing data and data other than certified cost or pricing data?

(9) Is the proposed subcontract type appropriate for the risks involved and consistent with current policy?

(10) Has adequate consideration been obtained for any proposed subcontract that will involve the use of Government-provided equipment and real property?

(11) Has the contractor adequately and reasonably translated prime contract technical requirements into subcontract requirements?

(12) Does the prime contractor comply with applicable cost accounting standards for awarding the subcontract?

(13) Is the proposed subcontractor listed as excluded in the System for Award Management (see subpart 9.4)?

(b) Particularly careful and thorough consideration under paragraph (a) above is necessary when—

(1) The prime contractor's purchasing system or performance is inadequate;

(2) Close working relationships or ownership affiliations between the prime and subcontractor may preclude free competition or result in higher prices;

(3) Subcontracts are proposed for award on a non-competitive basis, at prices that appear unreasonable, or at prices higher than those offered to the Government in comparable circumstances; or

(4) Subcontracts are proposed on a cost-reimbursement, time-and-materials, or labor-hour basis.

Sections it refers to

Sections that refer to it

← 44.202-1 Responsibilities. · 44.203 Consent limitations. →

Rule changes for FAR Part 44

Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗. Plain words for the terms: glossary.

FAR 44.202-2 Considerations · SpendQuery