FAR and DFARS › FAR Part 45: Government Property › Subpart 45.6
FAR 45.602-1 Inventory disposal schedules.
The codified text (eCFR, as of 2026-10-02). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule.
In plain English
This section sets timelines and procedures for plant clearance officers to review, accept, verify, and provide disposition instructions for contractor inventory disposal schedules. It also allows contractors to request removal of Government property from a schedule under certain conditions. Timely disposition instructions matter because failure to provide them may entitle the contractor to an equitable adjustment.
Applies to: Plant clearance officers and contractors managing Government property inventory disposal schedules
What it requires
- Plant clearance officers should review and accept, or return for correction, inventory disposal schedules within 10 days of receipt.
- Plant clearance officers shall use Standard Form 1423 to verify accepted schedules within 20 days following acceptance.
- Plant clearance officers shall require the contractor to correct any discrepancies found during verification.
- Plant clearance officers shall require the contractor to correct any failure to complete predisposal requirements of the contract.
Key terms: inventory disposal schedules · plant clearance officers · Standard Form 1428 · Standard Form 1423 · equitable adjustment
Written by AI from this section's text. A guide, not legal advice: the text below rules.
The text
(a) Plant clearance officers should review and accept, or return for correction, inventory disposal schedules within 10 days following receipt from a contractor. Schedules that are completed in accordance with the instructions for Standard Form 1428 should be accepted.
(b) Plant clearance officers shall—
(1) Use Standard Form 1423 to verify, in accordance with agency procedures, accepted schedules within 20 days following acceptance;
(2) Require the contractor to correct any discrepancies found during verification;
(3) Require the contractor to correct any failure to complete predisposal requirements of the contract; and
(4) Provide the contractor disposition instructions for property identified on an acceptable inventory disposal schedule within 120 days. A failure to provide timely disposition instructions may entitle the contractor to an equitable adjustment.
(c) The contractor may request the plant clearance officer's approval to remove the Government property from an inventory schedule.
(1) Plant clearance officers should approve removal of Government property from an inventory schedule when—
(i) The contractor wishes to purchase a contractor-acquired or contractor-produced item at unit acquisition cost and credit the contract;
(ii) The contractor is able to return unused property to the supplier at fair market value and credit the contract (less, if applicable, a reasonable restocking fee that is consistent with the supplier's customary practices);
(iii) The Government has authorized the contractor to use the property on another Government contract; or
(iv) The contractor has requested continued use of the Government property, and the contracting officer has authorized its retention and further use.
(2) If the screening process (see 45.602-3) has not begun, the plant clearance officer shall adjust the schedule or return the schedule to the contractor for correction. If screening has begun, the plant clearance officer shall promptly notify the activity performing the screening that the items should be removed from the screening process.
Sections it refers to
- 45.602-3 Screening.
← 45.602 Reutilization of Government property. · 45.602-2 Reutilization priorities. →
Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗. Plain words for the terms: glossary.