FAR 52.211-9 Desired and Required Time of Delivery.

The codified text (eCFR, as of 2026-10-02). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule.

In plain English

This clause sets out the Government's desired and required delivery schedules for a contract. An offeror may propose a different delivery schedule, but it cannot extend beyond the required delivery schedule, and offers that do not clearly fall within the required delivery period will be rejected as nonresponsive. The clause also explains how to compute the time available for performance based on the actual date of award, not the date the notice is received.

Applies to: Offerors and contractors responding to solicitations that include this clause.

What it requires

  • Propose a delivery schedule that does not extend beyond the Government's required delivery schedule.
  • Compute the time available for performance beginning with the actual date of award, not the date the notice of award is received.
  • If proposing delivery based on receipt of the contract or notice of award, add five calendar days for ordinary mail or one working day for electronic transmission when computing the offered delivery date.

Key terms: desired delivery schedule · required delivery schedule · offeror's proposed delivery schedule · nonresponsive · working day

Written by AI from this section's text. A guide, not legal advice: the text below rules.

The text

As prescribed in 11.404(a)(3), insert the following clause:

Desired and Required Time of Delivery (JUN 1997)

(a) The Government desires delivery to be made according to the following schedule:

DESIRED DELIVERY SCHEDULE

[Contracting Officer insert specific details]

If the offeror is unable to meet the desired delivery schedule, it may, without prejudicing evaluation of its offer, propose a delivery schedule below. However, the offeror's proposed delivery schedule must not extend the delivery period beyond the time for delivery in the Government's required delivery schedule as follows:

REQUIRED DELIVERY SCHEDULE

[Contracting Officer insert specific details]

Offers that propose delivery of a quantity under such terms or conditions that delivery will not clearly fall within the applicable required delivery period specified above, will be considered nonresponsive and rejected. If the offeror proposes no other delivery schedule, the desired delivery schedule above will apply.

OFFEROR'S PROPOSED DELIVERY SCHEDULE

(b) Attention is directed to the Contract Award provision of the solicitation that provides that a written award or acceptance of offer mailed or otherwise furnished to the successful offeror results in a binding contract. The Government will mail or otherwise furnish to the offeror an award or notice of award not later than the day the award is dated. Therefore, the offeror shall compute the time available for performance beginning with the actual date of award, rather than the date the written notice of award is received from the Contracting Officer through the ordinary mails. However, the Government will evaluate an offer that proposes delivery based on the Contractor's date of receipt of the contract or notice of award by adding (1) five calendar days for delivery of the award through the ordinary mails, or (2) one working day if the solicitation states that the contract or notice of award will be transmitted electronically. (The term working day excludes weekends and U.S. Federal holidays.) If, as so computed, the offered delivery date is later than the required delivery date, the offer will be considered nonresponsive and rejected.

(End of clause)

Alternate I (APR 1984). If the delivery schedule is expressed in terms of specific calendar dates or specific periods and is based on an assumed date of award, the contracting officer may substitute the following paragraph (b) for paragraph (b) of the basic clause. The time may be expressed by substituting on or before; during the months __; or not sooner than __, or later than __ as headings for the third column of paragraph (a) of the basic clause.

(b) The delivery dates or specific periods above are based on the assumption that the Government will make award by __ [Contracting Officer insert date]. Each delivery date in the delivery schedule above will be extended by the number of calendar days after the above date that the contract is in fact awarded. Attention is directed to the Contract Award provision of the solicitation that provides that a written award or acceptance of offer mailed or otherwise furnished to the successful offeror results in a binding contract. Therefore, the offeror shall compute the time available for performance beginning with the actual date of award, rather than the date the written notice of award is received from the Contracting Officer through the ordinary mails.

Alternate II (APR 1984). If the delivery schedule is expressed in terms of specific calendar dates or specific periods and is based on an assumed date the contractor receives notice of award, the contracting officer may substitute the following paragraph (b) for paragraph (b) of the basic clause. The time may be expressed by substituting within days after the date of receipt of a written notice of award as the heading of the third column of paragraph (a) of the basic clause.

(b) The delivery dates or specific periods above are based on the assumption that the successful offeror will receive notice of award by __ [Contracting Officer insert date]. Each delivery date in the delivery schedule above will be extended by the number of calendar days after the above date that the Contractor receives notice of award; provided, that the Contractor promptly acknowledges receipt of notice of award.

Alternate III (APR 1984). If the delivery schedule is to be based on the actual date the contractor receives a written notice of award, the contracting officer may delete paragraph (b) of the basic clause. The time may be expressed by substituting within days after the date of receipt of a written notice of award as the heading of the third column of paragraph (a) of the basic clause.

Sections it refers to

Sections that refer to it

← 52.211-8 Time of Delivery. · 52.211-10 Commencement, Prosecution, and Completion of Work. →