FAR and DFARS › FAR Part 52: Solicitation Provisions and Contract Clauses › Subpart 52.2
FAR 52.214-22 Evaluation of Bids for Multiple Awards.
The codified text (eCFR, as of 2026-10-02). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule.
In plain English
This provision tells bidders that the Government may make more than one award under a solicitation, and that bids will be evaluated on the advantages and disadvantages of doing so. For evaluation purposes, the Government assumes a $500 administrative cost for each contract awarded, and awards go to the items or combinations that produce the lowest total cost to the Government including those assumed costs.
Applies to: Bidders on solicitations that allow multiple awards
Key terms: multiple awards · administrative cost · lowest aggregate cost · solicitation
Written by AI from this section's text. A guide, not legal advice: the text below rules.
The text
As prescribed in 14.201-6(q), insert the following provision:
Evaluation of Bids for Multiple Awards (MAR 1990)
In addition to other factors, bids will be evaluated on the basis of advantages and disadvantages to the Government that might result from making more than one award (multiple awards). It is assumed, for the purpose of evaluating bids, that $500 would be the administrative cost to the Government for issuing and administering each contract awarded under this solicitation, and individual awards will be for the items or combinations of items that result in the lowest aggregate cost to the Government, including the assumed administrative costs.
(End of provision)
Sections it refers to
- 14.201-6 Solicitation provisions.
Sections that refer to it
- 14.201-6 Solicitation provisions.
← 52.214-21 Descriptive Literature. · 52.214-23 Late submissions, modifications, revisions, and withdrawals of technical proposals under two-step sealed bidding. →
Rule changes for FAR Part 52
- Federal Acquisition Regulation: Revolutionary FAR Overhaul Parts 8, 12, 13, 15, 38, 44, and 51 ↗ · proposed 2026-09-18 · comments due 2026-10-19
- Federal Acquisition Regulation: Revolutionary Federal Acquisition Regulation Overhaul Parts 16, 17, and 35 ↗ · proposed 2026-09-18 · comments due 2026-10-19
- Federal Acquisition Regulation: Revolutionary Federal Acquisition Regulation Overhaul Parts 9, 27, and 47 ↗ · proposed 2026-09-18 · comments due 2026-10-19
- Federal Acquisition Regulation: Revolutionary Federal Acquisition Regulation Overhaul Parts 14, 28, 36, and 52 ↗ · proposed 2026-09-18 · comments due 2026-10-19
- Federal Acquisition Regulation: Revolutionary Federal Acquisition Regulation Overhaul Parts 3 and 49 ↗ · proposed 2026-06-23 · comments due 2026-07-23
- Federal Acquisition Regulation: Revolutionary Federal Acquisition Regulation Overhaul Parts 5, 24, and 29 ↗ · proposed 2026-06-23 · comments due 2026-07-23
- Federal Acquisition Regulation: Revolutionary Federal Acquisition Regulation Overhaul Parts 6, 7, 10, 18, 26, 37, and 41 ↗ · proposed 2026-06-23 · comments due 2026-07-23
- Federal Acquisition Regulation: Revolutionary Federal Acquisition Regulation Overhaul Parts 1, 2, 4, 33, 39, 40, and 53 ↗ · proposed 2026-06-23 · comments due 2026-07-23
Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗. Plain words for the terms: glossary.