FAR and DFARS › FAR Part 52: Solicitation Provisions and Contract Clauses › Subpart 52.2
FAR 52.234-2 Notice of Earned Value Management System—Preaward Integrated Baseline Review.
The codified text (eCFR, as of 2026-10-02). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule.
In plain English
This provision requires offerors to show that their proposed earned value management system (EVMS) complies with EIA-748 guidelines, or to submit a plan to achieve compliance. It also requires the Government to conduct an Integrated Baseline Review before contract award to jointly assess the contractor's planning and ensure complete coverage of contract requirements.
Applies to: Offerors responding to solicitations that include this provision
What it requires
- Provide documentation that the Cognizant Federal Agency has determined the proposed EVMS complies with EIA-748 guidelines.
- If the system is not compliant, submit a comprehensive plan for compliance that includes the specified elements.
- Provide information and assistance as required by the Contracting Officer to support review of the plan.
- Identify major subcontractors or major subcontracted effort subject to the guidelines.
Key terms: Earned Value Management System (EVMS) · EIA-748 · Integrated Baseline Review (IBR) · Cognizant Federal Agency · BCWP
Written by AI from this section's text. A guide, not legal advice: the text below rules.
The text
As prescribed in 34.203(a) use the following provision:
Notice of Earned Value Management System—Preaward Integrated Baseline Review (NOV 2016)
(a) The offeror shall provide documentation that the Cognizant Federal Agency has determined that the proposed earned value management system (EVMS) complies with the EVMS guidelines in Electronic Industries Alliance Standard 748 (EIA-748) (current version at time of solicitation).
(b) If the offeror proposes to use a system that has not been determined to be in compliance with the requirements of paragraph (a) of this provision, the offeror shall submit a comprehensive plan for compliance with the EVMS guidelines.
(1) The plan shall—
(i) Describe the EVMS the offeror intends to use in performance of the contracts;
(ii) Distinguish between the offeror's existing management system and modifications proposed to meet the guidelines;
(iii) Describe the management system and its application in terms of the EVMS guidelines;
(iv) Describe the proposed procedure for administration of the guidelines, as applied to subcontractors; and
(v) Provide documentation describing the process and results of any third-party or self-evaluation of the system's compliance with the EVMS guidelines.
(2) The offeror shall provide information and assistance as required by the Contracting Officer to support review of the plan.
(3) The Government will review and approve the offeror's plan for an EVMS before contract award.
(4) The offeror's EVMS plan must provide milestones that indicate when the offeror anticipates that the EVM system will be compliant with the EIA-748 guidelines.
(c) Offerors shall identify the major subcontractors, or major subcontracted effort if major subcontractors have not been selected subject to the guidelines. The prime Contractor and the Government shall agree to subcontractors selected for application of the EVMS guidelines.
(d) The Government will conduct an Integrated Baseline Review (IBR), as designated by the agency, prior to contract award. The objective of the IBR is for the Government and the Contractor to jointly assess technical areas, such as the Contractor's planning, to ensure complete coverage of the contract requirements, logical scheduling of the work activities, adequate resources, methodologies for earned value (budgeted cost for work performed (BCWP)), and identification of inherent risks.
(End of provision)
Sections it refers to
- 34.203 Solicitation provisions and contract clause.
← 52.234-1 Industrial Resources Developed Under Title III, Defense Production Act. · 52.234-3 Notice of Earned Value Management System—Postaward Integrated Baseline Review. →
Rule changes for FAR Part 52
- Federal Acquisition Regulation: Revolutionary FAR Overhaul Parts 8, 12, 13, 15, 38, 44, and 51 ↗ · proposed 2026-09-18 · comments due 2026-10-19
- Federal Acquisition Regulation: Revolutionary Federal Acquisition Regulation Overhaul Parts 16, 17, and 35 ↗ · proposed 2026-09-18 · comments due 2026-10-19
- Federal Acquisition Regulation: Revolutionary Federal Acquisition Regulation Overhaul Parts 9, 27, and 47 ↗ · proposed 2026-09-18 · comments due 2026-10-19
- Federal Acquisition Regulation: Revolutionary Federal Acquisition Regulation Overhaul Parts 14, 28, 36, and 52 ↗ · proposed 2026-09-18 · comments due 2026-10-19
- Federal Acquisition Regulation: Revolutionary Federal Acquisition Regulation Overhaul Parts 3 and 49 ↗ · proposed 2026-06-23 · comments due 2026-07-23
- Federal Acquisition Regulation: Revolutionary Federal Acquisition Regulation Overhaul Parts 5, 24, and 29 ↗ · proposed 2026-06-23 · comments due 2026-07-23
- Federal Acquisition Regulation: Revolutionary Federal Acquisition Regulation Overhaul Parts 6, 7, 10, 18, 26, 37, and 41 ↗ · proposed 2026-06-23 · comments due 2026-07-23
- Federal Acquisition Regulation: Revolutionary Federal Acquisition Regulation Overhaul Parts 1, 2, 4, 33, 39, 40, and 53 ↗ · proposed 2026-06-23 · comments due 2026-07-23
Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗. Plain words for the terms: glossary.