FAR 52.236-6 Superintendence by the Contractor.

The codified text (eCFR, as of 2026-10-02). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule.

In plain English

This clause requires the contractor to directly supervise the work, or to assign a competent superintendent who is acceptable to the Contracting Officer and authorized to act for the contractor. This matters because the contractor must keep qualified supervision on the job throughout performance until the work is completed and accepted.

Applies to: Contractors performing work under this contract

What it requires

  • Directly superintend the work or assign and have on the work a competent superintendent
  • Ensure the superintendent is satisfactory to the Contracting Officer
  • Ensure the superintendent has authority to act for the Contractor
  • Maintain this supervision at all times during performance and until the work is completed and accepted

Key terms: superintend · competent superintendent · Contracting Officer · authority to act for the Contractor · completed and accepted

Written by AI from this section's text. A guide, not legal advice: the text below rules.

The text

As prescribed in 36.506, insert the following clause:

Superintendence by the Contractor (APR 1984)

At all times during performance of this contract and until the work is completed and accepted, the Contractor shall directly superintend the work or assign and have on the work a competent superintendent who is satisfactory to the Contracting Officer and has authority to act for the Contractor.

(End of clause)

Sections it refers to

  • 36.506 Superintendence by the contractor.

Sections that refer to it

  • 36.506 Superintendence by the contractor.

← 52.236-5 Material and Workmanship. · 52.236-7 Permits and Responsibilities. →

Rule changes for FAR Part 52

Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗. Plain words for the terms: glossary.

FAR 52.236-6 Superintendence by the Contractor · SpendQuery