FAR 52.247-35 F.o.b. Destination, Within Consignee's Premises.
The codified text (eCFR, as of 2026-10-02). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule.
In plain English
This clause defines what 'f.o.b. destination, within consignee's premises' means: the contractor delivers the goods free of expense to the Government, laid down inside the consignee's premises, including specific rooms if specified. It matters because the contractor bears responsibility for loss or damage until the consignee receives the shipment at the delivery point, and must pay all charges to that point.
Applies to: Contractors under solicitations and contracts where the delivery term is f.o.b. destination, within consignee's premises
What it requires
- Pack and mark the shipment to comply with contract specifications, or if none, prepare it per carrier requirements
- Prepare and distribute commercial bills of lading
- Deliver the shipment in good order and condition to the contract's specified delivery point
- Be responsible for loss or damage to the goods before the consignee receives them at the delivery point
Key terms: f.o.b. destination, within consignee's premises · consignee's premises · commercial bills of lading · delivery point · delivering carrier
Written by AI from this section's text. A guide, not legal advice: the text below rules.
The text
As prescribed in 47.303-7(c), insert the following clause in solicitations and contracts when the delivery term is f.o.b. destination, within consignee's premises:
F.o.b. Destination, Within Consignee's Premises (APR 1984)
(a) The term f.o.b. destination, within consignee's premises, as used in this clause, means free of expense to the Government delivered and laid down within the doors of the consignee's premises, including delivery to specific rooms within a building if so specified.
(b) The Contractor shall—
(1)(i) Pack and mark the shipment to comply with contract specifications; or
(ii) In the absence of specifications, prepare the shipment in conformance with carrier requirements;
(2) Prepare and distribute commercial bills of lading;
(3) Deliver the shipment in good order and condition to the point of delivery specified in the contract;
(4) Be responsible for any loss of and/or damage to the goods occurring before receipt of the shipment by the consignee at the delivery point specified in the contract;
(5) Furnish a delivery schedule and designate the mode of delivering carrier; and
(6) Pay and bear all charges to the specified point of delivery.
(End of clause)
Sections it refers to
- 47.303-7 F.o.b. destination, within consignee's premises.
Sections that refer to it
- 47.303-7 F.o.b. destination, within consignee's premises.
← 52.247-34 F.o.b. Destination. · 52.247-36 F.a.s. Vessel, Port of Shipment. →
Rule changes for FAR Part 52
- Federal Acquisition Regulation: Revolutionary FAR Overhaul Parts 8, 12, 13, 15, 38, 44, and 51 ↗ · proposed 2026-09-18 · comments due 2026-10-19
- Federal Acquisition Regulation: Revolutionary Federal Acquisition Regulation Overhaul Parts 16, 17, and 35 ↗ · proposed 2026-09-18 · comments due 2026-10-19
- Federal Acquisition Regulation: Revolutionary Federal Acquisition Regulation Overhaul Parts 9, 27, and 47 ↗ · proposed 2026-09-18 · comments due 2026-10-19
- Federal Acquisition Regulation: Revolutionary Federal Acquisition Regulation Overhaul Parts 14, 28, 36, and 52 ↗ · proposed 2026-09-18 · comments due 2026-10-19
- Federal Acquisition Regulation: Revolutionary Federal Acquisition Regulation Overhaul Parts 3 and 49 ↗ · proposed 2026-06-23 · comments due 2026-07-23
- Federal Acquisition Regulation: Revolutionary Federal Acquisition Regulation Overhaul Parts 5, 24, and 29 ↗ · proposed 2026-06-23 · comments due 2026-07-23
- Federal Acquisition Regulation: Revolutionary Federal Acquisition Regulation Overhaul Parts 6, 7, 10, 18, 26, 37, and 41 ↗ · proposed 2026-06-23 · comments due 2026-07-23
- Federal Acquisition Regulation: Revolutionary Federal Acquisition Regulation Overhaul Parts 1, 2, 4, 33, 39, 40, and 53 ↗ · proposed 2026-06-23 · comments due 2026-07-23
Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗. Plain words for the terms: glossary.