FAR 52.249-14 Excusable Delays.
The codified text (eCFR, as of 2026-10-02). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule.
In plain English
This clause protects a contractor from being found in default when a failure to perform is caused by events beyond the contractor's control and without its fault or negligence, such as acts of God, Government acts, fires, floods, epidemics, strikes, or unusually severe weather. It also addresses failures caused by subcontractors, with limited exceptions. If the Contracting Officer confirms such a cause, the delivery schedule is revised, subject to the Government's termination rights.
Applies to: Contractors under cost-reimbursement, time-and-material, labor-hour, and certain supply, service, construction, and R&D contracts where the clause is inserted
What it requires
- The Contractor must show the failure to perform was beyond its control and without its fault or negligence
- If a subcontractor's failure caused the delay, the Contractor must show the cause was beyond the control of both the Contractor and subcontractor and without fault or negligence of either
- The Contractor may request the Contracting Officer to ascertain the facts and extent of the failure
Key terms: excusable delays · default · beyond the control · fault or negligence · delivery schedule
Written by AI from this section's text. A guide, not legal advice: the text below rules.
The text
As prescribed in 49.505(b), insert the following clause in solicitations and contracts for supplies, services, construction, and research and development on a fee basis whenever a cost-reimbursement contract is contemplated. Also insert the clause in time-and-material contracts, and labor-hour contracts. When used in construction contracts, substitute the words “completion time” for “delivery schedule” in the last sentence of the clause.
Excusable Delays (APR 1984)
(a) Except for defaults of subcontractors at any tier, the Contractor shall not be in default because of any failure to perform this contract under its terms if the failure arises from causes beyond the control and without the fault or negligence of the Contractor. Examples of these causes are (1) acts of God or of the public enemy, (2) acts of the Government in either its sovereign or contractual capacity, (3) fires, (4) floods, (5) epidemics, (6) quarantine restrictions, (7) strikes, (8) freight embargoes, and (9) unusually severe weather. In each instance, the failure to perform must be beyond the control and without the fault or negligence of the Contractor. Default includes failure to make progress in the work so as to endanger performance.
(b) If the failure to perform is caused by the failure of a subcontractor at any tier to perform or make progress, and if the cause of the failure was beyond the control of both the Contractor and subcontractor, and without the fault or negligence of either, the Contractor shall not be deemed to be in default, unless—
(1) The subcontracted supplies or services were obtainable from other sources;
(2) The Contracting Officer ordered the Contractor in writing to purchase these supplies or services from the other source; and
(3) The Contractor failed to comply reasonably with this order.
(c) Upon request of the Contractor, the Contracting Officer shall ascertain the facts and extent of the failure. If the Contracting Officer determines that any failure to perform results from one or more of the causes above, the delivery schedule shall be revised, subject to the rights of the Government under the termination clause of this contract.
(End of clause)
Sections it refers to
- 49.505 Other termination clauses.
Sections that refer to it
- 49.505 Other termination clauses.
← 52.249-13 [Reserved] · 52.250-1 Indemnification Under Public Law 85-804. →
Rule changes for FAR Part 52
- Federal Acquisition Regulation: Revolutionary FAR Overhaul Parts 8, 12, 13, 15, 38, 44, and 51 ↗ · proposed 2026-09-18 · comments due 2026-10-19
- Federal Acquisition Regulation: Revolutionary Federal Acquisition Regulation Overhaul Parts 16, 17, and 35 ↗ · proposed 2026-09-18 · comments due 2026-10-19
- Federal Acquisition Regulation: Revolutionary Federal Acquisition Regulation Overhaul Parts 9, 27, and 47 ↗ · proposed 2026-09-18 · comments due 2026-10-19
- Federal Acquisition Regulation: Revolutionary Federal Acquisition Regulation Overhaul Parts 14, 28, 36, and 52 ↗ · proposed 2026-09-18 · comments due 2026-10-19
- Federal Acquisition Regulation: Revolutionary Federal Acquisition Regulation Overhaul Parts 3 and 49 ↗ · proposed 2026-06-23 · comments due 2026-07-23
- Federal Acquisition Regulation: Revolutionary Federal Acquisition Regulation Overhaul Parts 5, 24, and 29 ↗ · proposed 2026-06-23 · comments due 2026-07-23
- Federal Acquisition Regulation: Revolutionary Federal Acquisition Regulation Overhaul Parts 6, 7, 10, 18, 26, 37, and 41 ↗ · proposed 2026-06-23 · comments due 2026-07-23
- Federal Acquisition Regulation: Revolutionary Federal Acquisition Regulation Overhaul Parts 1, 2, 4, 33, 39, 40, and 53 ↗ · proposed 2026-06-23 · comments due 2026-07-23
Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗. Plain words for the terms: glossary.