FAR 7.107-5 Notifications.

The codified text (eCFR, as of 2026-10-02). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule.

In plain English

This section requires agencies to notify current small business contractors, the public, and the SBA before bundling or consolidating contract requirements. It also requires public posting of the rationale for such actions and annual reporting on bundled requirements. These notifications give small businesses advance notice and information about opportunities to compete or team.

Applies to: Contracting officers, agencies, and small business contractors affected by bundling or consolidation of contract requirements.

What it requires

  • Notify each small business performing a contract of intent to bundle at least 30 days before solicitation issuance.
  • Include SBA procurement center representative contact information in the notification.
  • Document the notification in the contract file.
  • For follow-on bundled or consolidated requirements, obtain specified information and notify the SBA PCR at least 30 days before solicitation issuance.

Key terms: bundling · consolidation of contract requirements · substantial bundling · SBA procurement center representative (PCR) · GPE

Written by AI from this section's text. A guide, not legal advice: the text below rules.

The text

(a) Notifications to current small business contractors of agency's intent to bundle. (1) The contracting officer shall notify each small business performing a contract that it intends to bundle the requirement at least 30 days prior to the issuance of the solicitation for the bundled requirement.

(2) The notification shall provide the name, phone number and address of the applicable SBA procurement center representative (PCR), or if an SBA PCR is not assigned to the procuring activity, the SBA Office of Government Contracting Area Office serving the area in which the buying activity is located.

(3) This notification shall be documented in the contract file.

(b) Notification to the public of rationale for bundled requirement. The agency is encouraged to provide notification of the rationale for any bundled requirement to the GPE, before issuance of the solicitation (see 5.201).

(c) Notification to the public of consolidation of contract requirements. The SPE or CAO shall publish in the GPE—

(1) A notice that the agency has determined a consolidation of contract requirements is necessary and justified (see 7.107-2) no later than 7 days after making the determination; the solicitation may not be publicized prior to 7 days after publication of the notice of the agency determination; and

(2) The determination that consolidation is necessary and justified with the publication of the solicitation. See 7.107-2 for the required content of the determination.

(d) Notification to the public of substantial bundling of contract requirements. The head of the agency shall publish in the GPE—

(1) A notice that the agency has determined that a procurement involves substantial bundling (see 7.107-4) no later than 7 days after such determination has been made; the solicitation may not be publicized prior to 7 days after the publication of the notice of the determination; and

(2) The rationale for substantial bundling with the publication of the solicitation. The rationale is the information required for inclusion in the acquisition strategy at 7.107-4(b).

(e) Notification to SBA of follow-on bundled or consolidated requirements. For each follow-on bundled or consolidated requirement, the contracting officer shall obtain the following from the requiring activity and notify the SBA PCR no later than 30 days prior to issuance of the solicitation:

(1) The amount of savings and benefits achieved under the prior consolidation or bundling.

(2) Whether such savings and benefits will continue to be realized if the contract remains consolidated or bundled.

(3) Whether such savings and benefits would be greater if the procurement requirements were divided into separate solicitations suitable for award to small business concerns.

(4) List of requirements that have been added or deleted for the follow-on.

(f) Annual notification to the public of the rationale for bundled requirements. The agency shall publish on its website a list and rationale for any bundled requirement for which the agency solicited offers or issued an award. The notification shall be made annually within 30 days of the agency's data certification regarding the validity and verification of data entered in the Federal Procurement Data System to the Office of Federal Procurement Policy (see 4.604).

(g) Notification to public of bundling policy. In accordance with 15 U.S.C. 644(q)(2)(A)(ii), agencies shall publish the Governmentwide policy regarding contract bundling, including regarding the solicitation of teaming and joint ventures, on their agency website.

Sections it refers to

Sections that refer to it

← 7.107-4 Substantial bundling. · 7.107-6 Solicitation provision. →

Rule changes for FAR Part 7

Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗. Plain words for the terms: glossary.

FAR 7.107-5 Notifications · SpendQuery