Contracting office · 1240LT

USDA-FS, CSA Intermountain 8

Forest Service · Department of Agriculture

USDA-FS, CSA Intermountain 8 (contracting office 1240LT, Forest Service) obligated $71.14M on contracts in FY2026 so far. It buys mostly highway, street, and bridge construction, most from Jackson Excavation Inc. It has 163 active contracts worth $89.19M. Of its 545 competed contracts in the last three years, 17% drew a single offer.

Key facts · data as of Nov 14, 2026

Obligations, FY2026 so far
$71.14M
Active contracts
163, $89.19M
Buys most
Highway, Street, and Bridge Construction
Largest vendor
Jackson Excavation Inc ($8.00M)
Competed contracts with one offer
17%
Open notices now
2

Source: USAspending.gov prime contract awards (obligations: money committed, net of de-obligations) and SAM.gov notices, data as of Nov 14, 2026.

Cite this page: SpendQuery, USDA-FS, CSA Intermountain 8 (1240LT) federal contracts, data as of Nov 14, 2026, https://spendquery.com/office?code=1240LT

This USDA Forest Service office mostly buys highway, street, and bridge construction, with $36.26M of its $71.14M in FY2026 obligations going there. Its largest vendors that year were Jackson Excavation Inc ($8.00M) and Veritas Facility Services and Construction, Inc ($4.03M). It usually buys through contract vehicles (IDVs), and 17% of its 545 competed contracts over the last three years drew only one offer. (AI summary of the numbers on this page, checked against them; how)

At a glance

  • 163 active contracts, $89.19M
  • 17% of its 545 competed contracts drew a single offer (last 3 years)
  • Usually buys through: Contract vehicle (IDV) itself
  • Posts the follow-on notice a median 210 days before a contract ends (middle half: 377 to 30 days; 35 contracts)
  • Gives a median 29 days to respond (126 solicitations, last 3 years)
  • Amends 85% of its solicitations at least once
  • A median 51 days from the first notice to the award notice (12 awards)

Money by year

  • FY2023$56.72M
  • FY2024$42.93M
  • FY2025$42.03M
  • FY2026$71.14M

Obligations (money committed) in prime awards, from USAspending.gov.

Who wins here

Open to newcomers 17% of its 128 contracts since FY2025 went to a company's first win since 2023; 42% to companies with 5 wins or fewer.

  • First win since 2023: 22
  • 2nd–5th win: 32
  • 6th–10th win: 15
  • More than 10 wins: 59

A win = a contract or order of $10,000 or more; a company counts with its subsidiaries. Our contract data starts with FY2023, so “first” means first since 2023. Orders under someone's IDIQ, GWAC or BPA count toward a company's wins but not in the shares.

Contracts ending in the next 12 months

20 contracts, $50.06M with options. The largest:

ContractIncumbentEndsValue with options
1240LT26P0013
0401 LUCERNE CAMPGROUND CONSTRUCTION PHASE 5
Advanced Solutions Group, LLC2026-11-30$2.00M
1240LT25C0021
GAOA JOES VALLEY CAMPGROUND RESTORATION
Big Duke Construction LLC2026-11-30$1.14M
1240LT25C0016
BUFFALO CREEK WORK CENTER OFFICE & ENGINE STORAGE ADDITIONS PSICC NATIONAL FOREST
Iicon Construction Colorado, LLC2027-01-18$3.32M
1240LT26P0033
GAOA RED CANYON CORRIDOR PAVING AND CAMPGROUND RESTORATION PROJECT, ASHLEY NATIONAL FOREST
Guardian Construction, Inc.2027-01-18$2.84M
1240LT26C0003
REPLACEMENT OF WEST MUDDY CREEK BRIDGES #4 AND #5 PER DRAWINGS AND SPECIFICATIONS. GRAND MESA, UNCOMPAHGRE AND GUNNISON NF
GCS LLC2027-01-30$2.40M
1240LT26P0023
GAOA CHILAO CAMPGROUND COMPLEX - WATER SYSTEM REHABILITATION, ANGELES NATIONAL FOREST
E2 Contracting, Inc.2027-02-15$2.91M
1240LT26C0038
MOUNTAIN SPRINGS FIRE COMPLEX DESIGN DOCUMENT DEVELOPMENT FY26 THIS PROJECT IS TO DESIGN THE NEW MOUNTAIN SPRINGS FIRE COMPLEX THROUGH AN A/E FIRM. PROJECT IS LOCATED NEAR THE INTERSECTION OF LOVELL CANYON ROAD AND NEVADA STATE HIGHWAY 160 NEAR MOUN
Lga Architecture2027-02-15$1.15M
1240LT26F0069Cutting Edge Contractors Inc2027-03-28$1.47M
1240LT26F0004
GAOA COTTONWOOD BRIDGE REPLACEMENT
Meridian Engineering Co2027-05-20$1.37M
1240LT26C0005
THIS GAOA PROJECT WILL MAKE IMPROVEMENTS TO THE ROAD - TO INCLUDE DESIGN, CONSTRUCTION AND RESURFACING. PACTOLA CAMPGROUND LOOP B WILL BE RECONSTRUCTED TO INCREASE CAPACITY, IMPROVE THE WATER SYSTEM, AND IMPROVE HOST SITES WITH REPAIRED SEWAGE VAULTS
Quality Driven Service LLC2027-05-20$1.31M

All of them, with filters →

Open notices

All 2 open notices →

From USAspending.gov prime awards and SAM.gov notices. Sources and limits