Contracting office · 1240LU
Usda-Fs, Csa Intermountain 9
Forest Service · Department of Agriculture
At a glance
- 174 active contracts, $69.81M
- 15% of its 392 competed contracts drew a single offer (last 3 years)
- Usually buys through: Multiple-award IDIQ
Money by year
Obligations (money committed) in prime awards, from USAspending.gov.
What it buys, FY2025
- 237310 Highway, Street, and Bridge Construction $16.94M
- 236220 Commercial and Institutional Building Construction $6.87M
- 562910 Remediation Services $5.00M
- 541370 Surveying and Mapping (Except Geophysical) Services $1.85M
- 238910 Site Preparation Contractors $1.56M
- 541330 Engineering Services $1.40M
- 237990 Other Heavy and Civil Engineering Construction $518.9K
- 237110 Water and Sewer Line and Related Structures Construction $279.4K
Who it buys from, FY2025
- Young Gun Construction LLC $6.19M
- Quality Construction Co $4.95M
- Battle Ridge Builders LLC $4.52M
- R. E. Miller and Sons $2.45M
- Price Contracting Inc $2.18M
- Cook & Sons Construction, LLC $1.57M
- Stone Ridge Construction, Inc $1.53M
- Diamond Construction Company $1.03M
- Haskins Excavating LLC $852.9K
- Dj&A, P.C. $822.5K
Contracts ending in the next 12 months
10 contracts, $21.82M with options. The largest:
| Contract | Incumbent | Ends | Value with options |
|---|---|---|---|
| 1240LU26C0011 2026 BLUFF B MINE WASTE EXCAVATION PROJECT - EXCAVATION OF 310,000 CUBIC YARDS OF HAZARDOUS MINE WASTE INCLUDING ROAD CONSTRUCTION TO ACCESS THE EXCAVATION AREAS. | Young Gun Construction LLC | 2026-10-15 | $3.61M |
| 1240LU25F0037 TASK ORDER (TO) - ERFO EAST ROSEBUD ROAD PERMANENT REPAIRS ON THE CUSTER GALLATIN NATIONAL FOREST, PER ATTACHED TERMS, SPECIFICATIONS, ITEM SCHEDULE, FSSS'S, PLANS,WAGE DETERMINATIONS AND MAPS | Battle Ridge Builders, LLC | 2026-10-15 | $3.04M |
| 1240LU25F0078 GAOA MARKLEY BRIDGE REPLACEMENT 1DU | Battle Ridge Builders, LLC | 2026-10-31 | $1.54M |
| 1240LU26C0033 GAOA PROJECT - REXFORD BENCH WATER & SEWER IMPROVEMENTS | Double Diamond Contracting Inc | 2026-11-30 | $1.93M |
| 1240LU26F0003 STORMIN' NORMAN ROAD CONSTRUCTION AND RECONSTRUCTION TASK ORDER - TS WHICH IS A GOOD NEIGHBOR AUTHORITY TIMBER SALE WITHIN THE KOOTENAI WILDFIRE CRISIS STRATEGY AREA. | Stone Ridge Construction, Inc | 2026-11-30 | $1.05M |
| 1240LU26C0034 FORT MISSOULA BAKERY BUILDING RENOVATION ON THE LOLO NATIONAL FOREST - BASE ITEMS SCOPE OF WORK AND ALL OPTION ITEMS - PER ATTACHED CONTRACT TERMS, CONDITIONS, SPECIFICATIONS, DRAWINGS AND CLAUSES | Sirius Construction, Inc. | 2027-01-31 | $1.05M |
| 1240LU25C0025 CONSTRUCTION - GAOA - RECONSTRUCTION OF T-150. DEMOLISH EXISTING T150 BUILDING AND CONSTRUCT NEW BUILDING WITH SIMILAR SIZE AND FOOTPRINT AT FORT MISSOULA. | Quality Construction Co | 2027-03-23 | $5.18M |
| 1240LU26C0019 GAOA PROJECT - AFD VISITOR CENTER REMODEL | TCS Northwest LLC | 2027-04-05 | $1.03M |
| 1240LU26C0003 GAOA TIMBERLANE CAMPGROUND RECONSTRUCTION TASK ORDER APPLICABLE CONTRACT, R1 ROAD AND BRIDGE MATOC AWARDEE LIST OR OTHER A. THE INTENT OF THE CONTRACT IS TO PROVIDE FOR THE COMPLETE CONSTRUCTION OF THE PROJECT AS DESCRIBED IN THE CONTRACT. T | Thompson Contracting, Inc. | 2027-09-30 | $1.57M |
| 1240LU26C0022 CONSTRUCTION; NINEMILE W+WW, ST. REGIS WW REPLACEMENT | Haskins Excavating LLC | 2027-10-01 | $1.82M |
Open notices
- USDA Forest Service - Hebgen Lake District Office Network Cabling and IT Room Improvements · Combined Synopsis/Solicitation · due 2026-10-22 · Small Business Set Aside - Total
From USAspending.gov prime awards and SAM.gov notices. Sources and limits