Los Angeles County Metropolitan Transportation Authority received this grant or assistance award from Federal Transit Administration: $64.75M obligated so far for federal transit formula grants. Its latest action was on 2026-07-31.
Key facts · data as of Nov 14, 2026
- Recipient
- Los Angeles County Metropolitan Transportation Authority
- Awarding agency
- Federal Transit Administration (Department of Transportation)
- Obligated to date
- $64.75M
Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Nov 14, 2026.
Cite this page: SpendQuery, Award CA-2026-099, data as of Nov 14, 2026, https://spendquery.com/award?id=ASST_NON_CA-2026-099_069
Los Angeles County Metropolitan Transportation Authority: all federal awards · Department of Transportation: spending
APPLICATION PURPOSE: THE LOS ANGELES COUNTY METROPOLITAN TRANSPORTATION AUTHORITY (LACMTA) HEREBY SUBMITS THIS GRANT APPLICATION REQUESTING $64749000 OF STBG AND CRP FUNDS APPORTIONED TO LOS ANGELES UZA (#60020). THESE FUNDS ARE BEING REQUESTED FOR BUS REPLACEMENTS DESIGN/CONSTRUCTION OF CHARGING INFRASTRUCTURE AND PROCUREMENT OF CHARGING EQUIPMENT.; ACTIVITIES PERFORMED: FUNDS WILL BE USED TO FUND LACMTAS ACQUISITION OF BUSES DESIGN/CONSTRUCTION OF METRO DIVISION 18 CHARGING INFRASTRUCTURE AND PROCUREMENT AND INSTALLATION OF CHARGING EQUIPMENT.; EXPECTED OUTCOMES: THIS PROJECT IS ESSENTIAL TO THE SAFE AND EFFICIENT OPERATIONS OF LACMTAS VEHICLE FLEET. IT WILL REDUCE ACCIDENTS DOWNTIME AND MAINTENANCE COSTS AS WELL AS IMPROVE DRIVER MORALE AND PUBLIC RELATIONS. LACMTAS PROJECT WILL IMPROVE THE CONDITION OF ITS BUS SYSTEM IMPROVE THE RELIABILITY OF IMPORTANT ROUTES ENHANCE OVERALL ACCESS AND MOBILITY. THIS PROJECT WILL REDUCE THE NUMBER OF ROAD CALLS AND ASSOCIATED REPAIR COSTS AS WELL INCONVENIENCE AND DELAYS FOR PATRONS DUE TO SERVICE INTERRUPTIONS. IT WILL ALSO IMPROVE VEHICLE EFFICIENCY AND WORKING CONDITIONS AND RETENTION FOR VEHICLE OPERATORS AND MECHANICS THROUGH IMPROVED RUN CUTTING. THE PROJECT WILL CONTRIBUTE TO OVERALL SERVICE AND OPERATION ENHANCEMENT.; INTENDED BENEFICIARIES: BUS AND RAIL RIDERS INCLUDING SENIORS PERSONS WITH DISABILITIES LOW-INCOME AND TRANSIT DEPENDENT INDIVIDUALS AND THOSE WHO DO NOT HAVE ALTERNATIVE OPTIONS FOR ESSENTIAL TRIPS.; SUBRECIPIENT ACTIVITIES: LACMTA DOES NOT INTEND TO SUBAWARD FUNDS.
What it is
- Program
- Federal Transit Formula Grants (Assistance Listing 20.507)
- Where the work is
- CA
- Funding law
- Infrastructure law (IIJA)
- Topics
- electric_vehicles
Obligations by fiscal year
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
Subrecipients: where the money went next
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
Every action
1 action since 2026-07-31. Each is a modification or amendment with the money it added or took back.
| Date | Amendment | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-07-31 | 0 | New award | $64.75M | APPLICATION PURPOSE: THE LOS ANGELES COUNTY METROPOLITAN TRANSPORTATION AUTHORITY (LACMTA) HEREBY SUBMITS THIS GRANT APPLICATION REQUESTING $64749000 OF STBG AND CRP FUNDS APPORTIONED TO LOS ANGELES UZA (#60020). THESE FUNDS ARE BEING REQUESTED FOR BUS… |