1240LU23F0150↗

Alta Science & Engineering Inc received this contract from Usda-Fs, Csa Intermountain 9, Forest Service: $396.1K obligated so far for environmental systems protection- water quality support. Its period of performance ended 2025-07-31.

Key facts · data as of Oct 28, 2026

Recipient
Alta Science & Engineering Inc
Awarding agency
Forest Service (Department of Agriculture)
Contracting office
Usda-Fs, Csa Intermountain 9 (1240LU)
Obligated to date
$396.1K
Potential value
$396.1K
Ends
2025-07-31

Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 28, 2026.

Cite this page: SpendQuery, Award 1240LU23F0150, data as of Oct 28, 2026, https://spendquery.com/award?id=CONT_AWD_1240LU23F0150_12C2_140F0822D0184_1448

BARKER HUGHESVILLE MINING DISTRICT ENGINEERING EVALUATION/COST ANALYSIS

Delivery Order · Forest Service · to Alta Science & Engineering Inc (UEI WNUGK5T5C8A5) · data as of 2026-10-28

Obligated to date$396.1K3 actions
Current value$396.1Kwith options exercised
Period2023-10-01 → 2025-07-31current end date

What it is

Product or service
Environmental Systems Protection- Water Quality Support (PSC F103)
Industry
Engineering Services (NAICS 541330)
Contracting office
Usda-Fs, Csa Intermountain 9 (1240LU)
Competition
Full and open after exclusion of sources · 1 offer received
Pricing
Firm fixed price
How it was bought
Multiple-award IDIQ · under 140F0822D0184
Where the work is
Lewis and Clark, MT · district MT-02
Funding law
Infrastructure law (IIJA)

Obligations by fiscal year

FY2023$396.1K
FY2025$0

SpendQuery holds FY2023 on; earlier years are on USAspending.gov.

Subcontractors: where the money went next

No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.

Every action

3 actions since 2023-09-28. Each is a modification or amendment with the money it added or took back.

DateModificationKindAmountWhat the agency wrote
2025-03-27P00002Supplemental agreement (work within scope)$0BARKER HUGHESVILLE MINING DISTRICT ENGINEERING EVALUATION/COST ANALYSIS
2024-11-22P00001Supplemental agreement (work within scope)$0BARKER HUGHESVILLE MINING DISTRICT ENGINEERING EVALUATION/COST ANALYSIS
2023-09-280$396.1KBARKER HUGHESVILLE MINING DISTRICT ENGINEERING EVALUATION/COST ANALYSIS