1240LU26F0035↗

Highland Construction Services LLC received this contract from Usda-Fs, Csa Intermountain 9, Forest Service: $807.7K obligated so far for construction of highways, roads, streets, bridges, and railways. It runs to 2027-09-30.

Key facts · data as of Oct 21, 2026

Recipient
Highland Construction Services LLC
Awarding agency
Forest Service (Department of Agriculture)
Contracting office
Usda-Fs, Csa Intermountain 9 (1240LU)
Obligated to date
$807.7K
Potential value
$807.7K
Ends
2027-09-30

Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 21, 2026.

Cite this page: SpendQuery, Award 1240LU26F0035, data as of Oct 21, 2026, https://spendquery.com/award?id=CONT_AWD_1240LU26F0035_12C2_1240LU25D0011_12C2

TASK ORDER FOR SELWAY SAGINAW ROAD IMPROVEMENTS ON THE BDNF - THE INTENT OF THIS PROJECT IS TO PROVIDE ACCESS/ROAD IMPROVEMENTS FOR THE SELWAY SAGINAW (SELSAG) AREA ON THE DILLON AND WISDOM RANGER DISTRICTS OF THE BEAVERHEAD-DEERLODGE NATIONAL FOREST

Delivery Order · Forest Service · to Highland Construction Services LLC (UEI L1HHB4J2S8G6) · data as of 2026-10-21

Obligated to date$807.7K2 actions
Current value$807.7Kwith options exercised
Period2026-06-01 → 2027-09-30current end date

Up for re-bid: ends 2027-09-30. Recompete brief →

What it is

Product or service
Construction of Highways, Roads, Streets, Bridges, and Railways (PSC Y1LB)
Industry
Highway, Street, and Bridge Construction (NAICS 237310)
Contracting office
Usda-Fs, Csa Intermountain 9 (1240LU)
Competition
Full and open after exclusion of sources · 4 offers received
Pricing
Firm fixed price
How it was bought
Multiple-award IDIQ · under 1240LU25D0011
Solicitation
1240LU26Q0037
Where the work is
Beaverhead, MT · district MT-01
Funding law
Infrastructure law (IIJA)

Obligations by fiscal year

FY2026$807.7K

SpendQuery holds FY2023 on; earlier years are on USAspending.gov.

Subcontractors: where the money went next

No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.

Every action

2 actions since 2026-04-09. Each is a modification or amendment with the money it added or took back.

DateModificationKindAmountWhat the agency wrote
2026-08-19P00001Supplemental agreement (work within scope)$42.5KMODIFICATION 0001 TO SELSAG AREA ROAD IMPROVEMENTS IS A SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE: NECESSARY DELETIONS OF WORK BASED ON CURRENT CONDITIONS OF ROAD AND NECESSARY INCREASE OF FULL DEPTH RECLAMATION ITEM 30401 AT ORIGINAL $6/MILE PRI
2026-04-090$765.2KTASK ORDER FOR SELWAY SAGINAW ROAD IMPROVEMENTS ON THE BDNF - THE INTENT OF THIS PROJECT IS TO PROVIDE ACCESS/ROAD IMPROVEMENTS FOR THE SELWAY SAGINAW (SELSAG) AREA ON THE DILLON AND WISDOM RANGER DISTRICTS OF THE BEAVERHEAD-DEERLODGE NATIONAL FOREST