PCL Construction Inc received this contract from International Boundary Water Comm US Mex, International Boundary and Water Commission: U.S.-Mexico: $552.37M obligated so far for construction of sewage and waste facilities. It runs to 2031-12-31.
Key facts · data as of Oct 21, 2026
Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 21, 2026.
Cite this page: SpendQuery, Award 191BWC24C0008, data as of Oct 21, 2026, https://spendquery.com/award?id=CONT_AWD_191BWC24C0008_19BM_-NONE-_-NONE-
PCL Construction Inc: all federal awards · Department of State: spending · International Boundary Water Comm US Mex: what it buys
INTERNATIONAL WASTEWATER TREATMENT PLANT REHABILITATION AND EXPANSION PROJECT
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
13 actions since 2024-08-20. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-09-29 | P00012 | Supplemental agreement (work within scope) | $445.92M | THE PURPOSE OF THIS BILATERAL MODIFICATION IS TO INCORPORATE THE CONSTRUCTION PACKAGES AND CHANGES AS PART OF THE PROGRESSIVE DB CONTRACT |
| 2026-08-18 | P00011 | Supplemental agreement (work within scope) | $53.1K | THE PURPOSE OF THIS MODIFICATION P00011 IS TO BILATERALLY INCORPORATE THE REA POLYMER RECIRC PUMP (PCL# CRX-018) AS PART OF THE PROGRESSIVE DB CONTRACT |
| 2026-06-01 | P00010 | Supplemental agreement (work within scope) | $25.99M | THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE THE FOLLOWING CONSTRUCTION EARLY WORK PACKAGE 2/3A AS PART OF THE PROGRESSIVE DB CONTRACT |
| 2026-05-26 | P00009 | Supplemental agreement (work within scope) | $19.96M | MODIFICATION IS TO INCORPORATE THE FOLLOWING CONSTRUCTION EARLY WORK PACKAGE 1B AS PART OF THE PROGRESSIVE DB CONTRACT |
| 2026-05-12 | P00008 | Supplemental agreement (work within scope) | $405.5K | DEFINITIZES SEVERAL PRIOR UNILATERAL MODS AND EXTENDING THE DESIGN PHASE BY 48 DAYS. IT FORMALIZES ADDED DESIGN AND CONSTRUCTION EFFORTS FOR THE TEMPORARY 10 MGD CAPACITY INCREASE, INCORPORATES A GRIT VALVE REPAIR REA, UPDATES SMALL BUSINESS GOALS |
| 2025-11-26 | P00007 | Supplemental agreement (work within scope) | $0 | EXCUSABLE DELAY |
| 2025-09-30 | P00006 | Funding only | $6.25M | REVISE THE DESCRIPTION OF THE ITEMS INCORPORATED WITHIN CLIN 0003 OPTIONAL DESIGN. |
| 2025-09-29 | P00005 | Administrative change | $0 | REVISE THE DESCRIPTION OF THE ITEMS INCORPORATED WITHIN CLIN 0003 OPTIONAL DESIGN. |
| 2025-09-15 | P00004 | Supplemental agreement (work within scope) | $0 | REVISE THE DESCRIPTION OF THE ITEMS INCORPORATED WITHIN CLIN 0003 OPTIONAL DESIGN. |
| 2025-05-29 | P00003 | Supplemental agreement (work within scope) | $3.10M | THE CONTRACTOR SHALL NOT EXCEED A TOTAL OF $3,100,000.00 IN THE PERFORMANCE OF THIS RFP-2 WORK FOR CLIN 007. |
| 2025-03-29 | P00002 | Change order | $700.0K | THE CONTRACTOR SHALL NOT EXCEED $700,000.00 IN THE PERFORMANCE. A PROPOSAL SHALL BE SUBMITTED BY THE CONTRACTOR NLT MAY 12, 2025. NEGOTIATIONS SHALL COMMENCE ON OR ABOUT MAY 15, 2025, AFTER WHICH A DEFINITIZED BILATERAL MODIFICATION WILL BE ISSUED. |
| 2025-03-29 | P00001 | Supplemental agreement (work within scope) | $7.56M | INTERNATIONAL WASTEWATER TREATMENT PLANT REHABILITATION AND EXPANSION PROJECT EARLY WORK PACKAGE 1A AS PART OF THE PROGRESSIVE DESIGN BUILD. |
| 2024-08-20 | 0 | $42.44M | INTERNATIONAL WASTEWATER TREATMENT PLANT REHABILITATION AND EXPANSION PROJECT |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-21). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗