70Z05021FOPCLA100↗

Gilbane Federal received this contract from FDCC Det Seattle(00050), U.S. Coast Guard: $8.09M obligated so far for construction of miscellaneous buildings. It runs to 2026-12-31.

Key facts · data as of Oct 25, 2026

Recipient
Gilbane Federal
Awarding agency
U.S. Coast Guard (Department of Homeland Security)
Contracting office
FDCC Det Seattle(00050) (70Z050)
Obligated to date
$8.09M
Potential value
$37.25M
Ends
2026-12-31

Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 25, 2026.

Cite this page: SpendQuery, Award 70Z05021FOPCLA100, data as of Oct 25, 2026, https://spendquery.com/award?id=CONT_AWD_70Z05021FOPCLA100_7008_70Z04718DGILBAN00_7008

THE PURPOSE OF THIS TASK ORDER IS TO SUPPORT THE UNITED STATES COAST GUARD (USCG) THROUGH THE PROVISION OF DESIGN-BUILD CONSTRUCTION SERVICES FOR LALB OPC WATERFRONT CONSTRUCTION.

Delivery Order · U.S. Coast Guard · to Gilbane Federal (UEI WHB7C12ADS35) · data as of 2026-10-25

Obligated to date$8.09M24 actions
Current value$37.25Mwith options exercised
Period2020-10-15 → 2026-12-31current end date

Up for re-bid: ends 2026-12-31. Recompete brief →

What it is

Product or service
Construction of Miscellaneous Buildings (PSC Y1JZ)
Industry
Commercial and Institutional Building Construction (NAICS 236220)
Contracting office
FDCC Det Seattle(00050) (70Z050)
Competition
Full and open competition · 3 offers received
Pricing
Firm fixed price
How it was bought
Multiple-award IDIQ · under 70Z04718DGILBAN00
Solicitation
70Z05020ROPCLA1
Where the work is
Los Angeles, CA · district CA-44

Obligations by fiscal year

FY2023$408.4K
FY2024$1.61M
FY2025$5.65M
FY2026$431.0K

SpendQuery holds FY2023 on; earlier years are on USAspending.gov.

Subcontractors: where the money went next

No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.

Every action

24 actions since 2023-01-18. Each is a modification or amendment with the money it added or took back.

DateModificationKindAmountWhat the agency wrote
2026-09-30P00029Administrative change$0ADMINISTRATIVE MODIFICATION - NO COST TO CHANGE COR FROM MARK MCALL TO ALEJANDRO N. FAJARDO.
2026-07-14P00028Supplemental agreement (work within scope)$0NO COST MODIFICATION EXTENDING PERIOD OF PERFORMANCE ONLY TO ADDRESS ADMINISTRATIVE ITEMS.
2026-06-11P00027Supplemental agreement (work within scope)$44.4KTECHNICAL ACCEPTANCE OF CMR 39, PAYMENT TO LADWP.
2026-04-23P00026Supplemental agreement (work within scope)$0NO COST EXTENSION FROM MARCH 31, 2026 TO JUNE 30, 2026. .
2026-03-06P00025Supplemental agreement (work within scope)$204.4KTECHNICAL ACCEPTANCE OF CMR 35-1 EXTENDED GC'S.
2026-02-12P00024Supplemental agreement (work within scope)$95.2KTECHNICAL ACCEPTANCE OF CMR 35 FOR TASKS ONLY - DOES NOT INCLUDE EXTENDED GENERAL CONDITIONS. TECHNICAL ACCEPTANCE FOR CMR 38 PROCESS PAYMENT TO LADWP.
2026-01-28P00023Supplemental agreement (work within scope)$87.0KTECHNICAL APPROVAL/ACCEPTANCE OF PROPOSAL FOR CMR 37_SUPPLEMENTAL PAYMENT TO LADWP.
2025-06-23P00022Supplemental agreement (work within scope)$686.6KUNILATERAL MODIFICATION: ACCEPTANCE OF PROPOSAL AMOUNT OF $686,579.83 FOR CMR 34: KTR FACILITATING $600,000.00 PAYMENT TO LADWP ON BEHALF OF THE CG.
2025-04-09P00021Supplemental agreement (work within scope)$10.8KACCEPTANCE OF GILBANE PROPOSAL AMOUNT FOR CMR 33/REA 10 $10,759.42.
2025-01-27P00020Supplemental agreement (work within scope)$4.16MACCEPT GILBANE CMR 15 12.20.24 PROPOSAL. POP EXTENDED TO 11.17.25. CLIN 0001 GILBANE SUBSTATION, $4,116,329.05, CLIN 0002, LADWP TRANSFORMER INSTALL 148 CALENDAR DAYS (SUBJECT TO LADWP PERFORMANCE) AT $303.85 PER DAY, $44,969.80. TOTAL $4,161,298.85
2024-10-28P00019Supplemental agreement (work within scope)$331.8K$331,771.32 REA 11, MOD DEV, PREP, IMPLEMENT, ADV. ELECT, CLARK NEXSEN DESIGN, BOND, .66%, G&A 6.96%, PROFIT 10.28%, BOND PREM ADJUST 1.25%.
2024-10-17P00018Administrative change$455.9KCMR 30: ACCEPTANCE OF CONTRACTOR PROPOSAL DATED 10SEP24 IN THE AMOUNT OF $455,926.39.
2024-07-12P00017Supplemental agreement (work within scope)$0THE GOVT AND KTR RELEASE EACH OTHER FROM ANY AND ALL LIABILITY FOR FURTHER EQUITABLE ADJUSTMENTS ATTRIBUTABLE TO SUCH FACTS OR CIRCUMSTANCES GIVING RISE TO REA 13, REA 14, REA 15 AND MODIFICATION P00017 DATED 12 JUL 2024.
2024-06-28P00016Supplemental agreement (work within scope)$89.0K89,000.00 IAW STORMWATER DRAINAGE DESIGN AND CONSTRUCTION DATED NOVEMBER 7, 2023 AND CIVILIAN BOARD OF CONTRACTS APPEAL #8065 DATED MARCH 29, 2024
2024-06-11P00015Supplemental agreement (work within scope)$483.0KNOTICE TO PROCEED IN ACCORDANCE WITH CMR 15 TO PROVIDE A NEW SUBSTATION ENCLOSURE PER LAWPD APPROVED DESIGN DRAWINGS PROVIDED UNDER CMR-30.
2024-06-06P00014Supplemental agreement (work within scope)$595.5KIN ACCORDANCE WITH GILBANE'S SETTLEMENT LETTER DATED 24 MAY 2024, SERIAL LETTER NO. J35000TO03.098.1 TO SETTLE CLAIM AND APPEAL FOR THE AMOUNT OF $595,516.00, 85 CALENDAR DAYS FROM 15 OCT 2022 TO 09 JAN 2023.
2024-03-04P00013Supplemental agreement (work within scope)$440.9KREA 12, PILE OBSTRUCTION $440,922.81, NO EXTENDED GENERAL CONDITIONS, NO EXTENDED PERIOD OF PERFORMANCE.
2023-09-11P00012Supplemental agreement (work within scope)$126.1KCMR 30 $132,064.07 (UNILATERAL MODIFICATION) AND CMR 31 CREDIT $6,003.67
2023-07-20P00011Supplemental agreement (work within scope)$20.0KSETTLEMENT, REA 7 SANDBLASTING EQUIPMENT CLAIM
2023-06-02P00010Supplemental agreement (work within scope)$0NO COST UNILATERAL MODIFICATION TO EXTEND THE PERIOD OF PERFORMANCE FROM 22 JUNE 2023 TO 3 AUG 2024 DUE TO COVID CAUSED DELAYS FOR THE DELIVERY, COMMISSION, AND FINAL INSPECTION OF HITACHI TRANSFORMERS.
2023-02-16P00009Supplemental agreement (work within scope)$12.4KCMR 26
2023-02-13P00008Supplemental agreement (work within scope)$104.7KCMR 23
2023-01-30P00007Supplemental agreement (work within scope)$92.5KCMR 23
2023-01-18P00006Supplemental agreement (work within scope)$52.8KCMR 24

Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-25). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗