70Z05023F43000003↗
Whiting-Turner Contracting Company, the received this contract from FDCC Det Seattle(00050), U.S. Coast Guard: $15.27M obligated so far for construction of miscellaneous buildings. Its period of performance ended 2026-03-17.
Key facts · data as of Oct 26, 2026
- Recipient
- Whiting-Turner Contracting Company, the
- Awarding agency
- U.S. Coast Guard (Department of Homeland Security)
- Contracting office
- FDCC Det Seattle(00050) (70Z050)
- Obligated to date
- $15.27M
- Potential value
- $15.27M
- Ends
- 2026-03-17
Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 26, 2026.
Cite this page: SpendQuery, Award 70Z05023F43000003, data as of Oct 26, 2026, https://spendquery.com/award?id=CONT_AWD_70Z05023F43000003_7008_70Z04718DWHITUR00_7008
Whiting-Turner Contracting Company, the: all federal awards · Department of Homeland Security: spending · FDCC Det Seattle(00050): what it buys
DB CONSTRUCTION SERVICES FOR CDC, PLAY AREA TRACEN PETALUMA, CA
What it is
- Product or service
- Construction of Miscellaneous Buildings (PSC Y1JZ)
- Industry
- Commercial and Institutional Building Construction (NAICS 236220)
- Contracting office
- FDCC Det Seattle(00050) (70Z050)
- Competition
- Full and open competition · 3 offers received
- Pricing
- Firm fixed price
- How it was bought
- Multiple-award IDIQ · under 70Z04718DWHITUR00
- Solicitation
- 70Z05022R731000002
- Where the work is
- Sonoma, CA · district CA-02
Obligations by fiscal year
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
Subcontractors: where the money went next
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
Every action
21 actions since 2022-11-25. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2025-09-25 | P00020 | Supplemental agreement (work within scope) | $477.1K | TECHNICAL ACCEPTANCE OF PROPOSAL FOR KITCHEN FFE AND PERIOD OF PERFORMANCE EXTENSION FROM 9.30.2025 TO 3.17.2026 |
| 2025-08-18 | P00019 | Supplemental agreement (work within scope) | $95.4K | TECHNICAL ACCEPTANCE OF WORK FOR REA 6: REPLACE THE DEAD BREAK ELBOWS, AND RE-TEST THE CABLES AND CONDUCTORS. |
| 2025-07-29 | P00018 | Supplemental agreement (work within scope) | $23.9K | TECHNICAL ACCEPTANCE OF REA 5; THIS MODIFICATION WILL ALSO EXTEND THE DUE DATE FROM 09/11/2025 TO 09/30/2025 AND CONFIRMS THE COR IS MARQUISE STEWART. |
| 2025-05-22 | P00017 | Supplemental agreement (work within scope) | $52.7K | ACCEPTANCE OF CONTRACTOR PROPOSAL DATED 3.25.25 FOR REA 4, SEWER MH01, MH02, IN THE AMOUNT OF $52,665.43. |
| 2025-04-09 | P00016 | Supplemental agreement (work within scope) | $0 | USCG ACCEPTANCE OF NO COST EXTENSION OF PERIOD OF PERFORMANCE FROM 11SEP2025 TO 24SEP2025 - WEATHER DAYS UP TO DECEMBER 26, 2024, ONLY |
| 2025-01-27 | P00015 | Supplemental agreement (work within scope) | $108.6K | TECHNICAL ACCEPTANCE OF WT PROPOSAL AMOUNT OF $108,602.21 FOR REA 3_RFI 36.1 UNFORESEEN UTILITIES. THIS MODIFICATION ALSO CORRECTS AN INTERNAL USCG FINANCE ISSUE. |
| 2024-11-20 | P00014 | Administrative change | $676.5K | PER FSMS0218086, VASSER_WIELAND EMAIL EXCHANGE DATED 10.23.24, ONCE THE A/L IS PROCESSED, FUNDED, AND APPROVED, CONTRACTING WILL DIRECTLY OBLIGATE $676,493.15 USING A/L FUNDS BY ADDING A NEW LINE TO THE AWARD. |
| 2024-09-26 | P00013 | Supplemental agreement (work within scope) | $207.1K | CMR 5, SATURATED SOIL REMOVAL AND REPLACEMENT. PERIOD OF PERFORMANCE EXTENDED TO SEPTEMBER 11, 2025. |
| 2024-09-26 | P00012 | Supplemental agreement (work within scope) | $8.7K | REA 2 UNFORESEEN PIPE |
| 2024-09-16 | P00011 | Supplemental agreement (work within scope) | $64.6K | CMR 4 SEWER LINE RE-ROUTE |
| 2024-07-10 | P00010 | Supplemental agreement (work within scope) | $1.27M | CMR 3 CONTRUCTION CHANGES |
| 2024-04-03 | P00009 | Supplemental agreement (work within scope) | $173.1K | REA/CMR CDC 2C PARTS 5 AND 6 ADMINISTRATIVE COSTS: $173,145.25. |
| 2024-01-03 | P00008 | Administrative change | $0 | UNILATERAL MODIFICATION TO ADD COR, EDWARD WIELAND |
| 2023-11-27 | P00007 | Supplemental agreement (work within scope) | $98.7K | CMR PART 1, UTILITY LOCATION AND TOPOGRAPHIC SURVEY. CMR PART 2, POTHOLING - UTILITY CROSSING DEPTS CMR PART 3, MEASURE EXISTING WASTEWATER MANHOLE INVERTS |
| 2023-11-09 | P00006 | Supplemental agreement (work within scope) | $147.3K | REA 1, CMR 2C PART 4 |
| 2023-09-11 | P00005 | Supplemental agreement (work within scope) | $52.6K | CMR 2B DESIGN CHARETTE THIS MODIFICATION INCORPORATES THE NOTICE-TO-PROCEED EMAILED TO WHITING TURNER ON 9.7.23. |
| 2023-08-08 | P00004 | Supplemental agreement (work within scope) | $42.7K | CMR-2A FOR GEOTECHNICAL BORINGS AND REPORTING ONLY, THIS MODIFICATION INCORPORATES A NOTICE TO PROCEED. |
| 2023-06-15 | P00003 | Supplemental agreement (work within scope) | $0 | THIS UNILATERAL MODIFICATION EXTENDS THE SUSPENSION OF WORK ISSUED ON MAY 19, 2023, FOR 30 CALENDAR DAYS (SCHEDULED TO EXPIRE JUNE 18, 2023) TO JUNE 30, 2023. A REQUEST FOR EQUITABLE ADJUSTMENT MAY BE SUBMITTED IN ACCORDANCE WITH FAR REGULATIONS. |
| 2023-05-24 | P00002 | Supplemental agreement (work within scope) | $13.7K | CMR 01 |
| 2023-02-24 | P00001 | Supplemental agreement (work within scope) | $0 | THIS MODIFICATION IS ISSUED TO IMMEDIATELY SUSPEND GEOTECHNICAL BORINGS UNDER THIS TASK ORDER IN ACCORDANCE WITH FAR 52242-14 SUSPENSION OF WORK (APR 1984), UNTIL FURTHER NOTICE. |
| 2022-11-25 | 0 | $11.76M | DB CONSTRUCTION SERVICES FOR CDC, PLAY AREA TRACEN PETALUMA, CA |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-26). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗