FA890324F0029↗

Gilbane Federal received this contract from Fa8903 772 Ess PK, Department of the Air Force: $71.90M obligated so far for construction of miscellaneous buildings. Its period of performance ended 2026-05-23.

Key facts · data as of Oct 28, 2026

Recipient
Gilbane Federal
Awarding agency
Department of the Air Force (Department of Defense)
Contracting office
Fa8903 772 Ess PK (FA8903)
Obligated to date
$71.90M
Potential value
$71.91M
Ends
2026-05-23

Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 28, 2026.

Cite this page: SpendQuery, Award FA890324F0029, data as of Oct 28, 2026, https://spendquery.com/award?id=CONT_AWD_FA890324F0029_9700_FA890317D0041_9700

CONSTRUCTION OF PHASE II NAVY IGLOOS MUNITIONS STORAGE AREAS AT KING SAUD AIR BASE (KSAB), AL JOUF AIR BASE (AJAB), KING FAHAD AIR BASE (KFDAB) AND PRINCE SULTAN AIR BASE (PSAB), KINGDOM OF SAUDI ARABIA.

Delivery Order · Department of the Air Force · to Gilbane Federal (UEI WHB7C12ADS35) · data as of 2026-10-28

Obligated to date$71.90M9 actions
Current value$71.91Mwith options exercised
Period2024-02-14 → 2026-05-23current end date

What it is

Product or service
Construction of Miscellaneous Buildings (PSC Y1JZ)
Industry
Commercial and Institutional Building Construction (NAICS 236220)
Contracting office
Fa8903 772 Ess PK (FA8903)
Competition
Full and open competition · 2 offers received
Pricing
Firm fixed price
How it was bought
Multiple-award IDIQ · under FA890317D0041
Solicitation
FA890323R0058
Where the work is
SAU

Obligations by fiscal year

FY2024$69.48M
FY2025$995.8K
FY2026$1.42M

SpendQuery holds FY2023 on; earlier years are on USAspending.gov.

Subcontractors: where the money went next

No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.

Every action

9 actions since 2024-02-15. Each is a modification or amendment with the money it added or took back.

DateModificationKindAmountWhat the agency wrote
2026-04-17P00008Change order$1.42MCONSTRUCTION OF ECMS AT MULTIPLE LOCATIONS IN KSA.
2025-09-17P00007Change order$846.0KCONSTRUCTION OF ECMS AT MULTIPLE LOCATIONS IN KSA.
2025-08-18P00006Administrative change$0CONSTRUCTION OF ECMS AT MULTIPLE LOCATIONS IN KSA.
2025-08-18P00005Change order$165.4KCONSTRUCTION OF ECMS AT MULTIPLE LOCATIONS IN KSA.
2025-07-18P00004Change order-$15.7KCONSTRUCTION OF ECMS AT MULTIPLE LOCATIONS IN KSA.
2025-06-05P00003Administrative change$0CONSTRUCTION OF ECMS AT MULTIPLE LOCATIONS IN KSA.
2024-05-28P00002Administrative change$0CONSTRUCTION OF ECMS AT MULTIPLE LOCATIONS IN KSA.
2024-02-22P00001Administrative change$0CONSTRUCTION OF PHASE II NAVY IGLOOS MUNITIONS STORAGE AREAS AT KING SAUD AIR BASE (KSAB), AL JOUF AIR BASE (AJAB), KING FAHAD AIR BASE (KFDAB) AND PRINCE SULTAN AIR BASE (PSAB), KINGDOM OF SAUDI ARABIA.
2024-02-150$69.48MCONSTRUCTION OF PHASE II NAVY IGLOOS MUNITIONS STORAGE AREAS AT KING SAUD AIR BASE (KSAB), AL JOUF AIR BASE (AJAB), KING FAHAD AIR BASE (KFDAB) AND PRINCE SULTAN AIR BASE (PSAB), KINGDOM OF SAUDI ARABIA.