NNG11FC20C↗
Lockheed Martin Integrated Systems, LLC received this contract from Nasa Goddard Space Flight Center, National Aeronautics and Space Administration: $91.10M obligated so far for support- administrative: other. It runs to 2027-09-30.
Key facts · data as of Oct 25, 2026
- Recipient
- Lockheed Martin Integrated Systems, LLC
- Awarding agency
- National Aeronautics and Space Administration
- Contracting office
- Nasa Goddard Space Flight Center (80GSFC)
- Obligated to date
- $91.10M
- Potential value
- $394.23M
- Ends
- 2027-09-30
Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 25, 2026.
Cite this page: SpendQuery, Award NNG11FC20C, data as of Oct 25, 2026, https://spendquery.com/award?id=CONT_AWD_NNG11FC20C_8000_-NONE-_-NONE-
Lockheed Martin Integrated Systems, LLC: all federal awards · National Aeronautics and Space Administration: spending · Nasa Goddard Space Flight Center: what it buys · The follow-on: recompete brief
THE MOSES II EFFORT IS A FIVE-YEAR SOLE-SOURCE FOLLOW-ON CONTRACT TO MAINTAIN THE HEALTH AND SAFETY OF THE HST OBSERVATORY THROUGH THE NEXT PHASE OF ITS SCIENCE MISSION. THE SCOPE OF THIS FOLLOW-ON EFFORT INCLUDES CONDUCTING ALL ELEMENTS OF HST OPERATIONS OTHER THAN SCIENCE OPERATIONS, AND TO PERFORM SYSTEMS ENGINEERING TASKS REQUIRED TO PROPERLY MAINTAIN HST FLIGHT AND GROUND SYSTEMS.MISSION OPERATIONS RESPONSIBILITIES INCLUDE SAFE AND EFFICIENT CONTROL AND UTILIZATION OF THE HST OBSERVATORY, MAINTENANCE AND OPERATION OF HST-UNIQUE FACILITIES AND EQUIPMENT, AS WELL AS CREATION, MAINTENANCE, AND UTILIZATION OF HST OPERATIONS PROCESSES AND PROCEDURES. CRITICAL SYSTEMS ENGINEERING RESPONSIBILITIES CONSIST OF OPTIMIZING MISSION SYSTEM CAPABILITIES TO MAXIMIZE HST OPERATIONS EFFECTIVENESS AND SCIENCE PRODUCTIVITY. ESSENTIAL MANAGEMENT REQUIREMENTS INCLUDE PROVIDING A TECHNICAL STAFF POSSESSING IN-DEPTH KNOWLEDGE OF HST S VARIED, COMPLEX, AND UNIQUE FLIGHT AND GROUND SYSTEMS, ENSURING SUCCESSFUL ACCOMPLISHMENT OF THE DIVERSE TASKS NECESSARY TO EFFECTIVELY CONDUCT HST MISSION OPERATIONS AND SYSTEMS ENGINEERING AS WELL AS TO MANAGE AND REPORT CONTRACT ELEMENT COST AND SCHEDULE PERFORMANCE.
Up for re-bid: ends 2027-09-30. Recompete brief → · Orbital Safety Analysis (OSA) Support - JOFOC ↗
What it is
- Product or service
- Support- Administrative: Other (PSC R699)
- Industry
- Engineering Services (NAICS 541330)
- Contracting office
- Nasa Goddard Space Flight Center (80GSFC)
- Competition
- Not competed · 1 offer received
- Pricing
- Cost plus fixed fee
- How it was bought
- Standalone contract
- Solicitation
- NNG10321685R
- Where the work is
- Prince Georges, MD · district MD-04
Obligations by fiscal year
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
Subcontractors: where the money went next
7 subawards totaling $2.03M (2.2% of what was obligated), as Lockheed Martin Integrated Systems, LLC reported them. Primes report subawards of $30,000 or more; smaller ones and unreported ones aren't here.
| Subcontractor | Amount | Subawards | Where | First | Last |
|---|---|---|---|---|---|
| Lentech, Inc | $1.92M | 2 | NM | 2023-07-26 | 2024-09-24 |
| General Dynamics Corporation | $236.2K | 2 | VA | 2022-10-12 | 2023-12-21 |
| Prototype Productions, Inc. | -$1 | 1 | VA | 2023-09-20 | 2023-09-20 |
| Danbury Mission Technologies LLC | -$59.5K | 1 | CT | 2023-04-11 | 2023-04-11 |
| Northrop Grumman Corporation | -$65.6K | 1 | MD | 2023-11-02 | 2023-11-02 |
The largest single subawards
| Date | To | Amount | For |
|---|---|---|---|
| 2023-07-26 | Lentech, Inc | $1.65M | MISSION OPS SYS ENGR S/W II (MOSES II) |
| 2024-09-24 | Lentech, Inc | $270.6K | MISSION OPS SYS ENGR S/W II (MOSES II) |
| 2023-12-21 | General Dynamics Information Technology, Inc. | $206.1K | MOSES II SUPPORT |
| 2022-10-12 | General Dynamics Information Technology, Inc. | $30.0K | MOSES II SUPPORT |
| 2023-09-20 | Prototype Productions Inc | -$1 | PPI MOSES II EXTENSION |
| 2023-04-11 | Danbury Mission Technologies, LLC | -$59.5K | ENG SUPT FOR HST. |
| 2023-11-02 | Atk Space Systems LLC | -$65.6K | ENGINEERING SERVICES ON MOSES II |
Every action
29 actions since 2022-10-26. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-09-23 | 123 | Funding only | $1.25M | EXECUTIVE ORDER (E.O.) 14398 TITLED "ADDRESSING DEI DISCRIMINATION BY FEDERAL CONTRACTORS. THE MOSES II EFFORT IS A SOLE-SOURCE FOLLOW-ON CONTRACT TO MAINTAIN THE HEALTH AND SAFETY OF THE HST OBSERVATORY THROUGH THE NEXT PHASE OF ITS SCIENCE MISSION. THE… |
| 2026-08-27 | 122 | Additional work (new agreement) | $7.04M | EXECUTIVE ORDER (E.O.) 14398 TITLED "ADDRESSING DEI DISCRIMINATION BY FEDERAL CONTRACTORS. THE MOSES II EFFORT IS A SOLE-SOURCE FOLLOW-ON CONTRACT TO MAINTAIN THE HEALTH AND SAFETY OF THE HST OBSERVATORY THROUGH THE NEXT PHASE OF ITS SCIENCE MISSION. THE… |
| 2026-08-12 | 121 | Administrative change | $0 | EXECUTIVE ORDER (E.O.) 14398 TITLED "ADDRESSING DEI DISCRIMINATION BY FEDERAL CONTRACTORS. THE MOSES II EFFORT IS A SOLE-SOURCE FOLLOW-ON CONTRACT TO MAINTAIN THE HEALTH AND SAFETY OF THE HST OBSERVATORY THROUGH THE NEXT PHASE OF ITS SCIENCE MISSION. THE… |
| 2026-07-10 | 120 | Novation (new contractor name or owner) | $0 | EXECUTIVE ORDER (E.O.) 14398 TITLED "ADDRESSING DEI DISCRIMINATION BY FEDERAL CONTRACTORS. THE MOSES II EFFORT IS A SOLE-SOURCE FOLLOW-ON CONTRACT TO MAINTAIN THE HEALTH AND SAFETY OF THE HST OBSERVATORY THROUGH THE NEXT PHASE OF ITS SCIENCE MISSION. THE… |
| 2026-06-29 | 119 | Change order | $2.98M | EXECUTIVE ORDER (E.O.) 14398 TITLED "ADDRESSING DEI DISCRIMINATION BY FEDERAL CONTRACTORS. THE MOSES II EFFORT IS A SOLE-SOURCE FOLLOW-ON CONTRACT TO MAINTAIN THE HEALTH AND SAFETY OF THE HST OBSERVATORY THROUGH THE NEXT PHASE OF ITS SCIENCE MISSION. THE… |
| 2026-06-03 | 118 | Administrative change | $0 | EXECUTIVE ORDER (E.O.) 14398 TITLED "ADDRESSING DEI DISCRIMINATION BY FEDERAL CONTRACTORS. THE MOSES II EFFORT IS A SOLE-SOURCE FOLLOW-ON CONTRACT TO MAINTAIN THE HEALTH AND SAFETY OF THE HST OBSERVATORY THROUGH THE NEXT PHASE OF ITS SCIENCE MISSION. THE… |
| 2026-03-31 | 117 | Funding only | $6.38M | THE MOSES II EFFORT IS A SOLE-SOURCE FOLLOW-ON CONTRACT TO MAINTAIN THE HEALTH AND SAFETY OF THE HST OBSERVATORY THROUGH THE NEXT PHASE OF ITS SCIENCE MISSION. THE SCOPE OF THIS FOLLOW-ON EFFORT INCLUDES CONDUCTING ALL ELEMENTS OF HST OPERATIONS OTHER THAN… |
| 2026-01-30 | 116 | Funding only | $115.0K | THE MOSES II EFFORT IS A SOLE-SOURCE FOLLOW-ON CONTRACT TO MAINTAIN THE HEALTH AND SAFETY OF THE HST OBSERVATORY THROUGH THE NEXT PHASE OF ITS SCIENCE MISSION. THE SCOPE OF THIS FOLLOW-ON EFFORT INCLUDES CONDUCTING ALL ELEMENTS OF HST OPERATIONS OTHER THAN… |
| 2025-12-01 | 115 | Funding only | $6.00M | THE MOSES II EFFORT IS A SOLE-SOURCE FOLLOW-ON CONTRACT TO MAINTAIN THE HEALTH AND SAFETY OF THE HST OBSERVATORY THROUGH THE NEXT PHASE OF ITS SCIENCE MISSION. THE SCOPE OF THIS FOLLOW-ON EFFORT INCLUDES CONDUCTING ALL ELEMENTS OF HST OPERATIONS OTHER THAN… |
| 2025-11-12 | 114 | Funding only | $2.10M | THE MOSES II EFFORT IS A SOLE-SOURCE FOLLOW-ON CONTRACT TO MAINTAIN THE HEALTH AND SAFETY OF THE HST OBSERVATORY THROUGH THE NEXT PHASE OF ITS SCIENCE MISSION. THE SCOPE OF THIS FOLLOW-ON EFFORT INCLUDES CONDUCTING ALL ELEMENTS OF HST OPERATIONS OTHER THAN… |
| 2025-07-24 | 113 | Funding only | $5.00M | THE MOSES II EFFORT IS A SOLE-SOURCE FOLLOW-ON CONTRACT TO MAINTAIN THE HEALTH AND SAFETY OF THE HST OBSERVATORY THROUGH THE NEXT PHASE OF ITS SCIENCE MISSION. THE SCOPE OF THIS FOLLOW-ON EFFORT INCLUDES CONDUCTING ALL ELEMENTS OF HST OPERATIONS OTHER THAN… |
| 2025-06-04 | 112 | Funding only | $3.99M | THE MOSES II EFFORT IS A SOLE-SOURCE FOLLOW-ON CONTRACT TO MAINTAIN THE HEALTH AND SAFETY OF THE HST OBSERVATORY THROUGH THE NEXT PHASE OF ITS SCIENCE MISSION. THE SCOPE OF THIS FOLLOW-ON EFFORT INCLUDES CONDUCTING ALL ELEMENTS OF HST OPERATIONS OTHER THAN… |
| 2025-05-01 | 111 | Funding only | $2.97M | THE MOSES II EFFORT IS A SOLE-SOURCE FOLLOW-ON CONTRACT TO MAINTAIN THE HEALTH AND SAFETY OF THE HST OBSERVATORY THROUGH THE NEXT PHASE OF ITS SCIENCE MISSION. THE SCOPE OF THIS FOLLOW-ON EFFORT INCLUDES CONDUCTING ALL ELEMENTS OF HST OPERATIONS OTHER THAN… |
| 2025-04-30 | 110 | Administrative change | $0 | REMOVAL OF CLAUSES/DRDS IAW EO 14173, 14168, 14148 AND 14057.THE MOSES II EFFORT IS A SOLE-SOURCE FOLLOW-ON CONTRACT TO MAINTAIN THE HEALTH AND SAFETY OF THE HST OBSERVATORY THROUGH THE NEXT PHASE OF ITS SCIENCE MISSION. THE SCOPE OF THIS FOLLOW-ON EFFORT… |
| 2025-03-03 | 109 | Funding only | $900.0K | THE MOSES II EFFORT IS A SOLE-SOURCE FOLLOW-ON CONTRACT TO MAINTAIN THE HEALTH AND SAFETY OF THE HST OBSERVATORY THROUGH THE NEXT PHASE OF ITS SCIENCE MISSION. THE SCOPE OF THIS FOLLOW-ON EFFORT INCLUDES CONDUCTING ALL ELEMENTS OF HST OPERATIONS OTHER THAN… |
| 2025-01-30 | 108 | Funding only | $5.12M | THE MOSES II EFFORT IS A SOLE-SOURCE FOLLOW-ON CONTRACT TO MAINTAIN THE HEALTH AND SAFETY OF THE HST OBSERVATORY THROUGH THE NEXT PHASE OF ITS SCIENCE MISSION. THE SCOPE OF THIS FOLLOW-ON EFFORT INCLUDES CONDUCTING ALL ELEMENTS OF HST OPERATIONS OTHER THAN… |
| 2024-12-16 | 107 | Funding only | $2.50M | THE MOSES II EFFORT IS A SOLE-SOURCE FOLLOW-ON CONTRACT TO MAINTAIN THE HEALTH AND SAFETY OF THE HST OBSERVATORY THROUGH THE NEXT PHASE OF ITS SCIENCE MISSION. THE SCOPE OF THIS FOLLOW-ON EFFORT INCLUDES CONDUCTING ALL ELEMENTS OF HST OPERATIONS OTHER THAN… |
| 2024-10-23 | 106 | Funding only | $3.12M | THE MOSES II EFFORT IS A SOLE-SOURCE FOLLOW-ON CONTRACT TO MAINTAIN THE HEALTH AND SAFETY OF THE HST OBSERVATORY THROUGH THE NEXT PHASE OF ITS SCIENCE MISSION. THE SCOPE OF THIS FOLLOW-ON EFFORT INCLUDES CONDUCTING ALL ELEMENTS OF HST OPERATIONS OTHER THAN… |
| 2024-09-17 | 105 | Funding only | $2.80M | THE MOSES II EFFORT IS A SOLE-SOURCE FOLLOW-ON CONTRACT TO MAINTAIN THE HEALTH AND SAFETY OF THE HST OBSERVATORY THROUGH THE NEXT PHASE OF ITS SCIENCE MISSION. THE SCOPE OF THIS FOLLOW-ON EFFORT INCLUDES CONDUCTING ALL ELEMENTS OF HST OPERATIONS OTHER THAN… |
| 2024-07-16 | 104 | Funding only | $4.22M | THE MOSES II EFFORT IS A SOLE-SOURCE FOLLOW-ON CONTRACT TO MAINTAIN THE HEALTH AND SAFETY OF THE HST OBSERVATORY THROUGH THE NEXT PHASE OF ITS SCIENCE MISSION. THE SCOPE OF THIS FOLLOW-ON EFFORT INCLUDES CONDUCTING ALL ELEMENTS OF HST OPERATIONS OTHER THAN… |
| 2024-05-01 | 103 | Funding only | $4.50M | THE MOSES II EFFORT IS A SOLE-SOURCE FOLLOW-ON CONTRACT TO MAINTAIN THE HEALTH AND SAFETY OF THE HST OBSERVATORY THROUGH THE NEXT PHASE OF ITS SCIENCE MISSION. THE SCOPE OF THIS FOLLOW-ON EFFORT INCLUDES CONDUCTING ALL ELEMENTS OF HST OPERATIONS OTHER THAN… |
| 2024-03-26 | 102 | Funding only | $2.75M | THE MOSES II EFFORT IS A SOLE-SOURCE FOLLOW-ON CONTRACT TO MAINTAIN THE HEALTH AND SAFETY OF THE HST OBSERVATORY THROUGH THE NEXT PHASE OF ITS SCIENCE MISSION. THE SCOPE OF THIS FOLLOW-ON EFFORT INCLUDES CONDUCTING ALL ELEMENTS OF HST OPERATIONS OTHER THAN… |
| 2024-02-15 | 101 | Funding only | $2.62M | THE MOSES II EFFORT IS A SOLE-SOURCE FOLLOW-ON CONTRACT TO MAINTAIN THE HEALTH AND SAFETY OF THE HST OBSERVATORY THROUGH THE NEXT PHASE OF ITS SCIENCE MISSION. THE SCOPE OF THIS FOLLOW-ON EFFORT INCLUDES CONDUCTING ALL ELEMENTS OF HST OPERATIONS OTHER THAN… |
| 2023-12-20 | 100 | Funding only | $3.00M | THE MOSES II EFFORT IS A SOLE-SOURCE FOLLOW-ON CONTRACT TO MAINTAIN THE HEALTH AND SAFETY OF THE HST OBSERVATORY THROUGH THE NEXT PHASE OF ITS SCIENCE MISSION. THE SCOPE OF THIS FOLLOW-ON EFFORT INCLUDES CONDUCTING ALL ELEMENTS OF HST OPERATIONS OTHER THAN… |
| 2023-11-22 | 99 | Funding only | $742.9K | THE MOSES II EFFORT IS A SOLE-SOURCE FOLLOW-ON CONTRACT TO MAINTAIN THE HEALTH AND SAFETY OF THE HST OBSERVATORY THROUGH THE NEXT PHASE OF ITS SCIENCE MISSION. THE SCOPE OF THIS FOLLOW-ON EFFORT INCLUDES CONDUCTING ALL ELEMENTS OF HST OPERATIONS OTHER THAN… |
| 2023-05-24 | 98 | Administrative change | $0 | THE MOSES II EFFORT IS A SOLE-SOURCE FOLLOW-ON CONTRACT TO MAINTAIN THE HEALTH AND SAFETY OF THE HST OBSERVATORY THROUGH THE NEXT PHASE OF ITS SCIENCE MISSION. THE SCOPE OF THIS FOLLOW-ON EFFORT INCLUDES CONDUCTING ALL ELEMENTS OF HST OPERATIONS OTHER THAN… |
| 2023-03-02 | 97 | Funding only | $16.00M | THE MOSES II EFFORT IS A SOLE-SOURCE FOLLOW-ON CONTRACT TO MAINTAIN THE HEALTH AND SAFETY OF THE HST OBSERVATORY THROUGH THE NEXT PHASE OF ITS SCIENCE MISSION. THE SCOPE OF THIS FOLLOW-ON EFFORT INCLUDES CONDUCTING ALL ELEMENTS OF HST OPERATIONS OTHER THAN… |
| 2023-02-14 | 96 | Vendor address changed | $0 | THE MOSES II EFFORT IS A SOLE-SOURCE FOLLOW-ON CONTRACT TO MAINTAIN THE HEALTH AND SAFETY OF THE HST OBSERVATORY THROUGH THE NEXT PHASE OF ITS SCIENCE MISSION. THE SCOPE OF THIS FOLLOW-ON EFFORT INCLUDES CONDUCTING ALL ELEMENTS OF HST OPERATIONS OTHER THAN… |
| 2022-10-26 | 95 | Funding only | $5.00M | THE MOSES II EFFORT IS A SOLE-SOURCE FOLLOW-ON CONTRACT TO MAINTAIN THE HEALTH AND SAFETY OF THE HST OBSERVATORY THROUGH THE NEXT PHASE OF ITS SCIENCE MISSION. THE SCOPE OF THIS FOLLOW-ON EFFORT INCLUDES CONDUCTING ALL ELEMENTS OF HST OPERATIONS OTHER THAN… |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-25). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗