W9123823C0014↗

Granite Construction Company received this contract from W075 Endist Sacramento, Department of the Army: $199.93M obligated so far for construction of other non-building facilities. It runs to 2026-12-02.

Key facts · data as of Oct 25, 2026

Recipient
Granite Construction Company
Awarding agency
Department of the Army (Department of Defense)
Contracting office
W075 Endist Sacramento (W91238)
Obligated to date
$199.93M
Potential value
$239.13M
Ends
2026-12-02

Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 25, 2026.

Cite this page: SpendQuery, Award W9123823C0014, data as of Oct 25, 2026, https://spendquery.com/award?id=CONT_AWD_W9123823C0014_9700_-NONE-_-NONE-

THE SACRAMENTO WEIR WIDENING WILL REDUCE WATER SURFACE ELEVATION IN SACRAMENTO RIVER AND ALLOW WATER TO FLOW INTO THE YOLO BYPASS SYSTEM. PROJECT CONSISTS OF CONSTRUCTION OF A PASSIVE WEIR, LEVEE SETBACK, FISH PASSAGE CONTROL AMONG OTHERS.

Definitive Contract · Department of the Army · to Granite Construction Company (UEI VAYJNMM2KBE5) · data as of 2026-10-25

Obligated to date$199.93M45 actions
Current value$239.13Mwith options exercised
Period2023-06-01 → 2026-12-02current end date

Up for re-bid: ends 2026-12-02. Recompete brief → · USACE SPK DBB Construction - Sacramento River East Levee Contract 5 (SREL C5), Sacramento, California ↗

What it is

Product or service
Construction of Other Non-Building Facilities (PSC Y1PZ)
Industry
Other Heavy and Civil Engineering Construction (NAICS 237990)
Contracting office
W075 Endist Sacramento (W91238)
Competition
Full and open competition · 3 offers received
Pricing
Firm fixed price
How it was bought
Standalone contract
Solicitation
W9123823B0005
Where the work is
Yolo, CA · district CA-07
Funding law
Other emergency or disaster supplementals

Obligations by fiscal year

FY2023$172.95M
FY2024$1.15M
FY2025$3.36M
FY2026$22.47M

SpendQuery holds FY2023 on; earlier years are on USAspending.gov.

Subcontractors: where the money went next

No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.

Every action

45 actions since 2023-05-03. Each is a modification or amendment with the money it added or took back.

DateModificationKindAmountWhat the agency wrote
2026-07-23A00032Supplemental agreement (work within scope)$4.00MARCF SACRAMENTO BYPASS WEIR WIDENING CLINS 001, 1042 AND 1044 R00050 - CD055-2 REPLACE N ABUTMENT - NTE INCREASE
2026-07-16P00012Supplemental agreement (work within scope)$659.0KARCF SAC BYPASS WEIR WIDENING CLINS 1041 AND1044 R00049/CD040-2 DEMOLISH EXISTING AB2 ABUTMENT
2026-07-01A00031Supplemental agreement (work within scope)$85.5KARCF SAC BYPASS WEIR WIDENING CLIN 0034/ MOD U00038, R00048/CD060 (VEQ- SOIL TYPE 2)(100% NONFED) (P2 NO. 456852)
2026-06-12P00011Supplemental agreement (work within scope)$7.00MARCF SAC BYPASS WEIR WIDENING CLIN 1047/ MOD R00047/CD054-1 (PT 1 WEIR STRUCTURAL BACKFILL)(100% NONFED) (P2 NO. 456852)
2026-05-27PZ0010Change order definitized$187.2KARCF SAC BYPASS WEIR WIDENING DEFINITIZE CHANGE ORDER CD 49 - ADDITIONAL INSTRUMENTATION
2026-04-27A00030Supplemental agreement (work within scope)$58.6KARCF SAC BYPASS WEIR WIDENING RAZOR WIRE AND AGG SURFACING
2026-04-23A00029Supplemental agreement (work within scope)$15.6KARCF SAC BYPASS WEIR WIDENING REA FOR DIFFERING SITE CONDITIONS ENCOUNTERED DURING EXCAVATION OF A FIBER OPTIC TRENCH
2026-04-17P00009Supplemental agreement (work within scope)$3.50MUNDEFINITIZED CONTRACT ACTION TO CONSTRUCT NORTH ABUTMENT PER THE REVISED DRAWINGS AND SPECIFICATIONS PROVIDED.
2026-03-12A00028Supplemental agreement (work within scope)$150.9KIN-PROGRESS QUANTITY INCREASE OF 26,263.29 CUBIC YARD FOR SOIL TYPE 1 IN-PROGRESS QUANTITY INCREASE OF 1,379.29 CUBIC YARD FOR SOIL TYPE 4
2026-03-06P00008Supplemental agreement (work within scope)$1.58MCD 41 / MOD REFERENCE R00040 REA BASED ON CHANGED VEHICLE BRIDGE PILE TIP ELEVATIONS FOR 51 PILES FROM AB1 THROUGH AB2
2026-02-24A00027Supplemental agreement (work within scope)-$223CD 45-2 / R00037 THIS MODIFICATION DEFINITIZES PREVIOUSLY EXECUTED MODIFICATION REFERENCE R00031 - PROVIDE ALL NECESSARY ITEMS REQUIRED TO INSTALL/MONITOR TWO ZERO-ANNULUS DIRECT PUSH PIEZOMETERS AT SPECIFIC LOCATIONS.
2026-02-06P00007Supplemental agreement (work within scope)$4.00MR00039 CD 40-1 AB 2 DEMOLISH EXISTING AB ABUTMENT 1. CONTRACTOR TO DEMOLISH ABUTMENT 2 TO THE EXTENTS, GRADES, AND LIMITS AS DESCRIBED IN REVISED DRAWING CD-105 AND PROCURE 173 ADDITIONAL PILES FABRICATED OF ASTM A252, GRADE 3, 60 KSI STEEL.
2026-02-05A00026Supplemental agreement (work within scope)$121.3KCONTRACT NO. W9123823C0014 ARCF SACRAMENTO BYPASS WEIR WIDENING. R00038 CD050 - UTILITY CONFLICT IN FP (RFI 229). TOTAL CONTRACT PRICE INCREASED BY $121,319.75. THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION.
2026-01-29A00025Supplemental agreement (work within scope)$9.2KCD 48 - GIRDER STORAGE COSTS REA STORAGE COSTS INCURRED FOR AN ADDITIONAL SEVEN MONTHS OF STORAGE FOR GIRDERS SUPPORTING SPANS C4 AND C5
2025-11-25A00024Supplemental agreement (work within scope)$299.2KCD 44 - CHANGES TO BULKHEAD GUARDRAIL CONFIGURATION CD 47 - GOV'T DIRECTED WORK TO INVESTIGATE, ADDRESS, AND/OR MONITOR THE SETTLEMENT OF THE NORTHERN WEIR ABUTMENT
2025-11-17A00023Supplemental agreement (work within scope)$53.7KREA FOR ADDITIONAL COSTS TO OBTAIN NEW PERMIT COVERAGE AND TO MAINTAIN COMPLIANCE WITH THE PERMIT REQUIREMENTS FOR THE REMAINING DURATION OF THE CONTRACT. STATE WATER BOARD REQUIRES PERMIT COVERAGE UNDER THE 2022 CONSTRUCTION GENERAL PERMIT.
2025-11-13A00022Supplemental agreement (work within scope)$150.0KWINTERIZING EFFORTS TO PREVENT EROSION OVER THE WINTER'S RAINY SEASON WHILE THE GOVERNMENT INVESTIGATES CONCERNS REGARDING THE WEIR STILLING BASIN AND ASSOCIATED SLAB SUBGRADE.
2025-11-05P00006Change order$600.0KADDITIONAL INSTRUMENTATION AND SUBSURFACE INVESTIGATIONS ARE NECESSARY TO PROVIDE ADDITIONAL GEOTECHNICAL INFORMATION ABOUT CURRENT SUBSURFACE CONDITIONS IN ORDER TO HAVE SUFFICIENT INFORMATION FOR A REDESIGN OF THE NORTH ABUTMENT.
2025-09-03A00021Change order$51.0KCD 45-1 INSTALL 2 PUSH-IN PIEZOMETERS DATA FROM THE INSTALLATION OF THESE PUSH-IN PIEZOMETERS WILL SUPPORT AND INFLUENCE A COURSE OF ACTION DIRECTLY RELATED TO THE RESOLUTION OF THE NORTH ABUTMENT WINGWALL SETTLEMENT/REPLACEMENT CHANGE CD 40-1.
2025-09-03A00020Supplemental agreement (work within scope)$51.5KDELETE FIBER OPTIC VAULT PER GOVERNMENT RESPONSE TO RFI 190
2025-08-19A00019Supplemental agreement (work within scope)$243.6KCD 34 - DESIGN CHANGES TO SOUTH ABUTMENT APPROACH
2025-08-12A00018Supplemental agreement (work within scope)$9.8KCHANGE: CD038 TITLE: VEQ - CLIN 35 INTERIM QTY IN PROGRESS QUANTITIES FOR CLIN 35 CHANGE: CD043 TITLE: NOC 12 - PG&E SPLICE BOX REA REA FOR REDESIGN AND RE-FABRICATION REQUIRED TO COMPLY WITH DIRECTED CHANGES PER THE GOV'T RESPONSE TO RFI 179.
2025-07-28A00017Supplemental agreement (work within scope)$379.5KVARIATION IN ESTIMATED QUANTITIES - CLIN 33 SOIL TYPE 1
2025-07-24P00005Administrative change$0SAC WEIR CONST - NON - FEDERAL FUNDING
2025-07-08A00016Supplemental agreement (work within scope)$196.6KADJUSTMENT TO FINAL ESTIMATED QUANTITIES TO CLIN 79 AND AN REA FOR WORK ON EXISTING STILLING BASIN
2025-05-20A00015Supplemental agreement (work within scope)$175.0KPHASE 2 TOPO SURVEY REA REA FOR MULTIPLE PRE-CONSTRUCTION SURVEY VISITS RFI 158 - LIFT GATE ALIGNMENT CONFLICT IN SELECT DRAWINGS LEBLS ACCESS RD REPAIR REA REA FOR THE REPAIR AND MAINTENANCE OF THE LEBLS CONNECTION ROAD FOR DWR EMERGENCY ACCESS.
2025-05-01A00014Supplemental agreement (work within scope)$162.6KCD 33 - REA FOR GATE STEM/GUIDE DESIGN REVISIONS CD 35 - REA FOR GROUNDBREAKING CEREMONY STANDDOWN
2025-04-15A00013Supplemental agreement (work within scope)$243.6KCD 17 - REA FOR 86 DAYS OF PILE DRIVING EQUIPMENT STANDBY COSTS. CD 25 - REA FOR THE REMOVAL AND DISPOSAL COSTS OF UNKNOWN SUB-SURFACE CONCRETE OBSTRUCTIONS.
2025-04-01A00012Supplemental agreement (work within scope)$262.6KREA FOR DIFFERING SITE CONDITIONS BASED ON EARTHWORK AND AGGREGATE BASE DISCREPANCIES OF THE CENTRAL EMBANKMENT RAMP.
2025-03-28A00011Supplemental agreement (work within scope)$33.2KMODIFICATION FOR THE FISH LADDER TOP OF WALL THICKNESS ENGINEERING CHANGE AND SWAINSON'S HAWK BIOLOGICAL MONITORING REA
2025-02-26A00010Supplemental agreement (work within scope)$40.5KA10 | R17 - VEHICLE BRIDGE PILE HORIZONTAL TOLERANCE CHANGE
2025-02-18A00009Supplemental agreement (work within scope)$370.1KSAC WEIR CONST - NON - FEDERAL FUNDING A09/R14 - REA FOR RAILROAD EMBANKMENT & OLD RIVER RD EXCAVATION
2025-01-21A00008Supplemental agreement (work within scope)$213.3KCD 08 - DOWEL BAR MATERIAL SPECIFICATIONS CD 14 - N. ABUTMENT WING WALL REDESIGN
2024-12-20A00007Supplemental agreement (work within scope)$292.0KCD013 REA FOR VEH BRIDGE PIER REBAR CHANGES
2024-12-18P00004Supplemental agreement (work within scope)$583.0KSAC WEIR CONST - NON - FEDERAL FUNDING FISH PASSAGE PILE TIP ELEVATION CHANGE CD0010
2024-11-21A00006Supplemental agreement (work within scope)$53.3KMOD R9/A6 BAFFLE CHANGES CREDIT, REA FOR UNKNOWN UTILITIES, REA FOR WEIR ABUTMENT FOUNDATION PREP
2024-10-24A00005Supplemental agreement (work within scope)$0SAC WEIR CONST - NON - FEDERAL FUNDING
2024-09-16P00003Supplemental agreement (work within scope)$800.0KSAC WEIR CONST - NON - FEDERAL FUNDING CD012-1 PILE DRIVING SPEC REVISION R00007/P00003
2024-05-30A00004Supplemental agreement (work within scope)$49.1KSAC WEIR CONST - NON - FEDERAL FUNDING
2024-05-14A00003Supplemental agreement (work within scope)$202.6KSAC WEIR CONST - NON - FEDERAL FUNDING
2024-05-01A00002Supplemental agreement (work within scope)$43.3KSAC WEIR CONST - NON - FEDERAL FUNDING R00004/CD004 CLIMATE CONTROLLED STORAGE
2024-04-04A00001Supplemental agreement (work within scope)$59.2KSAC WEIR CONST - NON - FEDERAL FUNDING
2023-08-09P00002Administrative change$0SAC WEIR CONST - NON - FEDERAL FUNDING
2023-06-08P00001Administrative change$0SAC WEIR CONST - NON - FEDERAL FUNDING
2023-05-030$172.95MTHE SACRAMENTO WEIR WIDENING WILL REDUCE WATER SURFACE ELEVATION IN SACRAMENTO RIVER AND ALLOW WATER TO FLOW INTO THE YOLO BYPASS SYSTEM. PROJECT CONSISTS OF CONSTRUCTION OF A PASSIVE WEIR, LEVEE SETBACK, FISH PASSAGE CONTROL AMONG OTHERS.

Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-25). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗