In plain English
This section requires that contracts, purchase orders, or BPAs using the fast payment procedure include specific terms: supplies must be shipped prepaid, invoices must go to a designated office or the contracting officer, and the consignee's copy must have a notification statement. It matters because it sets clear rules for payment and delivery, helping contractors avoid payment delays and disputes.
Applies to: Contracts, purchase orders, or BPAs using the fast payment procedure
What it requires
- Require that supplies be shipped transportation or postage prepaid.
- Require that invoices be submitted directly to the designated finance office or, for unpriced purchase orders, to the contracting officer.
- Include the specified consignee notification statement on the consignee's copy.
Key terms: fast payment procedure · priced or unpriced contracts · purchase orders · BPAs · consignee
Written by AI from this section's text. A guide, not legal advice: the text below rules.
The text
Priced or unpriced contracts, purchase orders, or BPAs using the fast payment procedure shall include the following:
(a) A requirement that the supplies be shipped transportation or postage prepaid.
(b) A requirement that invoices be submitted directly to the finance or other office designated in the order, or in the case of unpriced purchase orders, to the contracting officer (see 13.302-2(c)).
(c) The following statement on the consignee's copy:
Consignee's Notification to Purchasing Activity of Nonreceipt, Damage, or Nonconformance
The consignee shall notify the purchasing office promptly after the specified date of delivery of supplies not received, damaged in transit, or not conforming to specifications of the purchase order. Unless extenuating circumstances exist, the notification should be made not later than 60 days after the specified date of delivery.
Sections it refers to
- 13.302-2 Unpriced purchase orders.
← 13.402 Conditions for use. · 13.404 Contract clause. →
Rule changes for FAR Part 13
- Federal Acquisition Regulation: Revolutionary FAR Overhaul Parts 8, 12, 13, 15, 38, 44, and 51 ↗ · proposed 2026-09-18 · comments due 2026-10-19
- Federal Acquisition Regulation: Prohibition on Certain Semiconductor Products and Services ↗ · proposed 2026-02-17 · comments due 2026-04-20
- Federal Acquisition Regulation: Inflation Adjustment of Acquisition-Related Thresholds ↗ · final rule 2025-08-27 · effective 2025-10-01
- Federal Acquisition Regulation: Preventing Organizational Conflicts of Interest in Federal Acquisition ↗ · proposed 2025-01-15 · comments due 2025-03-17
- Federal Acquisition Regulation: Prohibition on Unmanned Aircraft Systems From Covered Foreign Entities ↗ · final rule 2024-12-30
- Federal Acquisition Regulation; Technical Amendments ↗ · final rule 2024-12-16 · effective 2025-01-03
- Federal Acquisition Regulation: Inflation Adjustment of Acquisition-Related Thresholds ↗ · proposed 2024-11-29 · comments due 2025-01-28
- Federal Acquisition Regulation: Prohibition on Unmanned Aircraft Systems From Covered Foreign Entities ↗ · final rule 2024-11-12 · effective 2024-11-12
Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗. Plain words for the terms: glossary.