FAR 13.404 Contract clause.
The codified text (eCFR, as of 2026-10-02). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule.
In plain English
This section tells the contracting officer when to include the Fast Payment Procedure clause (52.213-1) in solicitations and contracts. It applies when the conditions in 13.402 are met and the fast payment procedure is intended to be used. For BPAs, the contracting officer may put the clause either in the BPA or in orders under it.
Applies to: Contracting officers
What it requires
- Insert the clause at 52.213-1, Fast Payment Procedure, in solicitations and contracts when the conditions in 13.402 are applicable and fast payment is intended to be used
Key terms: Fast Payment Procedure · 52.213-1 · 13.402 · BPAs · solicitations
Written by AI from this section's text. A guide, not legal advice: the text below rules.
The text
The contracting officer shall insert the clause at 52.213-1, Fast Payment Procedure, in solicitations and contracts when the conditions in 13.402 are applicable and it is intended that the fast payment procedure be used in the contract (in the case of BPAs, the contracting officer may elect to insert the clause either in the BPA or in orders under the BPA).
Sections that refer to it
- 52.213-1 Fast Payment Procedure.
← 13.403 Preparation and execution of orders. · 13.500 General. →
Rule changes for FAR Part 13
- Federal Acquisition Regulation: Revolutionary FAR Overhaul Parts 8, 12, 13, 15, 38, 44, and 51 ↗ · proposed 2026-09-18 · comments due 2026-10-19
- Federal Acquisition Regulation: Prohibition on Certain Semiconductor Products and Services ↗ · proposed 2026-02-17 · comments due 2026-04-20
- Federal Acquisition Regulation: Inflation Adjustment of Acquisition-Related Thresholds ↗ · final rule 2025-08-27 · effective 2025-10-01
- Federal Acquisition Regulation: Preventing Organizational Conflicts of Interest in Federal Acquisition ↗ · proposed 2025-01-15 · comments due 2025-03-17
- Federal Acquisition Regulation: Prohibition on Unmanned Aircraft Systems From Covered Foreign Entities ↗ · final rule 2024-12-30
- Federal Acquisition Regulation; Technical Amendments ↗ · final rule 2024-12-16 · effective 2025-01-03
- Federal Acquisition Regulation: Inflation Adjustment of Acquisition-Related Thresholds ↗ · proposed 2024-11-29 · comments due 2025-01-28
- Federal Acquisition Regulation: Prohibition on Unmanned Aircraft Systems From Covered Foreign Entities ↗ · final rule 2024-11-12 · effective 2024-11-12
Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗. Plain words for the terms: glossary.