FAR 19.809-2 Limitations on subcontracting and nonmanufacturer rule.
The codified text (eCFR, as of 2026-10-02). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule.
In plain English
This section sets limits on how much an 8(a) participant can subcontract under an 8(a) contract. It requires the participant to perform a minimum percentage of the work with its own employees, depending on the type of work, and specifies when compliance is measured. It also allows the SBA District Director to waive certain compliance timing requirements under specific conditions.
Applies to: 8(a) program participants awarded contracts or orders
What it requires
- For services (except construction), perform at least 50 percent of the cost incurred for personnel with its own employees.
- For supplies or products (other than a nonmanufacturer procurement), perform at least 50 percent of the cost of manufacturing (excluding materials) with its own employees.
- For general construction, perform at least 15 percent of the cost with its own employees (excluding materials).
- For construction by special trade contractors, perform at least 25 percent of the cost with its own employees (excluding materials).
Key terms: limitations on subcontracting · 8(a) participant · nonmanufacturer rule · compliance period · waiver
Written by AI from this section's text. A guide, not legal advice: the text below rules.
The text
(a) Limitations on subcontracting. To be awarded a contract or order under the 8(a) program, the 8(a) participant is required to perform—
(1) For services (except construction), at least 50 percent of the cost incurred for personnel with its own employees;
(2) For supplies or products (other than a procurement from a nonmanufacturer of such supplies or products), at least 50 percent of the cost of manufacturing the supplies or products (not including the cost of materials);
(3) For general construction, at least 15 percent of the cost with its own employees (not including the cost of materials); and
(4) For construction by special trade contractors, at least 25 percent of the cost with its own employees (not including the cost of materials).
(b) Compliance period. An 8(a) contractor is required to comply with the limitations on subcontracting—
(1) For a contract under the 8(a) program, either by the end of the base term and then by the end of each subsequent option period or by the end of the performance period for each order issued under the contract, at the contracting officer's discretion; and
(2) For an order competed exclusively among contractors who are 8(a) participants or for an order issued directly to one 8(a) contractor in accordance with 19.504(c)(1)(ii), by the end of the performance period for the order.
(c) Waiver. The applicable SBA District Director may waive the provisions in paragraph (b)(1) requiring a participant to comply with the limitations on subcontracting for each period of performance or for each order. Instead, the SBA District Director may permit the participant to subcontract in excess of the limitations on subcontracting where the SBA District Director makes a written determination that larger amounts of subcontracting are essential during certain stages of performance.
(1) The 8(a) participant is required to provide the SBA District Director written assurance that the participant will ultimately comply with the requirements of this section prior to contract completion. The contracting officer shall review the written assurance and inform the 8(a) participant of their concurrence or nonconcurrence. The 8(a) participant can only submit the written assurance to the SBA District Director upon concurrence by the contracting officer.
(2) The contracting officer does not have the authority to waive the provisions of this section requiring an 8(a) participant to comply with the limitations on subcontracting for each period of performance or order, even if the agency has a Partnership Agreement with SBA.
(3) Where the 8(a) participant does not ultimately comply with the limitations on subcontracting by the end of the contract, SBA will not grant future waivers for the 8(a) participant.
(d) Nonmanufacturer rule. See 19.505(c) for application of the nonmanufacturer rule, inclusive of waivers and exceptions to the nonmanufacturer rule.
← 19.809-1 Preaward survey. · 19.810 SBA appeals. →
Rule changes for FAR Part 19
- Federal Acquisition Regulation: Inflation Adjustment of Acquisition-Related Thresholds ↗ · final rule 2025-08-27 · effective 2025-10-01
- Federal Acquisition Regulation: Small Business Participation on Certain Multiple-Award Contracts ↗ · proposed 2025-06-12
- Federal Acquisition Regulation: Small Business Participation on Certain Multiple-Award Contracts ↗ · proposed 2025-01-15 · comments due 2025-03-17
- Federal Acquisition Regulation: Subcontracting to Puerto Rican and Covered Territory Small Businesses ↗ · final rule 2025-01-03 · effective 2025-01-17
- Federal Acquisition Regulation: Rerepresentation of Size and Socioeconomic Status ↗ · final rule 2025-01-03 · effective 2025-01-17
- Federal Acquisition Regulation: Certification of Service-Disabled Veteran-Owned Small Businesses ↗ · final rule 2024-12-16 · effective 2024-12-16
- Federal Acquisition Regulation: Inflation Adjustment of Acquisition-Related Thresholds ↗ · proposed 2024-11-29 · comments due 2025-01-28
- Federal Acquisition Regulation; Technical Amendments ↗ · final rule 2024-08-29 · effective 2024-09-30
Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗. Plain words for the terms: glossary.