FAR and DFARS › DFARS Part 225: Foreign Acquisition › Subpart 225.70
DFARS 225.7018-3 Exceptions.
The codified text (eCFR, as of 2026-10-02). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule.
In plain English
This section lists exceptions to the DFARS restriction on acquiring certain covered materials. It tells contractors when the restriction does not apply, such as for small purchases, items used outside the U.S., or certain commercial items. Knowing these exceptions helps determine if a contract is subject to the restriction.
Applies to: Acquisitions subject to the restriction in DFARS 225.7018-2
Key terms: simplified acquisition threshold · covered material · commercially available off-the-shelf item · mill product · required form
Written by AI from this section's text. A guide, not legal advice: the text below rules.
The text
The restriction in section 225.7018-2 does not apply to an acquisition—
(a) At or below the simplified acquisition threshold;
(b) Outside the United States of an item for use outside the United States; or
(c) Of an end item containing a covered material that is—
(1) A commercially available off-the-shelf item (but see PGI 225.7018-3(c)(1) with regard to commercially available samarium-cobalt magnets), other than—
(i) A commercially available off-the-shelf item that is—
(A) 50 percent or more tungsten by weight effective through December 31, 2026; or
(B) 50 percent or more covered material by weight effective January 1, 2027;
(ii) Effective through December 31, 2026, a tantalum metal, tantalum alloy, or tungsten heavy alloy mill product, such as bar, billet, slab, wire, cube, sphere, block, blank, plate, or sheet, that has not been incorporated into an end item, subsystem, assembly, or component; or
(iii) Effective January 1, 2027, a covered material that is a mill product such as bar, billet, slab, wire, cube, sphere, block, blank, plate, or sheet, that has not been incorporated into an end item, subsystem, assembly, or component;
(2) An electronic device, unless the Secretary of Defense, upon the recommendation of the Strategic and Critical Materials Board of Directors pursuant to 50 U.S.C. 98h-1 determines that the domestic availability of a particular electronic device is critical to national security (but see PGI 225.7018-3(c)(2) with regard to samarium-cobalt magnets used in electronic components); or
(3) A neodymium-iron-boron magnet manufactured from recycled material if the milling of the recycled material and sintering of the final magnet takes place in the United States.
(d) If the authorized agency official concerned, as specified in 225.7018-4, determines that compliant covered materials of satisfactory quality and quantity, in the required form, cannot be procured as and when needed at a reasonable price.
(1) For tantalum metal, tantalum alloy, or tungsten heavy alloy, the term “required form” refers to the form of the mill product, such as bar, billet, wire, slab, plate, or sheet, in the grade appropriate for the production of a finished end item to be delivered to the Government under the contract; or a finished component assembled into an end item to be delivered to the Government under the contract.
(2) For samarium-cobalt magnets or neodymium-iron-boron magnets, the term “required form” refers to the form and properties of the magnets.
Sections it refers to
- 225.7018-2 Restriction.
- 225.7018-4 Nonavailability determination.
Sections that refer to it
- 212.505 Applicability of certain laws to contracts for the acquisition of COTS items.
- 225.7018-2 Restriction.
- 225.7018-4 Nonavailability determination.
← 225.7018-2 Restriction. · 225.7018-4 Nonavailability determination. →
Rule changes for DFARS Part 225
- Defense Federal Acquisition Regulation Supplement: Modifications to Printed Circuit Board Acquisition Restrictions (DFARS Case 2022-D011) ↗ · proposed 2026-07-02 · comments due 2026-08-31
- Defense Federal Acquisition Regulation Supplement: Small Purchase Exception for the Acquisition of U.S. Flags (DFARS Case 2024-D013) ↗ · proposed 2026-06-25 · comments due 2026-08-24
- Defense Federal Acquisition Regulation Supplement: Inflation Adjustment of Acquisition-Related Thresholds (DFARS Case 2024-D002) ↗ · final rule 2025-08-25 · effective 2025-10-01
- Defense Federal Acquisition Regulation Supplement; Technical Amendments ↗ · final rule 2025-08-25 · effective 2025-08-25
- Defense Federal Acquisition Regulation Supplement: Inflation Adjustment of Acquisition-Related Thresholds (DFARS Case 2024-D002) ↗ · proposed 2025-01-17 · comments due 2025-03-18
- Defense Federal Acquisition Regulation Supplement; Technical Amendments ↗ · final rule 2024-12-18 · effective 2024-12-18
- Defense Federal Acquisition Regulation Supplement: Inapplicability of Additional Defense-Unique Laws and Certain Non-Statutory DFARS Clauses to Commercial Item Contracts (DFARS Case 2018-D074) ↗ · final rule 2024-11-15 · effective 2024-11-25
- Defense Federal Acquisition Regulation Supplement; Technical Amendments ↗ · final rule 2024-11-15 · effective 2024-11-15
Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗. Plain words for the terms: glossary.