DFARS 252.204-7022 Expediting Contract Closeout.

In plain English: This clause lets the Government and the contractor agree on the leftover dollar amount remaining on a contract once standard closeout steps are done. Either side waives any residual amount of $1,000 or less, so neither has to chase small balances. Residual amounts exclude anything tied to taxes or violations of law, and offsets across contracts count only where the law allows. (A summary written by AI from the official text below, which is what governs. Not legal advice.)

When it applies: as prescribed in 204.804-70, which says when contracting officers use it.

Last amended 2021-05-20 · This page's summary last updated 2026-11-07 · Text as of 2026-10-29 (the eCFR copy this page shows) · Official text of DFARS 252.204-7022 ↗

The codified text (eCFR, as of 2026-10-29). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule. Today's text against the overhaul, side by side.

Open SAM.gov notices that cite DFARS 252.204-7022 · Ask the AI chat about it

In more detail

Applies to: Government contracts and contractors at contract closeout, when the DFARS clause is included

What it requires

  • Complete the applicable closeout requirements of FAR 4.804 before agreeing on the residual amount
  • Mutually agree with the Government on the residual dollar amount remaining on the contract
  • Waive payment of any residual amount of $1,000 or less to which the contractor may be entitled at closeout

Key terms: residual dollar amount · contract closeout · waive · offsets · FAR 4.804

Written by AI from this section's text. A guide, not legal advice: the text below rules.

The text

As prescribed in 204.804-70, use the following clause:

Expediting Contract Closeout (MAY 2021)

(a) At the conclusion of all applicable closeout requirements of Federal Acquisition Regulation 4.804, the Government and Contractor shall mutually agree on the residual dollar amount remaining on the contract. Both the Government and Contractor agree to waive payment of any residual dollar amount of $1,000 or less to which either party may be entitled at the time of contract closeout.

(b) A residual dollar amount includes all money owed to either party at the end of the contract and as a result of the contract, excluding amounts connected in any way with taxation or a violation of law or regulation.

(c) For purposes of determining residual dollar amounts, offsets (e.g., across multiple contracts or orders) may be considered only to the extent permitted by law.

(End of clause)

Sections it refers to

Sections that refer to it

  • 204.804 Closeout of contract files.
  • 204.804-70 Contract clause.
  • 212.301 Solicitation provisions and contract clauses for the acquisition of commercial products and commercial services.

Related DFARS 252.204 sections

← 252.204-7021 Contractor Compliance With the Cybersecurity Maturity Model Certification Level Requirements. · 252.204-7023 Reporting Requirements for Contracted Services. →

Rule changes for DFARS Part 252

Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗. Plain words for the terms: glossary.