FAR and DFARS › DFARS Part 252: Solicitation Provisions and Contract Clauses › Subpart 252.2

DFARS 252.217-7003 Changes.

The codified text (eCFR, as of 2026-10-02). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule.

In plain English

This clause allows the Contracting Officer to make changes to a job order under a Master Agreement, including changes to drawings, work, place, time, or other requirements. If a change affects cost or time, the Contracting Officer must make an equitable adjustment and modify the job order in writing. The Contractor must request a price adjustment within ten days of notification, and must continue working as changed even if there is a disagreement.

Applies to: Contractors performing job orders under a Master Agreement

What it requires

  • Submit a request for price adjustment with a written estimate of increased cost within ten days after receiving notification of the change.
  • Request an extension of the ten-day period within that period if needed.
  • Continue proceeding with the job order as changed, even if there is a dispute over the adjustment.

Key terms: Contracting Officer · job order · Master Agreement · equitable adjustment · Disputes clause

Written by AI from this section's text. A guide, not legal advice: the text below rules.

The text

As prescribed in 217.7104(a), use the following clause:

Changes (DEC 1991)

(a) The Contracting Officer may, at any time and without notice to the sureties, by written change order, make changes within the general scope of any job order issued under the Master Agreement in—

(1) Drawings, designs, plans, and specifications;

(2) Work itemized;

(3) Place of performance of the work;

(4) Time of commencement or completion of the work; and

(5) Any other requirement of the job order.

(b) If a change causes an increase or decrease in the cost of, or time required for, performance of the job order, whether or not changed by the order, the Contracting Officer shall make an equitable adjustment in the price or date of completion, or both, and shall modify the job order in writing.

(1) Within ten days after the Contractor receives notification of the change, the Contractor shall submit to the Contracting Officer a request for price adjustment, together with a written estimate of the increased cost.

(2) The Contracting Officer may grant an extension of this period if the Contractor requests it within the ten day period.

(3) If the circumstances justify it, the Contracting Officer may accept and grant a request for equitable adjustment at any later time prior to final payment under the job order, except that the Contractor may not receive profit on a payment under a late request.

(c) If the Contractor includes in its claim the cost of property made obsolete or excess as a result of a change, the Contracting Officer shall have the right to prescribe the manner of disposition of that property.

(d) Failure to agree to any adjustment shall be a dispute within the meaning of the Disputes clause.

(e) Nothing in this clause shall excuse the Contractor from proceeding with the job order as changed.

(End of clause)

Sections it refers to

Sections that refer to it

← 252.217-7002 Offering property for exchange. · 252.217-7004 Job orders and compensation. →

Rule changes for DFARS Part 252

Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗. Plain words for the terms: glossary.

DFARS 252.217-7003 Changes · SpendQuery