DFARS 252.217-7004 Job orders and compensation.

In plain English: This clause governs how the government awards and prices ship repair work under a Master Agreement. Job orders are awarded when the Contracting Officer signs them and incorporate the Master Agreement's terms, and in urgent cases the Contracting Officer can order immediate work on a vessel that the contractor must perform. If the parties cannot agree on price, that becomes a dispute under the Master Agreement's Disputes clause, but the contractor must keep working in the meantime. (A summary written by AI from the official text below, which is what governs. Not legal advice.)

When it applies: as prescribed in 217.7104(a), which says when contracting officers use it.

Last amended 2016-12-22 · This page's summary last updated 2026-11-07 · Text as of 2026-10-29 (the eCFR copy this page shows) · Official text of DFARS 252.217-7004 ↗

The codified text (eCFR, as of 2026-10-29). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule. Today's text against the overhaul, side by side.

Open SAM.gov notices that cite DFARS 252.217-7004 · Ask the AI chat about it

In more detail

Applies to: contractors performing vessel repair work under job orders and a Master Agreement

What it requires

  • Comply with a written emergency order to perform immediate work on a vessel within the contractor's capabilities
  • Upon request, furnish the Contracting Officer a breakdown of costs incurred and estimated costs to complete the work
  • Maintain records supporting the cost of performing the work and make them available for inspection
  • Diligently proceed with ordered work even if the price has not been agreed

Key terms: job order · Master Agreement · Contracting Officer · written order · Disputes clause

Written by AI from this section's text. A guide, not legal advice: the text below rules.

The text

As prescribed in 217.7104(a), use the following clause:

Job Orders and Compensation (MAY 2006)

(a) The Contracting Officer shall solicit bids or proposals and make award of job orders. The issuance of a job order signed by the Contracting Officer constitutes award. The job order shall incorporate the terms and conditions of the Master Agreement.

(b) Whenever the Contracting Officer determines that a vessel, its cargo or stores, would be endangered by delay, or whenever the Contracting Officer determines that military necessity requires that immediate work on a vessel is necessary, the Contracting Officer may issue a written order to perform that work and the Contractor hereby agrees to comply with that order and to perform work on such vessel within its capabilities.

(1) As soon as practicable after the issuance of the order, the Contracting Officer and the Contractor shall negotiate a price for the work and the Contracting Officer shall issue a job order covering the work.

(2) The Contractor shall, upon request, furnish the Contracting Officer with a breakdown of costs incurred by the Contractor and an estimate of costs expected to be incurred in the performance of the work. The Contractor shall maintain, and make available for inspection by the Contracting Officer or the Contracting Officer's representative, records supporting the cost of performing the work.

(3) Failure of the parties to agree upon the price of the work shall constitute a dispute within the meaning of the Disputes clause of the Master Agreement. In the meantime, the Contractor shall diligently proceed to perform the work ordered.

(c)(1) If the nature of any repairs is such that their extent and probable cost cannot be ascertained readily, the Contracting Officer may issue a job order (on a sealed bid or negotiated basis) to determine the nature and extent of required repairs.

(2) Upon determination by the Contracting Officer of what work is necessary, the Contractor, if requested by the Contracting Officer, shall negotiate prices for performance of that work. The prices agreed upon shall be set forth in a modification of the job order.

(3) Failure of the parties to agree upon the price shall constitute a dispute under the Disputes clause. In the meantime, the Contractor shall diligently proceed to perform the work ordered.

(End of clause)

Sections it refers to

Sections that refer to it

Related DFARS 252.217 sections

← 252.217-7003 Changes. · 252.217-7005 Inspection and manner of doing work. →

Rule changes for DFARS Part 252