DFARS 252.237-7015 Loss or damage (weight of articles).

In plain English: This clause makes a contractor responsible for returning articles the Government furnishes for service, and for compensating the Government for articles that are lost or damaged beyond satisfactory repair. It also sets a per-pound payment for losses and allows a maximum weight loss before payment applies, with repairs of damaged items done at the contractor's expense. Disagreements over the credit amount are handled under the contract's Disputes clause. (A summary written by AI from the official text below, which is what governs. Not legal advice.)

When it applies: as prescribed in 237.7101(d), which says when contracting officers use it.

Last amended 2022-05-26 · This page's summary last updated 2026-11-07 · Text as of 2026-10-29 (the eCFR copy this page shows) · Official text of DFARS 252.237-7015 ↗

The codified text (eCFR, as of 2026-10-29). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule. Today's text against the overhaul, side by side.

Open SAM.gov notices that cite DFARS 252.237-7015 · Ask the AI chat about it

In more detail

Applies to: contractors that service Government-furnished articles, such as laundry or textile services

What it requires

  • Return the articles furnished for service under the contract
  • Indemnify the Government for articles that are lost or damaged and cannot be repaired satisfactorily in the Contracting Officer's opinion
  • Repair agreed-upon damaged articles at the contractor's expense in a manner satisfactory to the Contracting Officer
  • Pay the per-pound amount for lost or damaged articles only for weight losses exceeding the maximum allowable weight loss

Key terms: articles · maximum weight loss · per pound · Contracting Officer · Disputes clause

Written by AI from this section's text. A guide, not legal advice: the text below rules.

The text

As prescribed in 237.7101(d), use the following clause:

Loss or Damage (Weight of Articles) (DEC 1991)

(a) The Contractor shall—

(1) Be liable for return of the articles furnished for service under this contract; and

(2) Indemnify the Government for any articles delivered to the Contractor for servicing under this contract that are lost or damaged, and in the opinion of the Contracting Officer, cannot be repaired satisfactorily.

(b) The Contractor shall pay to the Government ________ per pound for lost or damaged articles. The Contractor shall pay the Government only for losses which exceed the maximum weight loss in paragraph (e) of this clause.

(c) Failure to agree on the amount of credit due will be treated as a dispute under the Disputes clause of this contract.

(d) In the case of damage to any articles that the Contracting Officer and the Contractor agree can be satisfactorily repaired, the Contractor shall repair the articles at its expense in a manner satisfactory to the Contracting Officer.

(e) The maximum weight loss allowable in servicing the laundry is ________ percent of the weight recorded on delivery tickets when the laundry is picked up. Any weight loss in excess of this amount shall be subject to the loss provisions of this clause.

(End of clause)

Sections it refers to

  • 237.7101 Solicitation provisions and contract clauses.

Sections that refer to it

  • 237.7101 Solicitation provisions and contract clauses.

Related DFARS 252.237 sections

← 252.237-7014 Loss or damage (count-of-articles). · 252.237-7016 Delivery tickets. →