FAR and DFARS › DFARS Part 252: Solicitation Provisions and Contract Clauses › Subpart 252.2

DFARS 252.237-7016 Delivery tickets.

In plain English: This clause governs delivery tickets for contracts where the contractor services articles, such as laundry, that it picks up from the government. The contractor must fill out delivery tickets in the number of copies and format the Contracting Officer approves when it receives the articles, and include a copy of each ticket with its invoice for payment. The alternates add pickup and delivery steps where the contractor verifies and records bag weight and bag type, so the government can check the quantities it is billed for. (A summary written by AI from the official text below, which is what governs. Not legal advice.)

When it applies: as prescribed in 237.7101(e), which says when contracting officers use it.

Last amended 2016-12-22 · This page's summary last updated 2026-11-07 · Text as of 2026-10-29 (the eCFR copy this page shows) · Official text of DFARS 252.237-7016 ↗

The codified text (eCFR, as of 2026-10-29). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule. Today's text against the overhaul, side by side.

Open SAM.gov notices that cite DFARS 252.237-7016 · Ask the AI chat about it

In more detail

Applies to: contractors that pick up and service articles (such as laundry) under a government contract

What it requires

  • Complete delivery tickets in the number of copies and form the Contracting Officer approves, when the articles are received
  • Include one copy of each delivery ticket with the invoice for payment
  • At pickup (Alternates I and II), verify the bag weight (and bag type under Alternate I) and record it on the delivery ticket, then give the Contracting Officer or representative a copy
  • At delivery (Alternates I and II), record the weight (and bag type under Alternate I) of the serviced articles on the delivery ticket

Key terms: delivery ticket · Contracting Officer · bag type · articles to be serviced · invoice for payment

Written by AI from this section's text. A guide, not legal advice: the text below rules.

The text

Basic. As prescribed in 237.7101(e) and (e)(1), use the following clause:

Delivery Tickets—Basic (NOV 2014)

(a) The Contractor shall complete delivery tickets in the number of copies required and in the form approved by the Contracting Officer, when it receives the articles to be serviced.

(b) The Contractor shall include one copy of each delivery ticket with its invoice for payment.

(End of clause)

Alternate I. As prescribed in 237.7101(e) and (e)(2), use the following clause, which includes paragraphs (c), (d), and (e) not included in the basic clause:

Delivery Tickets—Alternate I (NOV 2014)

(a) The Contractor shall complete delivery tickets in the number of copies required and in the form approved by the Contracting Officer, when it receives the articles to be serviced.

(b) The Contractor shall include one copy of each delivery ticket with its invoice for payment.

(c) Before the Contractor picks up articles for service under this contract, the Contracting Officer will ensure that—

(1) Each bag contains only articles within a single bag type as specified in the schedule; and

(2) Each bag is weighed and the weight and bag type are identified on the bag.

(d) The Contractor shall, at time of pickup—

(1) Verify the weight and bag type and record them on the delivery ticket; and

(2) Provide the Contracting Officer, or representative, a copy of the delivery ticket.

(e) At the time of delivery, the Contractor shall record the weight and bag type of serviced laundry on the delivery ticket. The Contracting Officer will ensure that this weight and bag type are verified at time of delivery.

(End of clause)

Alternate II. As prescribed in 237.7101(e) and (e)(3), use the following clause, which includes paragraphs (c), (d), and (e) not included in the basic clause:

Delivery Tickets—Alternate II (NOV 2014)

(a) The Contractor shall complete delivery tickets in the number of copies required and in the form approved by the Contracting Officer, when it receives the articles to be serviced.

(b) The Contractor shall include one copy of each delivery ticket with its invoice for payment.

(c) Before the Contractor picks up articles for service under this contract, the Contracting Officer will ensure that each bag is weighed and that the weight is identified on the bag.

(d) The Contractor, at time of pickup, shall verify and record the weight on the delivery ticket and shall provide the Contracting Officer, or representative, a copy of the delivery ticket.

(e) At the time of delivery, the Contractor shall record the weight of serviced laundry on the delivery ticket. The Contracting Officer will ensure that this weight is verified at time of delivery.

(End of clause)

Sections it refers to

  • 237.7101 Solicitation provisions and contract clauses.

Sections that refer to it

  • 237.7101 Solicitation provisions and contract clauses.

Related DFARS 252.237 sections

← 252.237-7015 Loss or damage (weight of articles). · 252.237-7017 Individual laundry. →

Rule changes for DFARS Part 252